The Register of Planning Applications · Éire

Monday 31 August 2026

← Back to search

10/6062

CONDITIONAL

Cork - Cork County Council

Proposed Development

Construction of 96sqm extension to proposed new commercial unit (Planning Reg. No. 09/6352) to be utilised as a printing and sign manufacturing facility

View the full application file on the council's planning portal →

Application Timeline

  1. Application received

    17 Aug 2010

  2. Decision: CONDITIONAL

    27 Sept 2010

  3. Decision due

    11 Oct 2010

  4. Grant issued

    29 Oct 2010

Application Details

Location
Laragh Bandon
Applicant
N/A
Application Type
PERMISSION
Planning Authority
Cork County Council

Timeline

Registration Date
17 August 2010
Status
APPLICATION FINALISED
Decision
CONDITIONAL
Decision Date
27 September 2010
Grant Date
29 October 2010

Location

Loading map...

Planning Applications Nearby

What the council has granted and refused around this site is the best guide to how a similar application will fare.

0m
09/6352CONDITIONAL15 Jul 2009

Construction of new commercial unit, car park & associated works to be utilised as a printing & sign manufacturing facility

Laragh Bandon

51m
16/4958CONDITIONAL26 Apr 2016

(A) Construction of extension to existing food producing facility, (B) Construction of extensions to existing storage warehouse facilitating the food producing facility, (C) Construction of link extension between food production building and storage warehouse for use as covered loading/off-loading area, (D) To carry out all associated site works, and revised car parking arrangements including 9 no. additional spaces.

Laragh Industial Estate Laragh Bandon Co. Cork

51m
16/4158INCOMPLETED APPLICATION1 Feb 2016

(A) Construction of extensions to existing food producing facility, (B) construction of extensions to existing storage warehouse facilitating the food production facility, (C) to carry out all associated site works

Laragh Industrial Estate Laragh Bandon Co. Cork

51m
22/4039INCOMPLETED APPLICATION14 Jan 2022

(A) Construction of extension to existing food production facility, (B) Construction of extensions to existing storage warehouse facility, (C) Construction of link extension between food warehouse and food production building for use as covered loading/off-loading area, (D) To carry out all associated site works, and revised car parking arrangements. Extension of Duration to Permission granted under Planning Ref. No. 16/4958

Laragh Industrial Estate Laragh Bandon Co Cork

68m
16/5143INCOMPLETED APPLICATION13 May 2016

Upgrading the existing wastewater infrastructure to provide a pumping station with septicity dosing kiosk within the boundaries of the existing treatment plant. Treatment will no longer occur on site. Existing redundant treatment equipment will be decommissioned and left in suitable and safe condition.

Bandon IDA Laragh Industrail Estate Bandon Co. Cork

68m
16/5851CONDITIONAL25 Jul 2016

Upgrading the existing wastewater infrastructure to provide a pumping station with septicity dosing kiosk within the boundaries of the existing treatment plant. Treatment will no longer occur on site. Existing redundant treatment equipment will be decommissioned and left in suitable and safe condition

Bandon IDA Laragh Industrial Estate Laragh, Bandon Co. Cork

97m
25/6842Grant with Conditions17 Dec 2025

Permission for retention of extensions to existing food production areas and packing/store areas

Laragh Industrial Estate, Laragh, Bandon, Co. Cork.

140m
07/5596CONDITIONAL2 Mar 2007

Construction of electrical substation and retention of extension to window manufacturing factory

Laragh Bandon

140m
04/2973CONDITIONAL4 May 2004

Extend existing factory, offices, yard area, car parking and access road

Laragh Bandon

140m
07/4764INCOMPLETED APPLICATION6 Feb 2007

Construction of electrical substation and retention of extension to existing building

Laragh Bandon

Planning a project of your own?

Find out in two minutes whether you need planning permission. It's free, and based on the exempted development regulations.

Do I Need Permission?