17953
CONDITIONALClare - Clare County Council
Proposed Development
for the proposed contruction of a new dwelling house, garage, installation of wastewater treatment system and ancillary site works
View the full application file on the council's planning portal →Application Timeline
Application received
8 Dec 2017
Further information requested
8 Feb 2018
Further information received
13 Mar 2018
Decision: CONDITIONAL
28 Mar 2018
Decision due
9 Apr 2018
Grant issued
28 Apr 2018
Application Details
- Location
- Cappaghmore , Barefield , Co Clare
- Applicant
- N/A
- Application Type
- OUTLINE PERMISSION
- Planning Authority
- Clare County Council
Timeline
- Registration Date
- 8 December 2017
- Status
- APPLICATION FINALISED
- Decision
- CONDITIONAL
- Decision Date
- 28 March 2018
- Grant Date
- 28 April 2018
- Permission Expires
- 27 April 2021
Location
Planning Applications Nearby
What the council has granted and refused around this site is the best guide to how a similar application will fare.
on grant of outline permission (Ref. No. P17/953) for the proposed construction of a new dwelling house, garage, installation of a wastewater treatment system and ancillary site works
Cappaghmore , Barefield , Co Clare
of the extension and alterations to the dwellinghouse, the storage shed on site and all associated and ancillary site works
Cappaghmore , Barefield , Ennis Co. Clare V95 THF2
for development, the development consists of the construction of a slatted cubicle unit and associated site works
Cappagh More , Barefield , Co Clare
the development consists of the construction of a slatted cubicle unit and associated site works
Cappagh More , Barefield , Co Clare
for development which will consist of the construction of a slatted unit onto existing cubicle house and associated site works
Cappagh More , Barefield , Co. Clare
for development, the development consist of the construction of a dairy with waste water treatment system with percolation area and associated site works
Cappagh More , Barefield , Co Clare
for the construction of a slatted unit and loose shed with associated site works
Cappamore , Barefield , Co Clare
for the construction of 2 no. single storey extensions to the front and rear of the existing dwelling house, including minor front and side elevation alterations, the construction of a garage and all associated site works
Drumgranagh , Barefield , Ennis
for the construction of 2 no. single storey extensions to the front and rear of existing dwelling house, including minor front and side elevation alterations, the construction of a garage and all associated site works
Drumgranagh , Barefield , Co. Clare
- a permission of 10 years in duration is sought. The application site has a total of c. 60 hectares with a nett area for development of c. 45 hectares, and is bound to the south by R352 (Tulla Road), to the east and the north by agriculture land, to the west by the M18. The development will consist of: the demolition of an existing single storey with pitched roof farm dwelling house together with 8 No. farm outbuildings on the overall site. The construction of 6 No. two storey data centre buildings with three storey plant/office levels and associated ancillary development that will have a combined gross floor area of 118,740 sqm. These data halls are maximum 19m high and will consist of the data halls and air handling units and offices and ancillary plant and support. Each of the six data centre buildings will include data halls, associated electrical and mechanical plant rooms, loading bays, maintenance and storage spaces, office administration areas, pump rooms, water storage tanks, and plant, as well as backup (standby) generators (11 No. per building) for emergency use only situated along one elevation of each building. The standby diesel generators will have associated 8 m high flues. Each generator will also include local diesel storage tanks with a single refuelling area to serve the proposed emergency generators. A gas powered energy centre and Above Ground Installation (AGI)4,674 sqm in size . The energy centre will primarily comprise 18 no. lean-burn natural gas engines, 2 No. pump rooms, and fuel storage compound. Each generator will have its own flue of 25m height. The energy centre and buildings within the compound will be 12 m high, single storey with mezzanine level. The buildings will house ancillary office, welfare facilities and associated parking. A two storey Vertical Farm Building. The vertical farm will be c. 2,430 sqm and 12m high. It will comprise c. service area of 1,444 sqm, handling area of 844 sqm and ancillary areas. Please see newspaper notice for full development description
Tooreen Cahernalough Knockanean , Ballymacahill Muckinish and Rosslevan , Tulla Road Ennis Co Clare
Planning a project of your own?
Find out in two minutes whether you need planning permission. It's free, and based on the exempted development regulations.
Do I Need Permission?