Proposed Development

for a ten-year planning permission for the development of an up to 100MW Battery Energy Storage Facility that will provide energy services to the national grid and will be delivered in 4 no. phases. The development will consist of the construction and operation of up to 34 metal containers to store up to a project total of up to 100MW in sealed battery cells each with entrances, fire suppression systems, heating, ventilation and air conditioning systems. The proposed development includes for inverters, control systems, other electrical components, security lighting and ancillary infrastructure and all associated works including security fencing and ancillary grid infrastructure. Gross floor space of proposed works: 2186.6 sqm

View the full application file on the council's planning portal →

Application Timeline

  1. Application received

    21 Dec 2018

  2. Further information requested

    21 Feb 2019

  3. Further information received

    28 May 2019

  4. Decision: CONDITIONAL

    21 Jun 2019

  5. Decision due

    24 Jun 2019

  6. Appeal submitted

    16 Jul 2019

  7. Appeal decided: CONDITIONAL

    12 Nov 2019

Application Details

Location
Barrettspark ,
Applicant
N/A
Application Type
PERMISSION
Planning Authority
Galway County Council
Site Area
1.61 ha

Timeline

Registration Date
21 December 2018
Status
APPLICATION FINALISED
Decision
CONDITIONAL
Decision Date
21 June 2019
Permission Expires
11 November 2024

An Coimisiún Pleanála Appeal

Appeal Reference
ABP-304922-19
Decision
CONDITIONAL
Submitted
16 July 2019
Decided
12 November 2019

Location

Loading map...

Planning Applications Nearby

What the council has granted and refused around this site is the best guide to how a similar application will fare.

135m
19325CONDITIONAL7 Mar 2019

to refill an existing disused quarry with inert material

Barretts Park ,

258m
221006CONDITIONAL26 Aug 2022

for the development and operation of a 150 to 500 MVA (electrical rating) synchronous condenser. The development which will be located within a site compound of c. 1 hectare east of the existing ESB substation for the purpose of stabilizing the electricity grid will consist of the following elements: The development and operation of a 150 to 500 MVA (electrical rating) synchronous condenser. Compound building housing synchronous condenser generator and flywheel (540 sqm c. 12m high); 5 No. modular containers to house electrical and control equipment (total area of c. 195 sqm, c. 5m high), a generator step-up transformer, auxiliary transformer and electrical plant including and external circuit breaker (c. 8m); 1 No. firefighting water tank and pump, boundary fencing (c. 3m high) and CCTV, c. 50m of underground cabling ducts and cable to the neighbouring ESB Substation, all other ancillary site works including access roads and upgrade of existing local access road. Planning permission is being sought for a duration of 10 years. Gross floor space of proposed works: 540 sqm

Barrettspark ,

299m
22303REFUSED7 Mar 2022

for a development consisting of the development and operation of a 150 to 500 MVA (electrical rating) synchronous condenser. The development which will be located within a site compound of c. 1 hectare east of the existing ESB substation for the purpose of stabilizing the electricity grid will consist of the following elements: The development and operation of a 150 to 500 MVA (electrical rating) synchronous condenser. Compound building housing synchronous condenser generator and flywheel (540sqm c. 10m high). Cooling equipment (c. 160sqm, c. 3m high); 5 no. modular containers to house electrical and control equipment (total area of c. 195sqm, c. 5m high). A generator step-up transformer, auxiliary transformer and electrical plant including and external circuit breaker (c. 8m); 1 no. firefighting water tank and pump, boundary fencing (c. 3m high) and CCTV, c. 50m of underground cabling ducts and cable to the neighbouring ESB Substation, all other ancillary site works including access roads. Planning permission is being sought for a duration of 10 years. Gross floor space of proposed works: 540sqm.

Barrettspark ,

412m
24260CONDITIONAL6 Sept 2024

for the installation of solar panels over the roof of an existing telecommunications cabin on a steel frame (covering an area of 60 sqm to maximum height of 5 meters above ground level) works to consist of all ancillary development works, including steel uprights

Barrettspark , ESB Telecoms Ltd Compound , Cashla 220k V Substation

451m
20499CONDITIONAL21 Apr 2020

for a twenty year planning permission for the continued operation of the existing quarry and all associated uses and activities, as well as for an extension to the existing quarry extraction area and all associated site works including landscaping arrangements. The proposed quarry extraction area extension is on lands to the north, south and east of the existing quarry and the additional extraction area amounts to approximately 6.7 hectares. The application is accompanied by an Environmental Impact Assessment Report and a Natura Impact Statement.

Barrettspark ,

451m
21859UNCONDITIONAL20 May 2021

to continue quarrying with associated roads and ancillary services and to operate a concrete batching plant and a bitumen batching plant within the quarry. The 13 hectare extraction area and the 27.5 hectare site boundary remains identical to that outlined in the existing quarry planning permission for Coshla Quarries Ltd (P06/4125). An Environment Impact Statement (EIS) will be submitted with the application

Barretts Park ,

451m
2560220CONDITIONAL4 Mar 2025

for continued use of the existing quarry to the permitted depth of minus 5 mOD, including drill-ing, blasting, crushing, processing, stockpiling of materials, associated roads and ancillary services (granted under Planning Ref. File No.: 09/1958 and ABP Ref.: PL07.235821); Continued use of open storage areas; Continued use of existing permitted concrete manufacturing facility (granted under Planning Ref. File No. 09230 and 19/517: ABP-304769-19); Continued use of the existing office (granted under Planning Ref. File No.: 09/1958 and ABP Ref.: PL07.235821); Continued use of the existing maintenance shed (granted under Planning Ref. File No. 09610); Continued use of the existing water management system (including settlement lagoons), weighbridge and wheelwash; Lateral extension of the existing permitted quarry area over a previously permitted extraction area (granted under Planning Ref. File No. 06/4125) of c.4.6 ha. area to a final floor level of minus 5 mOD. The total quarry extraction area will be c. 13 Ha.; Restoration of the application area to natural habitat after uses following completion of ex-traction. The proposed development is within an overall application area of c. 27.5 hectares and is for a total period of 22 years (comprising an operational period of 20 years followed by 2 years for restoration). This application is accompanied by an Environmental Impact Assessment Report (EIAR)

Barrettspark , Athenry , Co. Galway

509m
201221REFUSED28 Aug 2020

and completion of extension to Industrial Premises. Gross floor space of work to be retained: 3980.00 sqm

Cashla ,

521m
21829REFUSED17 May 2021

of extensions and alterations to factory premises and site and entrances at Cashla, Athenry to include the following: - A. Machine Shop and Canteen to South Elevation. B. Switch Room & Compressor Room to south elevation. C. Maintenance Garage and Stores to East elevation. D. Monitoring Office Building to back of site. E. Steel Cleaning Shop to North elevation. F. Store to south elevation. G. Retention of existing entrance at North Western corner of site as HGV entrance only. (existing entrance on West Boundary to be relocated nearer to car park to be for cars only. -- covered under planning ref. no:- 20/1221. H. Enlargement of site to back of factory

Cashla ,

525m
2360948CONDITIONAL11 Aug 2023

& retention permission for development at C&F Tooling, Cashla, Athenry, County Galway. Retention planning permission for the following extensions to the existing C&F Tooling premises: • machine shop & canteen (gross floor area - 792m2) • switch room & compressor room (gross floor area - 96 m2) •maintenance garage & stores gross floor area - 673 m2) • monitoring office building (gross floor area - 444 m2) • steel cleaning shop (gross floor area - 62.3 m2) • store (gross floor area - 20.3 m2) • machine shop (gross floor area - 4,065 m2). In addition to the above, retention permission for the existing component storage area (external) (approx. 1.54 Ha in area). Planning permission for: • upgraded surface water drainage system & associated works, •relocation of existing traffic barrier at the existing vehicular entrance to the premises, • new vehicular staff entrance on the western boundary of the site, & • alterations to the existing staff car park to provide 357no. car parking spaces to include the provision of EV charging & accessible car parking bays, • provision of visitor car park to provide 31no. car parking spaces (including EV charging & accessible car parking bays). The proposed development includes for all associated site development works & landscaping

Cashla , Athenry , Co. Galway

Planning a project of your own?

Find out in two minutes whether you need planning permission. It's free, and based on the exempted development regulations.

Do I Need Permission?