18931

CONDITIONAL

Kerry - Kerry County Council

Proposed Development

CONSTRUCT A BATTERY STORAGE FACILITY WITHIN A TOTAL SITE AREA OF UP TO 2.178HA, TO INCLUDE 60 NO SELF-CONTAINED BATTERY CONTAINER UNITS WITH ASSOCIATED HVAC COOLING UNITS, 14 CONVERTER AND 14 STEP UP TRANSFORMER CONTAINER UNITS, ASSOCIATED COMPOUND CABLING AND DUCTING, A GRID TRANSFORMER, A SINGLE STOREY SUBSTATION/CONTROL BUILDING WITH WELFARE FACILITIES , A FOUL WATER HOLDING TANK, A CABLE ROUTE GRID CONNECTION TO THE ADJACENT ESB SUBSTATION, MAINTENANCE LIGHTING , SECURITY F3ENCING, A CCTV MONITORING SYSTEM , LANDSCAPING WORKS AND ALL ASSOCIATED ANCILLARY INFRASTRUCTURE ON LANDS

View the full application file on the council's planning portal →

Application Timeline

  1. Application received

    25 Sept 2018

  2. Further information requested

    16 Nov 2018

  3. Further information received

    15 Feb 2019

  4. Decision: CONDITIONAL

    12 Mar 2019

  5. Decision due

    14 Mar 2019

  6. Grant issued

    15 Apr 2019

Application Details

Location
SHRONEBEIRNE , LISTOWEL , CO KERRY
Applicant
N/A
Application Type
PERMISSION
Planning Authority
Kerry County Council
Site Area
2.178 ha

Timeline

Registration Date
25 September 2018
Status
APPLICATION FINALISED
Decision
CONDITIONAL
Decision Date
12 March 2019
Grant Date
15 April 2019
Permission Expires
14 April 2024

Location

Loading map...

Planning Applications Nearby

What the council has granted and refused around this site is the best guide to how a similar application will fare.

2m
23499N/A8 May 2023

INVALID APPLICATION

SHRONEBEIRNE , LISTOWEL , CO KERRY

2m
23574CONDITIONAL18 May 2023

CONSTRUCT A BATTERY STORAGE FACILITY WITHIN A TOTAL SITE AREA OF 2.178HA, TO INCLUDE 60 NO SELF-CONTAINED BATTERY UNITS WITH ASSOCIATED HVAC COOLING UNITS, 14 CONVERTER AND 14 STEP UP TRANSFORMER CONTAINER UNITS, ASSOCIATED COMPOUND CABLING AND DUCTING, A GRID TRANSFORMER, TWO SINGLE STOREY SUBSTATION/CONTROL BUILDINGS WITH WELFARE FACILITIES, A FOUL WATER HOLDING TANK, A CABLE ROUTE GRID CONNECTION TO THE ADJACENT ESB SUBSTATION, MAINTENANCE LIGHTING, SECURITY FENCING, A CCTV MONITORING SYSTEM, LANDSCAPING WORKS AND ALL ASSOCIATED ANCILLARY INFRASTRUCTURE NECESSARY TO FACILITATE THE DEVELOPMENT ON LANDS. A NATURA IMPACE STATEMENT HAS BEEN SUBMITTED WITH THIS APPLICATION

SHRONEBEIRNE , LISTOWEL , CO KERRY

2m
18847N/A28 Aug 2018

CONSTRUCT A BATTERY STORAGE FACILITY WITHIN A TOTAL SITE AREA UP TO 2.178HA, TO INCLUDE 60 NO SELF-CONTAINED BATTERY CONTAINER UNITS WITH ASSOCIATED HVAC COOLING UNITS, 14 CONVERTER AND 14 STEP UP TRANSFORMER CONTAINER UNITS, ASSOCIATED COMPOUND CABLING AND DUCTING, A GRID TRANSFORMER , A SINGLE STOREY SUBSTATION/CONTROL BUILDING WITH WELFARE FACILITIES, A FOUL WATER HOLDING TANK , A CABLE ROUTE GRID CONNECTION TO THE ADJACENT ESB SUBSTATION , MAINTENANCE LIGHTING, SECURITY FENCING , A CCTV MONITORING SYSTEM, LANDSCAPING WORKS AND ALL ASSOCIATED ANCILLARY INFRASTRUCTURE ON LANDS. A TEN YEAR PLANNING PERMISSION IS BEING SOUGHT TO CONSTRUCT THE DEVELOPMENT

SHRONEBEIRNE , LISTOWEL , CO. KERRY

25m
20346N/A14 Apr 2020

CHANGE OF DESIGN TO SUBSTATION BUILDING WITHIN PLANNING REFERENCE 18/847. THE NEW BUILDING DESIGN WILL INCORPORATE A 23% REDUCTION OF PLAN AREA AND A REDUCED HEIGHT. THE PERMITTED BUILDING WILL BE SPILT INTO TWO AND LOCATED ON A SIMILAR FOOTPRINT TO THE ORIGINAL ON LANDS

SHRONEBEIRNE , LISTOWEL , CO KERRY

45m
20661CONDITIONAL23 Jul 2020

FOR CHANGE OF DESIGN TO THE SUBSTATION COMPOUND PERMITTED CARE OF REG NO 18/931, CREATING 2 NO COMPOUND AREAS; ESB COMPOUND AND IPP COMPOUND AND A SEPERATE CONTROL BUILDING WITHIN EACH COMPOUND, SEPERATE ENTRANCE GATES AND ALL ASSOCIATED SITE WORKS

SHRONEBEIRNE , LISTOWEL , CO KERRY

66m
2560249CONDITIONAL2 Apr 2025

permission to construct a battery storage facility including self-contained battery units with associated HVAC cooling and inverter equipment, associated compound cabling and ducting, electrical substation including grid transformer and single storey control building with welfare facilities, a foul water holding tank, an underground cable route grid connection to the adjacent ESB substation, maintenance lighting, security fencing, a CCTV monitoring system, landscaping works and all associated ancillary infrastructure necessary to facilitate the development on lands at Shronebeirne, Listowel, Co. Kerry. A Natura Impact Statement (NIS) was prepared in respect of the proposed development and accompanies the application.

Shronebeirne , Listowel , Co. Kerry

626m
23762REFUSED5 Jul 2023

TO CONSTRUCT A NEW SITE ENTRANCE WITH SPLAYED ENTRANCE WALLS AND NEW ENTRANCE GATES, INCLUDING ALL ASSOCIATED ANCILLARY SITE WORKS AND BOUNDARY TREATMENT

SHRONEBEIRNE , LISTOWEL , CO KERRY

626m
2560662CONDITIONAL30 Jul 2025

(A) CONSTRUCT A SINGLE STOREY EXTENSION TO THE REAR (SOUTH) ELEVATION, (B) MINOR CHANGES TO BOTH THE FRONT (NORTH) ELEVATION AND SIDE (EAST) ELEVATION OF EXISTING DWELLING, (C) DECOMMISSION EXISTING SEPTIC TANK AND (D) INSTALL A NEW PACKAGED WASTEWATER TREATMENT SYSTEM AND PERCOLATION AREA AND ALL NECESSARY ANCILLARY SITE WORKS.

SHRONEBEIRNE , LISTOWEL , CO. KERRY

889m
2561042CONDITIONAL10 Nov 2025

Full planning permission to (A) construct new dwelling house and (B) construct new septic tank and percolation area along with all ancillary site services at Coolroe Upper, Glenbeigh, Co.Kerry

Coolroe Upper , Glenbeigh , Co.Kerry

896m
19822CONDITIONAL2 Aug 2019

RETAIN HIS DOMESTIC GARAGE AS CONSTRUCTED ON HIS SITE

LACKA EAST , KILMORNA , LISTOWEL

Planning a project of your own?

Find out in two minutes whether you need planning permission. It's free, and based on the exempted development regulations.

Do I Need Permission?