← Back to search

Knocknageeha Townland , Co. Sligo

CONDITIONAL

Planning application 17416

Sligo - Sligo County Council

Proposed Development

for development consisting of the construction of a Forest Road site entrance at

View the full application file on the council's planning portal →

Application Timeline

  1. Application received

    1 Nov 2017

  2. Decision: CONDITIONAL

    20 Dec 2017

  3. Decision due

    4 Jan 2018

  4. Grant issued

    31 Jan 2018

Application Details

Location
Knocknageeha Townland , Co. Sligo
Applicant
N/A
Application Type
PERMISSION
Planning Authority
Sligo County Council
Site Area
0.121 ha

Timeline

Registration Date
1 November 2017
Status
APPLICATION FINALISED
Decision
CONDITIONAL
Decision Date
20 December 2017
Grant Date
31 January 2018
Permission Expires
30 January 2023

Location

Loading map...

Planning Applications Nearby

What the council has granted and refused around this site is the best guide to how a similar application will fare.

905m
2560039CONDITIONAL6 Feb 2025

(a) demolish shed to rear of existing dwelling house, (b) construct single storey extension to rear of existing dwelling house, (c) proposed garage, (d) elevation changes to existing dwelling house, (e) upgrade of existing wastewater treatment system consisting of an effluent treatment unit and soil polishing filter on site, together with all ancillary site works and services on site at

Cartrontaylor , Ballintogher , Co. Sligo

994m
2360214CONDITIONAL17 Aug 2023

A 10 year planning permission for the construction of a: 1. enclosed battery energy storage system compound on a total of up to c. 5.05 hectare site, to include: • 150 battery units set inside storage blocks on concrete support structures containing Heating, ventilation and air conditioning unit (HVAC units); • Transformer and inverter units on concrete support structures; • 1 no. two storey customer 220kV Gas Insulated Substation (GIS) (See Drawing 23553-201 and 23552-202); • 1No. Customer Control Building and 220kV Transformer with associated Switchgear; • 3No. Containing Back-up Generators, Auxiliary Transformers, Switchgear containers, LV and Control Containers; • 1No. Lightning Pole; • 2No. Firewater reservoir ponds with Pumping station and 1No. detention basin with associated drainage systems (as per Drawing 23553-102); • Security gates, 2.6m palisade perimeter security fencing, CCTV and lighting system, landscaping works and all associated ancillary infrastructure; • 4.5m wide Access tracks and site entrance along with upgrade works on the public site access road (c.950m), • Associated electrical cabling and ducting and all other ancillary and miscellaneous site works including site clearance; site access, internal roads and development of areas of hard standing including a maintenance lay-down area. • c.100m of underground cabling ducts and cable to the neighbouring ESB substation. A Natura Impact Statement has been prepared for this proposed development to assess and mitigate any potential ecological impacts. the development will be located at a site in the townland of Ballysumaghan, Fannybrook, Quarry Lane Co. Sligo. The proposed development will have a projected life span of 35 years.

Townland of Ballysumaghan Fannybrook , Quarry Lane Co. Sligo , Ireland

1.0km
22369N/A9 Nov 2022

development consisting of the development of a battery energy storage system. The development will consist of a 10 year planning permission for the construction of a: (1) enclosed battery energy storage system compound on a total of up to c. 1.7 hectare site, to include: 1 no. single storey customer substation and 1 no. TSO substation (c. 182m2), control and switch rooms, up to 174 battery units set inside storage blocks on concrete support structures including heating, ventilation and air conditioning unit (HVAC units), transformer and inverter units. Including access tracks and site entrance along with upgrade works on the public roads (c.800m), associated electrical cabling and ducting, security gates, palisade perimeter security fencing (c. 2.6m height), CCTV system, landscaping works and all associated ancillary infrastructure. The total development area including the area of public road improvements is c.2.3 hectares. A Natura Impact Statement has been prepared for this proposed development to assess and mitigate any potential ecological impacts

Townland of Ballysumaghan , Fannybrook , Quarry Lane

1.0km
2090CONDITIONAL19 Mar 2020

development consisting of a 10 year permission. The development will consist of the development and operation of a 250 to 300 MVA (electrical rating) synchronous condenser. The development which will be located within a site compound of c. 1 hectare and will consist of the following elements: A Condenser and Control Building to house equipment including the synchronous condenser, flywheel, lube oil skid system, air compressor and pumps. Equipment to be located outside the footprint of the Condenser and Control Building but within the fenced compound will include: Cooling equipment (c. 160 sq m., c.3m high); 6 No. modular containers to house electrical and control equipment (total area of c. 195 sqm., c. 5m high); A step-up transformer, auxillary transformer and electrical plant including an external circuit breaker; 1 No. firefighting water tank; A below ground oil interceptor and attenuation tank in lieu of the originally proposed above ground oil interceptor and collection pit. Underground cabling ducts and cable to the neighbouring ESB substation boundary fencing (c. 500m). Palisade security entrance gate, boundary fencing and CCTV; All other ancillary and miscellaneous site works including site clearance; demolition of an existing agricultural shed, site access, internal roads and development of areas of hard standing including a maintenance lay-down area. Following a direction under section 177T(5) of the Planning and Development Act 2000 (as amended), a Natura Impact Statement (NIS) will now accompany the planning application.

Ballysumaghan , Sooey , Co Sligo

1.1km
1859CONDITIONAL5 Mar 2018

for development consisting of the construction of a single storey extension to the rear and side of existing dwelling house and all associated site works

Cartrontaylor , Ballintogher , Co. Sligo

1.1km
1970CONDITIONAL4 Mar 2019

Development consisting of construction of a single storey extension to the rear and side of existing dwelling house with alterations to existing porch and bay window with all associated site works.

Cartrontaylor , Ballintogher , Co. Sligo

1.1km
22312CONDITIONAL21 Sept 2022

development consisting of construction of a domestic shed/garage ancillary to an existing dwelling house

Kiltyclogan , Ballintogher , Co Sligo

1.1km
21378CONDITIONAL20 Sept 2021

Development consisting of retention of an existing domestic garage and all associated ancillary works, parent application No. 03/333.

Kiltycloghan , Ballintogher , Co Sligo

1.2km
2560036CONDITIONAL5 Feb 2025

The development will consist of an enclosed battery energy storage system compound on c. 2.04 hectares. The development will consist of up to 15 no. BESS units comprising of battery cells, modules and racks set within containers stored on concrete bases and ancillary equipment (4 no. BESS containers within each ‘BESS unit’); an individual unit inverter at each BESS unit with some additional ancillary equipment; a Transformer Compound, Control building (including control room and switch room), Interface Kiosk and all associated electrical infrastructure equipment and works; attenuation drainage pond to the northwest of the site; a temporary site compound and all associated works (to be located to the south of the BESS site); a new vehicular entrance to local road and all associated internal access tracks; associated electrical underground cabling and ducting works facilitating the connection of proposed electrical substation to the adjacent Srananagh transmission station; all associated site development, lighting, landscaping, CCTV, security fencing, boundary treatment works above and below ground and all associated ancillary infrastructure.

Townland of Ballysumaghan , Srananagh , Co. Sligo

1.2km
2360312CONDITIONAL14 Nov 2023

Permission for retention of single storey porch extension to front of dwelling house and retention of 2 storey extension to rear of dwelling house built as replacement for previous 2 storey extension to the rear with all associated site works

Woodfield , Ballintogher , Co. Sligo

Planning a project of your own?

Find out in two minutes whether you need planning permission. It's free, and based on the exempted development regulations.

Do I Need Permission?