The Register of Planning Applications · Éire

Sunday 30 August 2026

← Back to search

171147

CONDITIONAL

Galway - Galway County Council

Proposed Development

for the construction of a dwelling house, domestic garage and proprietary treatment system. Gross floor space of proposed works 230.6sqm.

View the full application file on the council's planning portal →

Application Timeline

  1. Application received

    28 Jul 2017

  2. Further information requested

    20 Sept 2017

  3. Further information received

    19 Oct 2017

  4. Decision: CONDITIONAL

    13 Nov 2017

  5. Decision due

    15 Nov 2017

  6. Grant issued

    18 Dec 2017

Application Details

Location
Lack ,
Applicant
N/A
Application Type
PERMISSION
Planning Authority
Galway County Council
Site Area
0.42 ha
Floor Area
230 sq m
Residential Units
1

Timeline

Registration Date
28 July 2017
Status
APPLICATION FINALISED
Decision
CONDITIONAL
Decision Date
13 November 2017
Grant Date
18 December 2017
Permission Expires
17 December 2022

Location

Loading map...

Planning Applications Nearby

What the council has granted and refused around this site is the best guide to how a similar application will fare.

199m
2460406CONDITIONAL15 Apr 2024

of the following development on revised site boundaries; 1: Dwelling house, 2: Domestic Garage, 3: Stables, 4: Septic tank and percolation area. Previous planning permissions granted under Planning Reference numbers 71131 and 05/825 refer to the property being sought to retain. Gross floor space of work to be retained: 306.10 sqm (house) & 30.95 sqm (garage) & 47 sqm (stables)

Lack , Milltown , Co.Galway

256m
21372CONDITIONAL15 Mar 2021

for works to existing dwelling house including construction of a new roof with higher ridge and eaves levels, a single-story extension to the side and rear and associated works. Gross floor space of proposed works: 236 sqm. Gross floor space of any demolition: 10 sqm

Milltown ,

301m
19197CONDITIONAL14 Feb 2019

of planning to application ref number 082873 & 13641, for the following changes, on front elevation --changes to window layout, enlarged porch design. On rear elevation-- changes to window layout, including velux windows to attic storage / office space. On side elevations-- additional windows at ground floor level. Also retention of attic conversion to storage and office space. Relocation of site entrance to centre of site and retention and completion for garage with foundation now in place. Gross floor space of proposed works: Garage - 60 sqm. Gross floor space of work to be retained: Attic - 38 sqm

Lack ,

331m
212074CONDITIONAL8 Nov 2021

of garage as built on site, all as per drawing documentation submitted together with all ancillary site works and services. Gross floor of space of work to be retained: 50.83 sqm.

Lack ,

377m
191399CONDITIONAL10 Sept 2019

to alter front extension and construct new rear extension to existing dwelling house and all ancillary works. Gross floor space of proposed works: 73.34 sqm

Milltown ,

398m
2360030CONDITIONAL20 Jan 2023

of 1: the existing dormer window and Velux roof light on the front roof façade of the dwelling house. 2: of the existing wooden garden shed. 3:of the additional ground floor window in the rear elevation of the dwelling house from previous planning application reference numbers 02/3244 and 04/2174 and all ancillary site works.Gross floor space of work to be retained House : 234.2 and Shed: 8.20sqm.

Lack , Milltown , Co. Galway

494m
2660304CONDITIONAL25 Feb 2026

for change of use of shop unit to one bedroom apartment

Milltown , 46 Millbrook , Co. Galway

495m
2561432REFUSED2 Oct 2025

to change of use of shop unit to one bedroom apartment

Milltown , 46 Millbrook , Co. Galway

500m
181432CONDITIONAL11 Oct 2018

for change of use of shop unit to a one bedroom apartment at 48 Millbrook. Gross floor space of proposed works: 52.5 sqm. Gross floor space of work to be retained: 52.5 sqm.

Milltown ,

507m
2461042REFUSED13 Aug 2024

for: 1) Construction of a housing development with a total of 23 no. dwellings in semi-detached, terrace, apartment and duplex configurations, consisting of 2no. 4-bed semi-detached houses, 2no. 3-bed semi-detached houses, 3no. 4-bed terrace houses, 4no. 3-bed terrace houses, 5no. 3-bed duplex units, 4no. 1-bed apartments and 3no. 3-bed apartments. 2) Associated development and works including the extension of granted pedestrian and vehicular access under planning reference 21/617, all hard and soft landscaping, internal roads and footpaths, cycle and car parking, public and private amenities and open spaces, boundary treatments, public lighting, and all other ancillary works above and below ground including connections to water supply, surface water infrastructure, wastewater infrastructure and utilities. Gross floor space of proposed work: 2,364.00 sqm

Milltown , Tuam , Co. Galway

Planning a project of your own?

Find out in two minutes whether you need planning permission. It's free, and based on the exempted development regulations.

Do I Need Permission?