17554
CONDITIONALClare - Clare County Council
Proposed Development
to construct an extension incorporating a sports/general purpose hall to the existing clubhouse in lieu of previous extension granted under Planning permission reference No. P14-74
View the full application file on the council's planning portal →Application Timeline
Application received
19 Jul 2017
Decision: CONDITIONAL
24 Aug 2017
Decision due
12 Sept 2017
Grant issued
24 Sept 2017
Application Details
- Location
- Ballyguiry , Labasheeda , Co. Clare
- Applicant
- N/A
- Application Type
- PERMISSION
- Planning Authority
- Clare County Council
Timeline
- Registration Date
- 19 July 2017
- Status
- APPLICATION FINALISED
- Decision
- CONDITIONAL
- Decision Date
- 24 August 2017
- Grant Date
- 24 September 2017
- Permission Expires
- 22 November 2019
Location
Planning Applications Nearby
What the council has granted and refused around this site is the best guide to how a similar application will fare.
for a change of design of the extension to the clubhouse previously granted under Planning Permission Reference no. P14-74
Ballyguiry , Labasheeda , Co Clare
for the construction of an extension to the rear and front of an existing dwelling house along with alterations to the existing house and ancillary works
Ballyartney , Labasheeda , Co Clare
for development which will consist of a 10 year planning permission for the construction of a: 1. enclosed battery energy storage system compound on a total of up to c.7.8-hectare site, to include: 1 no. TSO electrical substation building and 1 no. single storey customer substation, control and switch rooms, up to 19 battery storage block on concrete support structures including heating, ventilation and air conditioning unit (HVAC units) transformer and inverter units. Including access tracks and site entrance, associated electrical cabling and ducting, security gates, perimeter security fencing, CCTV system, landscaping works and all associated ancillary infrastructure
Ballygerry West , Co Clare
to apply for a 10 year planning permission for development on a c. 1 ha at Ballygeery West, Co Clare. The development will consist of the development and operation of a 250 to 500 MVA (electrical rating) synchronous condenser. The development which will be located within a site compound of c. 1 hectare behind the existing ESB substation for the purpose of stabilising the electricity grid will consist of the following elements; Compound building, within which the synchronous condenser generator and flywheel will be located (540m2c.7m high), Synchronous condenser, with a 250-500 MVA (electrical rating); Cooling equipment (c.160sqm., c. 3m high); 6 No. modular containers to house electrical and Control equipment (total area of c. 195sqm., c. 5m high), A generator step-up transformer, auxiliary transformer and electrical plant including an external circuit breaker (c.8m high); 1 No. firefighting water tank and pump, An above-ground oil separator and collection pit, Boundary fencing (c.3m high), palisade security entrance gate and CCTV, c.100m of underground cabling ducts and cable to the neighbouring ESB substation, All other ancillary and miscellaneous site works including site clearance; site access, internal roads and development of area of hard standing including a maintenance lay-down area. Planning PERMISSION is being sought for a duration of 10 years
Ballygeery West , Co Clare
for development which will consist of: 1 No. enclosed battery energy storage system compound on a total of c. 6.2 hectare site, to include: 1 no. 220kv GIS electrical substation building and 1 no. single storey customer substation building, control and switch room, 220kv transformer and four no. auxiliary transformers, up to 192 battery storage blocks on concrete support structures including heating, ventilation and air conditioning unit (HVAC units), 16 transformer and 32 inverter units. Including access tracks and site entrance, associated electrical cabling and ducting, security gates, perimeter security fencing, CCTV system, landscaping works and all associated ancillary infrastructure. The proposed development will have a projected life span of 35 years. A Natura Impact Statement has been prepared to accompany this application
Ballygeery West , Co. Clare
to construct a slatted house incorporating a feeding passage and calving area along with all other necessary ancillary and associated works
Ballygeery East , Labasheeda , Co. Clare
to alter and extend the dwelling with a series of single-storey extensions to the side and front, a two-storey extension to the rear, and all associated site works, servicing, and landscaping
Cloonkerry West , Labasheeda , Co. Clare
to extend and refurbish an existing house along with all associated works
Cullenagh , Labasheeda , Co. Clare
to demolish existing side extension and construct a replacement side extension to the existing dwelling house along with all associated site works
Cullenagh , Labasheeda , Co Clare
to RETAIN alterations and extensions carried out to dwelling house, to RETAIN construction of a private garage, PERMISSION to refurbish, reconstruct part of and extend existing dwelling house, to use the adjoining building as a workshop for home-based economic activity in accordance with CDP 6.23 of the Clare County Development Plan 2017-2023 and to upgrade the existing sewerage treatment facilities along with all associated works
Cullenagh , Labasheeda , Co. Clare
Planning a project of your own?
Find out in two minutes whether you need planning permission. It's free, and based on the exempted development regulations.
Do I Need Permission?