17552
CONDITIONALClare - Clare County Council
Proposed Development
for development which will consist of the importation of inert excavation spoil comprising natural materials of clay, silt, sand, gravel or stone for the purpose of restoration of a previously extracted area ( 1.08ha) within Ballyquin Pit. The application is accompanied by Environmental Impact Statement ( Environmental Impact Assessment Report)
View the full application file on the council's planning portal →Application Timeline
Application received
19 Jul 2017
Further information requested
11 Sept 2017
Further information received
14 Feb 2018
Decision due
10 Apr 2018
Decision: CONDITIONAL
10 Apr 2018
Grant issued
11 May 2018
Application Details
- Location
- Ballyquin Pit , O'Briensbridge , Co. Clare
- Applicant
- N/A
- Application Type
- PERMISSION
- Planning Authority
- Clare County Council
Timeline
- Registration Date
- 19 July 2017
- Status
- APPLICATION FINALISED
- Decision
- CONDITIONAL
- Decision Date
- 10 April 2018
- Grant Date
- 11 May 2018
- Permission Expires
- 10 May 2023
Location
Planning Applications Nearby
What the council has granted and refused around this site is the best guide to how a similar application will fare.
for development at the existing Ballyquin Quarry. The development will consist of: (i) The extraction of sand from an area of approximately 16.3 hectares within an overall site area of 97.5 hectares; (ii) The infill and restoration of existing and future quarry voids (38 hectares) using inert soil and stone waste (imported inert greenfield and non-greenfield soils and stone, and river dredge spoil) which will be a soil recovery facility and require a waste management licence or soil and stone by-product (i.e. essentially virgin soil or equivalent to virgin soil and stone, and river dredge spoil) which will be notified to the Environmental Protection Agency (EPA) as an Article 27 by-product; (iii) The upgrade of existing quarry infrastructure including site office, weigh bridge, wheelwash, and welfare facilities; (iv) Refuelling area and associated drainage works, comprising 1 No. concrete hardstand area, hydrocarbon interceptor, wetland, inspection chamber and soakaway; (v) 1 No. soil inspection shed (c.875q. m) for the inspection of soil material; (vi) Erection of washplant; (vii) Settlement ponds; (viii) Landscape berms and fencing; (ix) All associated ancillary works. Site access is via the existing entrance off the R466. An Environmental Impact Assessment Report (EIAR) and a Natura Impact Statement (NIS) have been prepared in respect of the proposed development. Should the inert soil, stone and inert dredge spoil materials be deemed to be a waste, then a Waste Management Licence will be required under Part 5 of the Waste Management Act 1996 (as amended) and an application for a Waste Management Licence will be made to the EPA following a grant of planning permission for the proposed development.
Ballyquin More and Woodpark , Ballyquin , Co. Clare
to fill the existing poor quality agricultural land with stone and soil in order to raise the level of the ground, utilising existing site entrance, including all ancillary site works
Ballyquin More Td , O'Briensbridge , Co Clare
to construct a Slatted Shed, Cattle Crush and associated site works
Fahymore , Bridgetown , Co. Clare
the proposed development, on an overall site of 3.58 hectares, will consist of: A co-located Battery Energy Storage System (BESS) Compound with associated internal access tracks; Access to the proposed BESS compound will be from the R466 local road and will consist of the use of an existing quarry entrance in the townland of Leitrim which will be upgraded as permitted as part of the Fahy Beg Wind Farm (under Clare County Council Ref: 23148 & ACP Ref 317227); Installation of grid code compliance equipment to facilitate an under-the-fence connection to the adjacent Fahy Beg 38kV substation. The grid code compliance equipment will include: Backup Generator, Neutral Earthing Resistor (NER), Auxiliary House Transformer, Marshalling Kiosks; 3 no. spare parts shipping containers (measuring 12.2 m (L) x 2.4 m (W) x 2.6 m (H)); and Associated ancillary development. Installation of 32 no. Battery Energy Storage Units comprising metal shipping containers housing batteries (measuring 6 m (L) x 2.4 m (W) and 2.9 m (H) each), and associated ancillary control and ventilation units; Installation of 8 no. Medium Voltage (MV) Inverter Stations comprising metal shipping containers housing the inverter, MV transformer, and an MV-LV room (measuring 6 m (L) x 2.4 m (W) and 2.9 m (H) each); Installation of 1 no. water storage tank (measuring 5.15 m (L) x 4.15 m(W) x 2.58 m (H)); Construction of 250m of new access tracks; Provision of a crane hardstanding area to facilitate lifting operations on site (280m2); Provision of 10 no. car parking spaces (8 no. standard parking spaces, and 2 no. accessible parking spaces); Reprofiling of the existing cut slope embankment with the erection of a gabion basket retaining wall measuring 75m in length and 2.5m in height, and construction of a reinforced fill slope embankment; Underground electrical and communications cabling; Security lighting, CCTV and communications mast; Provision of 150m of Sound reflective barriers; Security fencing and gates; Drainage system including on-site surface water attenuation ponds; Tree felling of 0.19 Ha (1,890m2) to facilitate required clearance for BESS compound, associated earthworks and drainage infrastructure; Removal of 109m of hedgerow to facilitate development of the BESS compound, and replanting of 109m at perimeter locations; and All associated ancillary site development and vegetation clearance works including landscaping and hedgerow reinstatement. The Applicant requests that the development be
Within the townlands of Woodpark TD and Leitrim TD , near Bridgetown , Co. Clare
for development of a wind farm in the townlands of Fahy Beg, Fahy More North, Ballymoloney, Ballyknavin (Ed O'Briensbridge), Balllyquin More, Woodpark and Leitrim, Co Clare together with the development of an underground grid connection cable to the national grid. The underground grid connection is located primarily within the public road within the townlands of Leitrim, Fahy More South, Ballybrack, Aharinaghmore, Tooreen (Ed Cloghera) Aharinaghbeg, Knockdonagh, Roo East, Blackwater, Rosmadda West, Parkroe, Lackyle (Ed Ballyglass) and Castlebank, Co Clare. Temporary accommodation works to facilitate the delivery of wind turbine components to the site will be required in the townland of Ardataggle, Co Clare. The development will consist of: Construction of 8 no. wind turbines with a blade tip height range from 169m to 176.5m, a hub height range from 102.5m to 110m and a rotor diameter range from 131m to 138m; Erection of 1 no. permanent meteorological mast to a height of 100m above ground level; Construction of 1 no. onsite 38kV electrical substation to ESB Networks (ESBN) specifications and associated compound including welfare facilities, electrical infrastructure, parking, wastewater holding tank, rainwater harvesting tank, security fencing and all associated infrastructure, services and site works including landscaping in the townland of Woodpark; Installation of medium voltage electrical and communication cabling underground between the proposed turbines and the proposed on-site substation and associated ancillary works; Construction of turbine foundations and crane pad hardstanding area; Construction of new site tracks and associated drainage infrastructure; Upgrading of existing tracks and associated drainage infrastructure where necessary; Access to the proposed wind farm site will be from the R466 local road and will consist of the use of an existing quarry entrance in the townland of Leitrim which will be upgraded, as well as the creation of 1 no. new permanent site entrance on the Fahymore local road in the townland of Ballyquin More, and the use of 1 no. existing field entrance which will be upgraded, in the townland of Ballymoloney. The site entrances shall be used for both construction and operation of the proposed wind farm; All associated drainage and sediment control; Installation of new watercourse and drain crossings; Reuse and upgrading of existing internal watercourse and drain crossings; 2 no. temporary construction site compounds and
Fahy Beg Fahy More North Ballymoloney Ballyknavin (Ed O'Briensbridge) Ballyquin More , Woodpark Leitrim Fahy More South Ballybrack Aharinaghmore Tooreen , (Ed Cloghers) Aharinaghbeg Knockdonagh Roo East Blackwater Rosmadda West Parkroe Lackyle (Ed
for development of a wind farm in the townlands of Fahy Beg, Fahy More North, Ballymoloney, Ballyknavin (Ed O'Briensbridge), Balllyquin More, Woodpark and Leitrim, Co Clare together with the development of an underground grid connection cable to the national grid. The underground grid connection is located primarily within the public road within the townlands of Leitrim, Fahy More South, Ballybrack, Aharinaghmore, Tooreen (Ed Cloghera) Aharinaghbeg, Knockdonagh, Roo East, Blackwater, Rosmadda West, Parkroe, Lackyle (Ed Ballyglass) and Castlebank, Co Clare. Temporary accommodation works to facilitate the delivery of wind turbine components to the site will be required in the townland of Ardataggle, Co Clare. The development will consist of: Construction of 8 no. wind turbines with a blade tip height range from 169m to 176.5m, a hub height range from 102.5m to 110m and a rotor diameter range from 131m to 138m; Erection of 1 no. permanent meteorological mast to a height of 100m above ground level; Construction of 1 no. onsite 38kV electrical substation to ESB Networks (ESBN) specifications and associated compound including Welfare facilities, Electrical infrastructure, Parking, Wastewater holding tank, Rainwater harvesting tank, Security fencing and all associated infrastructure, services and site works including landscaping in the townland of Woodpark; Installation of medium voltage electrical and communication cabling underground between the proposed turbines and the proposed on-site substation and associated ancillary works; Construction of turbine foundations and crane pad hardstanding area; Construction of new site tracks and associated drainage infrastructure; Upgrading of existing tracks and associated drainage infrastructure where necessary; Access to the proposed wind farm site will be from the R466 local road and will consist of the use of an existing quarry entrance in the townland of Leitrim which will be upgraded, as well as the creation of 1 no. new permanent site entrance on the Fahymore local road in the townland of Ballyquin More, and the use of 1 no. existing field entrance which will be upgraded, in the townland of Ballymoloney. The site entrances shall be used for both construction and operation of the proposed wind farm; All associated drainage and sediment control; Installation of new watercourse and drain crossings; Reuse and upgrading of existing internal watercourse and drain crossings; 2 no. temporary construction site compounds and
Fahy Beg Fahy More North Ballymoloney Ballyknavin (Ed O'Briensbridge) Ballyquin More , Woodpark Leitrim Fahy More South Ballybrack Aharinaghmore Tooreen , (Ed Cloghera) Aharinaghbeg Knockdonagh Roo East Blackwater Rosmadda West Parkroe Lackyle (Ed
the development will consist of construction of one new single storey dwelling house with wastewater treatment system, bored well, garage, entrance from public road and all associated works
Leitrim , O'Briensbridge , Co Clare
to RETAIN alterations to elevations and roof of existing house together with all associated site works
Ballyquin More , Kilbane , Broadford Co Clare
to construct an Agricultural Shed and associated site works
Springmount , Kilmore , Co. Clare
for the construction of a new single storey dwelling, septic tank, percolation area, entrance and all associated site works
Faheymore North , Bridgetown , Co. Clare
Planning a project of your own?
Find out in two minutes whether you need planning permission. It's free, and based on the exempted development regulations.
Do I Need Permission?