18325
CONDITIONALSligo - Sligo County Council
Proposed Development
Development consisting of construction of a bedroom and a wetroom at ground floor level of dwelling.
View the full application file on the council's planning portal →Application Timeline
Application received
9 Aug 2018
Decision: CONDITIONAL
13 Sept 2018
Decision due
3 Oct 2018
Grant issued
16 Oct 2018
Application Details
- Location
- 6 Boyle Road , Collooney , Co. Sligo
- Applicant
- N/A
- Application Type
- PERMISSION
- Planning Authority
- Sligo County Council
- Site Area
- 0.045 ha
- Floor Area
- 26.1 sq m
- Residential Units
- 1
Timeline
- Registration Date
- 9 August 2018
- Status
- APPLICATION FINALISED
- Decision
- CONDITIONAL
- Decision Date
- 13 September 2018
- Grant Date
- 16 October 2018
- Permission Expires
- 15 October 2023
Location
Planning Applications Nearby
What the council has granted and refused around this site is the best guide to how a similar application will fare.
The development consists of 1) permission for construction of a vehicular access onto R290, 2) change of use from a Former Girls’ Primary School to an Active Inclusion Day Service centre and 3) conversion of the former play area into (7) parking spaces, along with all associated site works.
Lower Main Street , Collooney , Co. Sligo
The construction of 12 No. dwelling houses, 4 maisonette apartments and 13 No. apartments in a three storey apartment block, renovation and conversion of existing two-storey building with car parking and green area, total existing building area of circa 418.31m² and the use of this building for residential accommodation to include interior alterations, new internal partitions, alterations to window and door openings on the front, rear and side elevations, external communal areas; demolition of external sheds circa 60.43m2 and 16.86m2, external tank of circa 9.57m2, and demolition of external storage of circa 9.73m2 and external garage of circa 16.82m2 both adjoining to existing Convent, and all associated site works, to the property and building known as ‘Convent of Mercy’, Lower Main Street, Collooney, Co. Sligo. The Main Building of the Convent of Mercy is a Protected Structure NIAH Ref. No. 32310011 and RPS 151 CDP on the record of Protected Structures of the Sligo County Development Plan 2024-2030. The site also contains a Walled Garden with Ref. No. SL026-170, which is listed in the nation RMP register. The proposed development will consist of: 1.permission to complete renovations and alterations to the Convent of Mercy main building, the original Protected Structure 2. Conversion and use of the Ground and First floor of the main Convent of Mercy Protected Structure for 6 no. residential units consisting of 1 No. x 2 bed apartments and 5 No. x 1 bed apartments along with all associated works. 3. permission to construct 16 No. residential units consisting of 4 No. x 1 bed maisonette apartments and 12 No. x 3 bed dwelling houses along with all associated works. 4. permission to construct a new 3 storey block of apartments containing 13 No. residential units consisting of 3 No. x 2 bed apartments and 10 No. x 1 bed apartments along with all associated works. 5. Carry out all associated elevational changes, including the localised repair of the roof area on the protected structure, together with all associated site works including the provision of new walls, common areas, private amenity and common amenity space, walkways, pathways and roadways throughout the property including the delineation of external car parking areas. There will not be any increase in the floor area of the existing buildings
Convent of Mercy Collooney , Lower Main St Collooney , Co. Sligo
development consisting of the upgrading of the Collooney Wastewater Treatment Plant and will generally comprise the following: change of use of existing single-storey control building to storage building (c.16m2); construction of secondary treatment tanks with associated air blowers and pumps; erection of single-storey administration and control building (c.47.85m2); proposed utility yard area comprising associated equipment including screens, grit removers and odour control; conversion of existing aeration tank to stormwater holding tanks; conversion of existing clarifier to a sludge holding tank and all ancillary site development works including hard and soft landscaping and boundary treatments
Collooney Wastewater Treatment Plant , Union Road , Collooney
PP - for development consisting of the following: to carry out preliminary and preparatory site works for reduction of existing ground levels on site with temporary vehicle access, associated facilities all associated works.
Union Road , Collooney , Co. Sligo
Development consisting of 1. Retain boundary wall (2.54m in height) and entrance as constructed 2. Retain hard surface measuring 1140 m2 and 748 m2 for the storage of metal and end of life vehicles respectively 3. Retain existing shed and office 4. Retain and complete partially constructed precious metals shed 5. All ancillary works associated with the above. A Natura Impact Statement (NIS) accompanies this application
Collooney Co. Sligo , , Collooney
Development consisting of change of use of existing guest house and retail unit, to 2 number 2 bed apartments & 2 number 1 bed apartments. Proposed works consist of demolition of existing rear extensions. Construction of two new extensions to rear with provision of parking and all associated site works.
Main Street , Collooney , Co SLigo
development consisting of the following: - (1) change of use & amalgamation of existing units 10, 11, 12 & 13 from warehouse & office space to light industrial unit which will be used to manufacture plastic products (floor area = 2293m2); (2) carrying out of alterations to elevations of existing building; (3) provision of first floor office space in existing building with additional floor area of 231m2; (4) construction of an extension to side elevation with additional floor area of 266m2, provision of 6 no. silos for raw material storage, each with a capacity of 99.7m3, a rain water harvesting tank and water chiller; (5) relocation of existing site entrance and construction of new boundary walls and fencing; (6) revised car parking layout and provision of loading bays; (7) signage & 3 no. flag poles and (8) carrying out of ancillary site development works
Units 10 11 12 & 13 GWI Business Park , Union Road , Collooney
development consisting of the installation of CCTV system with cameras mounted on existing poles to cover playground / tennis court area
The Fair Green , Collooney , Co. Sligo
Development consisting of a dwelling house, septic tank and percolation area, enlarged entrance and all necessary ancillary site works
Rinn , Collooney , Co Sligo
Development consisting of the following; permission for subdivision of Unit No. 9 (total floor area 1726 m2) into 2 separate units and all associated works. Previous permission 04/1477 refers
Union Road , Collooney , Co Sligo