18117
CONDITIONALKilkenny - Kilkenny County Council
Proposed Development
to construct a silage pit and a slatted cattle walkway and all associated site works at
View the full application file on the council's planning portal →Application Timeline
Application received
21 Feb 2018
Further information requested
13 Apr 2018
Further information received
24 Apr 2018
Decision: CONDITIONAL
9 May 2018
Decision due
21 May 2018
Grant issued
11 Jun 2018
Application Details
- Location
- Courtnabooly West , Callan , Co. Kilkenny
- Applicant
- N/A
- Application Type
- PERMISSION
- Planning Authority
- Kilkenny County Council
- Site Area
- 2 ha
- Floor Area
- 426 sq m
- Residential Units
- 1
Timeline
- Registration Date
- 21 February 2018
- Status
- APPLICATION FINALISED
- Decision
- CONDITIONAL
- Decision Date
- 9 May 2018
- Grant Date
- 11 June 2018
- Permission Expires
- 10 June 2023
Location
Planning Applications Nearby
What the council has granted and refused around this site is the best guide to how a similar application will fare.
to construct a cattle underpass and all associated site works under the public road
Courtnabooly , West Callan , Co. Kilkenny
for construction of 2 no. livestock underpasses and effluent holding tanks and all associated siteworks
Courtnabooly West & , Courtnabooly East , Callan
for construction of a livestock underpass and effluent holding tank and all associated siteworks
Courtnabooly East , Callan , Co Kilkenny
for single storey kitchen extension to side of existing house and associated site works at
Coolaghmore , Callan , Co Kilkenny
to construct a bungalow, garage, entrance, wastewater treatment system with soil polishing filter, borehole, soakpits and all other associated site works
Coolaghmore , Callan , Co. Kilkenny
for proposed development which will consist of a 20kV grid connection from the consented Ballytobin Solar Farm to the existing 38kV ESB substation south of Callan Co.Kilkenny. The grid connection is 3.6km long. The grid connection line will consist of c.496m of overhead line and c.3.1km of underground cable. The cable ducting will be located in the existing road verge and in the road itself with short section of c.25m on the solar farm to connect to the overhead line. The applicaiton is accompanied by a Natura Impact Statement (NIS). An appropiate period of 10 years (ie.duration of the planning permission to construct the development) is sought, with an operational life of up to 30 years after the date of commissioning
Ballytobin , Bolton , Callan
to construct of a new dwelling, with associated new entrance, on-site wastewater treatment & disposal system, group water scheme connection, and all associated site works
Courtnabooly West , Callan , Co. Kilkenny
for the construction of a new dwelling with garage, associated new entrance, on-site wastewater treatment & disposal system, group water scheme connection, and all associated site works
Courtnabooly West , Callan , Co. Kilkenny
retention of conversion of garage attached to dwelling to habitable living space and all associated site works
Courtnabooly West , Callan , Co Kilkenny
for 1) a domestic garage/storage shed and 2) a storage shed consisting of boiler house, fuel store and store and all associated site works
Coolaghmore , Callan , Co. Kilkenny
Planning a project of your own?
Find out in two minutes whether you need planning permission. It's free, and based on the exempted development regulations.
Do I Need Permission?