The Register of Planning Applications · Éire

Sunday 30 August 2026

← Back to search

06/7334

CONDITIONAL

Cork - Cork County Council

Application Timeline

  1. Application received

    19 May 2006

  2. Decision due

    13 Jul 2006

  3. Decision: CONDITIONAL

    13 Jul 2006

  4. Grant issued

    18 Aug 2006

Application Details

Location
Ballydaniel Killeagh
Applicant
N/A
Application Type
PERMISSION
Planning Authority
Cork County Council

Timeline

Registration Date
19 May 2006
Status
APPLICATION FINALISED
Decision
CONDITIONAL
Decision Date
13 July 2006
Grant Date
18 August 2006

Location

Loading map...

Planning Applications Nearby

What the council has granted and refused around this site is the best guide to how a similar application will fare.

0m
05/6239CONDITIONAL30 Aug 2005

Dwellinghouse

Ballydaniel Killeagh

0m
06/7341CONDITIONAL19 May 2006

Dwellinghouse

Ballydaniel Killeagh

24m
05/2553WITHDRAWN20 Apr 2005

Dwellinghouse

Ballydaniel Killeagh

48m
07/12385INCOMPLETED APPLICATION15 Nov 2007

Demolition of cottage and construction of dwellinghouse, installation of wastewater treatment unit and alterations to existing entrance

Ballydaniel Youghal

48m
08/4625CONDITIONAL7 Feb 2008

Demolition of cottage, construction of dwellinghouse, installation of wastewater treament unit and alterations to existing entrance

Ballydaniel Youghal

84m
04/9204REFUSED15 Dec 2004

Dwelling and effluent treatment system

Ballydaniel Killeagh

156m
17/4312CONDITIONAL14 Feb 2017

Construction of a new part single storey, part two storey, detached dwelling and single storey detached garage including a new waste water treatment unit, percolation area, site entrance and all associated site works.

Ballydaniel Youghal Co. Cork

327m
11/4962CONDITIONAL5 May 2011

Construction of livestock underpass along with associated soiled water storage facilities and associated site works

Ballydaniel Lackroe Youghal

410m
26/2133Awaiting Admin Validation13 Aug 2026

We, Perigus Energy Ireland Midco Ltd., intend to apply for permission for development at this site: Knocknagappagh, Barnaviddane, Ballyneague, Ballydaniel, Youghalpark, Ballydaheen and Cornaveigh in County Cork. The development will consist of: • A 323.28 ha solar farm with ca. 210ha of solar panels fixed on ground-mounted frames or precast concrete solar panel footings, gabion basket, or ballasted solutions. • The provision of 54 no. Inverter/transformer stations placed on concrete pads on hardcore sized 120m2. • Site access tracks formed from the provision of 5,135m of new site access tracks and the upgrade of 7,115m of existing access tracks/roads to facilitate access to all onsite infrastructure. • The provision of 1 no. new permanent site entrance for construction and operational access, with the addition of a temporary overrun area from the R634 regional road in the townland of Ballydaniel (site entrance 1). • The permanent realignment of 1 no. existing field access for construction and operational access from the L7806 local road in the townland of Knocknagappagh (site entrance 2). • The provision of 1 no. new permanent site entrance for construction and operational access from the L3803 local road in the townland of Barnaviddane (site entrance 3). • The permanent realignment of 1 no. existing entrance for construction and operational access from the L3808 local road in the townland of Youghalpark (site entrance 4). • The permanent realignment of 1 no. existing entrance for construction and operational access from the L38081 local road in the townland of Cornaveigh (site entrance 5). • The permanent realignment of 2 no. existing field entrances for construction and operational access from the L7828 local road in the townland of Ballyneague (site entrance 6 and 7). • The permanent realignment of 3 no. existing field access for construction and operational access from the L7829 local road in the townland of Ballydaniel (site entrance 8, 9 and 10). • The permanent realignment of 1 no. existing entrance for construction and operational access from the L38032 local road in the townland of Knocknagappagh (site entrance 11). • Underground electrical ducting and cabling, including 3 no. road crossings (local roads L7829, L3803 and L78281) and 3 no. culvert crossings on the L3808. • The provision of 5 no. Temporary construction compounds of which there will be 1 main temporary construction compound (Compound No. 1 located in Ballyneague) ca. 5,200m2 with associated temporary offices, staff facilities parking and security fencing, and 4 no. additional temporary laydown areas of ca. 2,000m2 each located in the townlands of Ballydaniel, Barnaviddane, Cornaveigh and Youghalpark. • Landscaping works encompassing the removal of 395m hedgerow, the planting of 1,400m of new hedgerow and up to 31,000m of linear hedgerow and mosaic hedgerow as required all included in a Landscape Mitigation Plan. • The provision of Biodiversity Enhancement Areas. • The provision of 1 no. temporary spoil storage area. • The construction of a ca. 7,800m2 Battery Energy Storage System (BESS) compound including 56 no. Battery Container Units, 7 no. Inverter Twin Skid Units each consisting of 2 no. Inverters and 1 no. Transformer housed in Modular Enclosures, Communications Building housing switchgear and controls, House Transformer, Back-up Generator and Fuel Supply located in a Bunded Reinforced Concrete Plinth Area, Control Building, Internal Access Tracks, Security Fencing, CCTV, Lighting, Drainage any all other ancillary infrastructure. • All ancillary development such as drainage infrastructure (clean water cut off drains), security fencing, CCTV, weather stations and storage containers for spare parts. The application is requesting a 10-year planning permission for the development of a solar farm with an operational life of 40 years. A separate planning application for the on-site 220kV AIS Substation and loop in Gri

Knocknagappagh, Barnaviddane, Ballyneague, Ballydaniel, Youghalpark, Ballydaheen, Cornaveigh,, Cork, Ireland

410m
25/6876Invalid - Case Closed19 Dec 2025

The application is requesting a 10-year planning permission for the development of a solar farm with an operational life of 40 years. We, Orsted Onshore Ireland Midco Ltd, intend to apply for permission for development at this site: Knocknagappagh, Barnaviddane, Ballyneague, Ballydaniel, Youghalpark, Ballydaheen and Cornaveigh in County Cork. The development will consist of: • A 323.28 ha solar farm with ca. 210 ha of solar panels fixed on ground-mounted frames. • The provision of 54 no. Inverter/transformer stations placed on concrete pads on hardcore sized 120m2. • Site access tracks formed from the provision of 5,135m of new site access tracks and the upgrade of 7,115m of existing access tracks/roads to facilitate access to all onsite infrastructure. • The provision of 1 no. new permanent site entrance for construction and operational access, with the addition of a temporary overrun area from the R634 regional road in the townland of Ballydaniel (site entrance 1). • The permanent realignment of 1 no. existing field access for construction and operational access from the L7806 local road in the townland of Knocknagappagh (site entrance 2). • The provision of 1 no. new permanent site entrance for construction and operational access from the L3803 local road in the townland of Barnaviddane (site entrance 3). • The permanent realignment of 1 no. existing entrance for construction and operational access from the L3808 local road in the townland of Youghalpark (site entrance 4). • The permanent realignment of 1 no. existing entrance for construction and operational access from the L38081 local road in the townland of Cornaveigh (site entrance 5). • The permanent realignment of 2 no. existing field entrances for construction and operational access from the L7828 local road in the townland of Ballyneague (site entrance 6 and 7). • The permanent realignment of 3 no. existing field access for construction and operational access from the L7829 local road in the townland of Ballydaniel (site entrance 8, 9 and 10). • The permanent realignment of 1 no. existing entrance for construction and operational access from the L38032 local road in the townland of Knocknagappagh (site entrance 11). • Underground electrical ducting and cabling, including 3 no. road crossings (local roads L7829, L3803 and L78281) and 3 no. culvert crossings on the L3808. • The provision of 5 no. Temporary construction compounds of which there will be 1 main temporary construction compound (Compound No. 1 located in Ballyneague) ca. 5,200m2 with associated temporary offices, staff facilities parking and security fencing, and 4 no. additional temporary laydown areas of ca. 2,000m2 each located in the townlands of Ballydaniel, Barnaviddane, Cornaveigh and Youghalpark. • Landscaping works encompassing the removal of 395m hedgerow, the planting of 1,400m of new hedgerow and up to 31,000m of linear hedgerow and mosaic hedgerow as required all included in a Landscape Mitigation Plan. • The provision of Biodiversity Enhancement Areas. • The provision of 1 no. temporary spoil storage area. • The construction of a ca. 7,800m2 Battery Energy Storage System (BESS) compound including 56 no. Battery Container Units, 7 no. Inverter Twin Skid Units each consisting of 2 no. Inverters and 1 no. Transformer housed in Modular Enclosures, Communications Building housing switchgear and controls, House Transformer, Back-up Generator and Fuel Supply located in a Bunded Reinforced Concrete Plinth Area, Control Building, Internal Access Tracks, Security Fencing, CCTV, Lighting, Drainage any all other ancillary infrastructure. • All ancillary development such as drainage infrastructure (clean water cut off drains), security fencing, CCTV, weather stations and storage containers for spare parts. The application is requesting a 10-year planning permission for the development of a solar farm with an operational life of 40 years. A separate planning applicatio

Knocknagappagh, Barnaviddane, Ballyneague, Ballydaniel, Youghalpark, Ballydaheen, Cornaveigh,, Cork, Ireland

Planning a project of your own?

Find out in two minutes whether you need planning permission. It's free, and based on the exempted development regulations.

Do I Need Permission?