The Register of Planning Applications · Éire

Monday 31 August 2026

← Back to search

17555

CONDITIONAL

Clare - Clare County Council

Proposed Development

to change the design of the dwelling house previously granted under planning permission No. P11-354, and extended in duration by permission No. P16-282, with all associated site works

View the full application file on the council's planning portal →

Application Timeline

  1. Application received

    20 Jul 2017

  2. Decision due

    13 Sept 2017

  3. Decision: CONDITIONAL

    13 Sept 2017

  4. Grant issued

    14 Oct 2017

Application Details

Location
Coolready , Bodyke , Co. Clare
Applicant
N/A
Application Type
PERMISSION
Planning Authority
Clare County Council
Floor Area
247.04 sq m
Residential Units
1

Timeline

Registration Date
20 July 2017
Status
APPLICATION FINALISED
Decision
CONDITIONAL
Decision Date
13 September 2017
Grant Date
14 October 2017
Permission Expires
10 August 2021

Location

Loading map...

Planning Applications Nearby

What the council has granted and refused around this site is the best guide to how a similar application will fare.

577m
20168CONDITIONAL9 Mar 2020

to alter and extend dwelling house and associated site works.

9 Beechwood Lawn , Bodyke , Co. Clare

720m
258000UNCONDITIONAL31 Jan 2025

to carry out the following development: a) Construct a public car park on green field site in the village centre of Bodyke to include b) Provision of vehicular and pedestrian access from the R352 roadway via alterations to existing access. c) Provision of additional pedestrian access to the car park from the adjacent Bodyke Community Park. d) Provision of cycle parking and repair station. e) Installation of public lighting. f) Connection to existing surface water drainage system, via a proposed rain water garden. g) All ancillary site works. In accordance with the Habitats Directive, Appropriate Assessment Screening has been carried out on the project and the screening report accompanies the application. A preliminary examination of the nature, size and location of the development has been carried out pursuant to Article 120(1) of the Planning & Development Regulations, 2000 (as amended) and it has been concluded that there is no real likelihood of significant effects on the environment arising from the proposed deveopment and, accordingly an Environmnetal Impact Assessment is not required

Bodyke Village Centre , Coolready , Bodyke Co Clare

851m
23427CONDITIONAL31 Jul 2023

of the conversion of old stables to a guest cottage, connection to existing services and all associated site works. The stables area to the rear of Fort Edward House which is a protected structure

Fort Edward , Coolreagh , Bodyke Co Clare

1.2km
25325CONDITIONAL15 Oct 2025

to alter and extend dwelling house and associated site works

Coolready , Bodyke , Co. Clare

1.2km
211200REFUSED12 Nov 2021

to erect a dwelling house, garage, entrance, effluent treatment system and soil polishing filter and associated site works

Lisbarren , Bodyke , Co Clare

1.3km
2646CONDITIONAL20 Feb 2026

of alterations and extension to derelict cottage, including raising of cottage ridge height, provision of ground and first floor extension, enlarged porch structure to front elevation, removal of front boundary ditch and provision of vehicular entrance. PERMISSION is sought to complete building work to cottage and extension, complete front boundary with appropriate hedge planting and stone wall splayed site entrance, installation of waste water treatment system with percolation area and associated site works

Drummod , Bodyke , Co. Clare

1.3km
1735CONDITIONAL24 Jan 2017

to construct a house, garage and a waste water treatment system along with all ancillary site works

Coolreagh , Bodyke , Co. Clare

1.3km
18860CONDITIONAL26 Oct 2018

to relocate the entrance to house including the drainage pipe under the entrance and all associated site works

Coolreagh , Bodyke , Co. Clare

1.3km
18798REFUSED12 Oct 2018

to construct phase one of East Clare Golf Club redevelopment scheme being: 14 no. 2 bedroom and 14 number 4 bedroom time share holiday homes together with access road, modified existing site road access, drainage works, connection to and upgrading existing sewage facility, boundary treatments, tree and scrub removal, tree planting, landscaping and ancillary works. The proposed units will be utilised as an extension of the existing East Clare Golf Village

Coolreagh , Bodyke , Co. Clare

1.6km
2460206CONDITIONAL13 May 2024

of bay window and other minor changes to the elevations of house, garage/shed for private domestic use and existing entrance and driveway as constructed and all associated site works

Coolreagh Beg , Bodyke , Co. Clare