CONDITIONAL

Cavan - Cavan County Council

Proposed Development

for the development of a battery energy storage system (BESS) within a total site area of up to 0.62 hectares, to include 1 no. single storey electrical substation building, 1 no. customer switchgear container, 15 no. electrical inverter/transformer station modules (SKIDS), 10 no. containerised battery storage modules on concrete support structures, 20 no. heating, ventilation and air conditioning units (HVAC units), access tracks and upgraded site entrance, associated electrical cabling and ducting, security gates, perimeter security fencing, CCTV security monitoring system, culvert, landscaping works and all associated ancillary infrastructure on land

View the full application file on the council's planning portal →

Application Timeline

  1. Application received

    16 Jul 2018

  2. Further information requested

    6 Sept 2018

  3. Further information received

    28 Sept 2018

  4. Decision: CONDITIONAL

    24 Oct 2018

  5. Decision due

    25 Oct 2018

  6. Grant issued

    29 Nov 2018

Application Details

Location
Mucklagh , Ballyconnell , Co. Cavan
Applicant
N/A
Application Type
PERMISSION
Planning Authority
Cavan County Council
Site Area
0.62 ha
Floor Area
1 sq m
Residential Units
1

Timeline

Registration Date
16 July 2018
Status
APPLICATION FINALISED
Decision
CONDITIONAL
Decision Date
24 October 2018
Grant Date
29 November 2018
Permission Expires
28 November 2023

Location

Loading map...

Planning Applications Nearby

What the council has granted and refused around this site is the best guide to how a similar application will fare.

36m
2360327N/A20 Dec 2023

for thirty-year permission for a grid system services facility located at Gortawee, Mucklagh, Ballyconnell, County Cavan, over an area of c.3.46 hectares. The proposed works shall consist of the installation and operation of energy storage units, including 1no. customer switchgear containers and compound, which will be connected to the national grid via the adjacent Gortawee 110kV substation infrastructure, electrical transformers and inverter units, underground cabling and ducting, boundary fencing, security entrance gates, CCTV, internal access road and all associated ancillary infrastructure on land

Gortawee , Mucklagh , Ballyconnell

60m
2460072CONDITIONAL29 Feb 2024

to apply for thirty-year permission for a grid system services facility located at Gortawee, Mucklagh, Ballyconnell, County Cavan, over an area of c.3.46 hectares. The proposed works shall consist of the installation and operation of energy storage units, including 1no. customer switchgear containers and compound, which will be connected to the national grid via the adjacent Gortawee 110kV substation infrastructure, electrical transformers and inverter units, underground cabling and ducting, boundary fencing, security entrance gates, CCTV, internal access road and all associated ancillary infrastructure on land

Gortawee , Mucklagh , Ballyconnell

73m
2460045N/A29 Feb 2024

for thirty-year permission for a grid system services facility located at Gortawee, Mucklagh, Ballyconnell, County Cavan, over an area of c.3.46 hectares. The proposed works shall consist of the installation and operation of energy storage units, including 1no. customer switchgear containers and compound, which will be connected to the national grid via the adjacent Gortawee 110kV substation infrastructure, electrical transformers and inverter units, underground cabling and ducting, boundary fencing, security entrance gates, CCTV, internal access road and all associated ancillary infrastructure

Gortawee , Mucklagh , Ballyconnell

298m
17282CONDITIONAL23 Jun 2017

for development at Aughrim Mucklagh Quarry Complex for the continuation of quarrying on some of the lands covered by a previous time limited planning consent PL02.206783 to include extraction from two distinct limestone quarries and a shale quarry, with progressive restoration of the development site and the complete rehabilitation of a former shale quarry, over a 20 year period. The development includes lateral development of the two limestone quarries and a shale quarry employing existing practices, environmental mitigation measures and associated works extending over some 60 hectares of the 107.7 hectare site. The application is accompanied by an Environmental Impact Statement

Aughrim Mucklagh Gortoorlan and Snugborough , Ballyconnell , Co. Cavan

387m
2227CONDITIONAL27 Jan 2022

for the erection of 2 no. fully enclosed fuel storage tanks proposed for the refuelling of the Applicant's internal transport fleet. Each tank will have an outer bund which has in excess of 110% of tank capacity and will be sited upon a Concrete Apron with a Class 1 Full Retention Oil Interceptor . Significant further information and revised plans have been submitted.

Lands c.450m to North West ofBallyconnell Cement Works , Ballyconnell , Co Cavan

579m
18244CONDITIONAL13 Jun 2018

for development consisting of alterations, extension and change of use to Slieve Rushen House to form a Heritage and Ecological Visitor Centre, including toilet facilities, café, information display etc and meeting rooms and 1 no. self catering apartment with associated improvements and upgrade to the existing vehicular access and provision of new car-parking, picnic area and play-park and connection to the public sewer

Slieve Rushen House , Gortawee or Scotchtown , Ballyconnell

619m
19200CONDITIONAL29 May 2019

to construct 1 No. Poultry House together with all ancillary structures and all associated site works arising from the above proposed development. Significant further information and revised plans have been submitted

Aughrim , Ballyconnell , Co Cavan

662m
2560481N/A15 Aug 2025

for a solar energy development comprising ground mounted solar photovoltaic (PV) panels, mounted on steel support structures, underground cabling, temporary construction compound, erection of Transformer station (11kV), laying of a permeable gravel access track, widening of existing site (field) entrance, relocation of the existing ESB overhead line, erection of CCTV poles and cameras, erection of an entrance gate, artificial berm, landscaping and biodiversity measures all associated ancillary development works, for the purpose of generation renewable energy electricity. Planning Permission is sought for 35-year operation of the solar farm following which the site will be decommissioned, all development removed and the Site restored to agricultural lands

Lands to the South of Mannok Cement Works Entrance , In the Townlands of Gortawee or Scotchtown and Rakeelan , Ballyconnell County Cavan

666m
2560506CONDITIONAL27 Aug 2025

- RED III - for a solar energy development comprising ground mounted solar photovoltaic (PV) panels, mounted on steel support structures, underground cabling, temporary construction compound, erection of Transformer station (11kV), laying of a permeable gravel access track, widening of existing site (field) entrance, relocation of the existing ESB overhead line, erection of CCTV poles and cameras, erection of an entrance gate, artificial berm, landscaping and biodiversity measures all associated ancillary development works, for the purpose of generation renewable energy electricity. Planning Permission is sought for 35-year operation of the solar farm following which the site will be decommissioned, all development removed and the Site restored to agricultural lands

Lands to the South of Mannok Cement Works Entrance , In the Townlands of Gortawee or Scotchtown and Rakeelan , Ballyconnell County Cavan

682m
2660003CONDITIONAL14 Jan 2026

- RED III - for a solar energy development comprising ground mounted solar photovoltaic (PV) panels, mounted on steel support structures, underground cabling, temporary construction compound, erection of 3 Transformer stations (11)kV, laying of a permeable gravel access tracks, widening of existing field entrances, erection of CCTV poles and cameras, erection of entrance gates and perimeter fencing, landscaping and biodiversity measures all associated ancillary development works, for the purpose of generation renewable energy electricity. Planning Permission is sought for a 40-year operation of the solar farm following which the site will be decommissioned, all development removed and the Site restored to agricultural lands. SIGNIFICANT FURTHER INFORMATION HAS BEEN RECEIVED

Lands to the West of Mannok Cement WorksBallyconnell County Cavan. , In the Townlands of Mucklagh Gortoorlan and Snugborough , Ballyconnell County Cavan