18868
CONDITIONALKilkenny - Kilkenny County Council
Proposed Development
to construct slatted cubicle Shed with loose straw area and all associated site works
View the full application file on the council's planning portal →Application Timeline
Application received
31 Dec 2018
Further information requested
22 Feb 2019
Further information received
28 Mar 2019
Decision: CONDITIONAL
18 Apr 2019
Decision due
24 Apr 2019
Grant issued
21 May 2019
Application Details
- Location
- Clontubbrid , Freshford , Co Kilkenny
- Applicant
- N/A
- Application Type
- PERMISSION
- Planning Authority
- Kilkenny County Council
- Site Area
- 0.57 ha
Timeline
- Registration Date
- 31 December 2018
- Status
- APPLICATION FINALISED
- Decision
- CONDITIONAL
- Decision Date
- 18 April 2019
- Grant Date
- 21 May 2019
- Permission Expires
- 20 May 2024
Location
Planning Applications Nearby
What the council has granted and refused around this site is the best guide to how a similar application will fare.
for the construction of a 3 metre high ball wall, all weather area, perimeter fencing and associated site works
Clontubrid , Co Kilkenny
for (1) American Barn containing 5 stable boxes tack room and loose house. (2) roofed working yard, (3) Roofed manure pit, (4) soiled water tank as constructed, at different location on applicants lands from that granted under P06/1858
Clontubrid , Freshford , County Kilkenny
to build a dwelling, alter existing entrance, install waste water treatment system, including associated site works
Graigueswood , Freshford , Co. Kilkenny
for the construction of a bungalow style dwelling, detached garage, on site effluent treatment system, new entrance and all associated site development works
Clontubbrid , Ballyragget , Co Kilkenny
for a wind energy project consisting of nine 500 kW wind turbines represents a total installed capacity of 4.5 MW. This medium-scale wind farm is suitable for small communities, industrial applications, or grid-connected renewable energy projects. Key Details: Total Capacity: 4.5 MW (9 turbines x 500 kW each). Annual Energy Output: Approximately 10–18 million kWh/year (depending on the site's wind conditions and capacity factor). Land Requirement: Requires around 20–40 hectares, depending on the spacing between turbines (typically 5–7 times the rotor diameter). Grid Connection: Includes step-up transformers to integrate the generated power into the local grid at higher voltage levels. Turbine Configuration: Rotor diameter: 40–50 meters. Hub height: 40–60 meters. Cut-in wind speed: ~3 m/s. Cut-out wind speed: ~20 m/s. Environmental Benefits: Offsets ~13,500–18,000 metric tons of CO2 annually compared to coal-fired electricity. Provides clean energy for approximately 2,700–3,600 households. Applications: This project could support rural electrification, reduce dependence on fossil fuels, and serve as a model for community-based renewable energy development.
Tifeaghna ( Mt Garrett) , Clontubrid , Lisdowney
to construct a dormer style, three-bedroom dwelling house, a detached garage, a new site entrance, a new septic tank and a percolation area and all associated site works
Lodge Demesne West , Freshford , Co. Kilkenny
for retention of 1) extensions to side and rear of existing dwelling and 2) garage store and all associated site works
Clone , Freshford , Co. Kilkenny
for a new single storey four bedroom dwelling, detached domestic garage, new residential site entrance, new wastewater treatment system, plus all associated site works at
Skinstown , Ballyraggett , Co. Kilkenny
for a development of 10 no. short stay / holiday static glamping pods, replacement of existing pumphouse with storage shed containing pumphouse, alterations to as built wastewater treatment plant and percolation area plus associated site works
Clone , Freshford , Co. Kilkenny
is sought for the erection of a part two storey/ part single storey dwelling, a garage, a waste water treatment system and percolation area, a site entrance and associated site works at
Tifeaghna , Freshford , Co. Kilkenny