17600440

CONDITIONAL

Tipperary - Tipperary County Council

Proposed Development

the development will consist of a Phase III mushroom substrate (compost) production facility and will involve the construction of an administration building (296.16 sq. m), storage building (8444.04 sq. m), bunker building (9967.59 sq. m), tunnel building (10628.75 sq. m), woodchip bio-filter, wheelwash, weighbridge, 6 no. water storage tanks, 2 no. fuel storage tanks, well, wastewater treatment system, hardstanding areas, internal access roads, parking facilities, boundary fencing, landscaping, and all ancillary works. An Environmental Impact Statement (EIS) will be submitted with the planning application. The application relates to development which comprises or is for the purposes of an activity requiring an Integrated Pollution Prevention and Control Licence or a Waste Licence

View the full application file on the council's planning portal →

Application Timeline

  1. Application received

    26 Apr 2017

  2. Further information requested

    19 Jun 2017

  3. Further information received

    20 Nov 2017

  4. Decision due

    23 Jan 2018

  5. Decision: CONDITIONAL

    23 Jan 2018

  6. Grant issued

    27 Feb 2018

Application Details

Location
Killoran , Moyne , Thurles
Applicant
N/A
Application Type
PERMISSION
Planning Authority
Tipperary County Council
Site Area
8.88 ha

Timeline

Registration Date
26 April 2017
Status
APPLICATION FINALISED
Decision
CONDITIONAL
Decision Date
23 January 2018
Grant Date
27 February 2018
Permission Expires
26 February 2023

Location

Loading map...

Planning Applications Nearby

What the council has granted and refused around this site is the best guide to how a similar application will fare.

132m
2460936CONDITIONAL2 Nov 2024

construction of an anaerobic digestion plant comprising: 4 no. primary digester tanks (each measuring c. 7.6 m in height); 3 no. secondary digester tanks (each measuring c. 14.5 m in height); 4 no. feed hoppers; 4 no. technical rooms (ranging in size from c. 35 sq m to c. 95 sq m GFA); 2 no. biogas conditioning units; process, storage and buffer tanks (comprising: 1 no. buffer digestate storage tank (c. 7.5 m in height), 1 no. suspension buffer tank (c. 8 m in height), 1 no. process area runoff storage tank (c. 4.5 m in height); 1 no. buffer digestate process tank (c. 4.5 m in height), 1 no. treated digestate liquids recycle storage tank (c. 4.5 m in height); 1 no. roofed liquids feed-mix tank (c. 3 m in height)); these components will be located within a containment bund constructed c. 3 m below ground level. The proposed development will also consist of: feedstock storage (comprising 3 no. storage clamps (c. 1,050 sq m in area each) and 2 no. storage sheds (c. 500 sq m GFA each)); a biomethane upgrading plant (including natural gas compression unit); a biomethane loading facility (comprising 4 no. loading bays with associated gates and safety features measuring c. 490 sq m in area); a biomass boiler with its associated pellet storage silo (c. 12.5 m in height); Combined Heat and Power (CHP) plant and associated heat exchanger; a single storey bio-based fertiliser processing and storage unit (c. 3,890 sq m GFA) (including digestate dewatering plant, fertiliser pasteurisation plant and bio-based fertiliser loading facilities); a single storey office building (c. 105 sq m GFA) (including offices, meeting room, control room, laboratory, welfare facilities, storeroom and a first-aid facility); bin storage; 9 no. car parking spaces (including 5 no. standard parking spaces, 2 no. electric vehicle (EV) spaces and 1 no. accessible car parking space); electric vehicle (EV) charging infrastructure; 10 no. bicycle parking spaces; vehicular, cyclist and pedestrian access / egress and associated circulation routes; 2 no. weighbridges; a vehicle steam wash area; fuel storage tank and associated bund; an emergency flare (c. 7.6 m in height); a process area runoff lagoon; an attenuation pond; an ESB sub-station; boundary treatments [including gates, piers and fencing]; site lighting; all hard and soft landscaping; provision of sustainable urban drainage systems (SUDS); and all other associated site excavation, infrastructural and all other associated site excavation

Former Lisheen Mine Site , Killoran Moyne , Thurles Co. Tipperary

283m
211171CONDITIONAL10 Aug 2021

1) Demolition of the existing loading bay canopy 2) Change of use from maintenance depot to an agri-food sector Research and Development Unit for light indutrial use with ancillary office space 3) Extension of the existing first floor accomodation by 169 sqm. 4) Construction of an external stair to the rear, additional windows to the front and rear elevations with an external perforated printed mesh screen fixed to the front and south gable elevation, canopy over the front entrance door and an array of PV Panels fixed to the roof 5) Landscape works including a waste water treatment plant and car parking with 4 no. electric vehicle chargers

Former Maintenance Depot Former Lisheen Mine , Kiloran , Moyne Thurles Co. Tipperary

397m
2460875N/A14 Oct 2024

extensions & alterations to existing farmhouse, permission for new septic tank & percolation area and a new vehicular entrance and to include all associated site works

Killoran , Templetuohy Thurles , Co. Tipperary

401m
2460918CONDITIONAL25 Oct 2024

extensions and alterations to existing farmhouse, relevant demolition works to structures attached to house to facilitate the extension and renovation of the house, permission for new septic tank and percolation area, a new vehicular entrance and to include all associated site works

Killoran , Templetuohy Thurles , Co. Tipperary

401m
2561132CONDITIONAL9 Nov 2025

change of design and subsequent boundary adjustment to granted planning permission Ref: 2460918

Killoran , Templetuohy Thurles , Co.Tipperary

402m
20825CONDITIONAL28 Jul 2020

works within the boundary of the existing Lisheen 110 kV Substation, the proposed works will comprise: replacement and improvement works to an existing electrical transformer bund; construction of two new concrete plinths for associated electrical infrastructure; installation of electrical infrastructure; and underground cable connection from the electrical infrastructure to the existing substation control building. The application is accompanied by a Planning and Environmental Report and Appropriate Assessment Screening Report

Killoran , Templetuohy , Co Tipperary

545m
2360281CONDITIONAL28 Apr 2023

development consisting of Workshop Building (1242m2), Truck Washout Building (64m2), commercial yard area, new boundary fence and entrance gates, an on-site Wastewater Treatment System and associated polishing filter bed percolation area, attenuation tank, bored well & water storage tank, rainwater harvesting tank, emergency storage tank, solar panels to roof of existing building and all associated siteworks - application is accompanied by an NIS

Killoran , Thurles , Co. Tipperary

627m
18601296CONDITIONAL26 Oct 2018

a biorefinery facility comprising of a process building with processing areas, plant rooms, stores, personnel & administrative areas; external bunded process & storage areas; vessels and tanks; CHP plant; an effluent & water treatment plant which includes bunded tanks & a building;sewage treatment plant; water storage tanks & site development works including demolition of an existing electrical building, roads, paved areas, parking areas, drains and services, bore well, lighting, fire water retention tank, attenuation pond, site fencing, alterations to the discharge pipeline from the sewage treatment plant, weighbridges & weighbridge office, connection to an existing outfall pipeline and landscaping works. The application is accompanied by an Environmental Impact Assessment Report. This application relates to development which comprises or is for the purpose of an activity requiring an Integrated Pollution Prevention and Control Licence

Killoran , Moyne , Thurles

678m
18601265N/A22 Oct 2018

a biorefinery facility comprising of a process building with processing areas, plant rooms, stores, personnel & administrative areas; external bunded process & storage areas; vessels and tanks; CHP plant; an effluent & water treatment plant which includes bunded tanks & a building;sewage treatment plant; water storage tanks & site development works including demolition of an existing electrical building, roads, paved areas, parking areas, drains and services, bore well, lighting, fire water retention tank, attenuation pond, site fencing, alterations to the discharge pipeline from the sewage treatment plant, weighbridges & weighbridge office, connection to an existing outfall pipeline and landscaping works. The application is accompanied by an Environmental Impact Assessment Report. This application relates to development which comprises or is for the purpose of an activity requiring an Integrated Pollution Prevention and Control Licence

Killoran , Moyne , Thurles

750m
20129CONDITIONAL13 Feb 2020

a 10 year planning permission for modifications to Condition No. 1 of previously granted planning permission Ref. No. 18/601296. The modifications comprise an outfall drain and associated pumping station and monitoring chambers to discharge surface water and treated waste water from the Biorefinery site through the townlands of Cooleeny and Derryfadda to the Drish River; a water supply pumphouse and associated site works including access road and security fencing in the townland of Derryville and a water supply pipeline from the pumphouse to the Biorefinery facility site. A Natura Impact Statement (NIS) will accompany the application. This application relates to development which comprises or is for the purpose of an activity requiring an Industrial Emissions Licence.

Cooleeny Derryfadda Derryville and Killoran , Moyne , Thurles