The Register of Planning Applications · Éire

Monday 31 August 2026

← Back to search

19/5031

CONDITIONAL

Cork - Cork County Council

Proposed Development

Creation of a site access into a forestry plantation to facilitate a timber harvest and haulage operation, the proposed development consists of the creation of a bellmouth/back in loading bay

View the full application file on the council's planning portal →

Application Timeline

  1. Application received

    25 Apr 2019

  2. Decision: CONDITIONAL

    6 Nov 2019

  3. Decision due

    7 Nov 2019

  4. Grant issued

    12 Dec 2019

Application Details

Location
Carrigcleena More Dromore Mallow Co. Cork
Applicant
N/A
Application Type
PERMISSION
Planning Authority
Cork County Council

Timeline

Registration Date
25 April 2019
Status
APPLICATION FINALISED
Decision
CONDITIONAL
Decision Date
6 November 2019
Grant Date
12 December 2019

Location

Loading map...

Planning Applications Nearby

What the council has granted and refused around this site is the best guide to how a similar application will fare.

66m
19/4674INCOMPLETED APPLICATION20 Mar 2019

The creation of a site entrance onto a public road in order to facilitate a forestry operation.

Carrigcleena More Mallow Co. Cork

205m
16/5808CONDITIONAL20 Jul 2016

The application site comprises an existing asphalt plant (permitted under planning reg no. 06/4390). The proposed development seeks to provide for the occasional operation of the asphalt plant outside normal working hours up to a maximum of 40 no. days per annum. The proposed development also provides for additions/alterations to the existing asphalt plant including the reorientation of the existing cold feed bins and the provision of a hot storage unit.

Carrigcleena More Bweeng Co. Cork

206m
16/5639INCOMPLETED APPLICATION4 Jul 2016

The application site comprises an existing asphalt plant (permitted under planning reg. 06/4390). The proposed development seeks to provide for the occasional operation of the asphalt pant outside normal working hours up to a maximum of 40 no. days per annum. The proposed development also provides foe additions / alterations to the existing asphalt plant including the reorientation of the existing cold feed bins and the provision of hot storage unit.

Carrigcleena More Bweeg Co. Cork

217m
05/8072INCOMPLETED APPLICATION2 Nov 2005

Retention of asphalt plant with associated feed hoppers, bitumen storage tanks, bunded diesel tank and generator

Carrigcleena Quarry Carrigcleena More Bweeng Mallow

225m
06/4390CONDITIONAL30 Jan 2006

Retention of change of use from quarry to asphalt plant

Carrigcleena Quarry Carrigcleena More Bweeng Mallow

228m
07/4884CONDITIONAL8 Feb 2007

Change of use of silage pit to cubicles and crush, construction of silage slab, dungstead, covered and uncovered feed passage, removable feed rail, floatation channel and slatted unit incorporating slatted tanks, feed areas and feed passage

Carrigcleena More Bweeng Mallow

327m
18/7244CONDITIONAL10 Dec 2018

The development consists of the retention of demolition of structures previously used for aggregate storage purposes, comprising of an aggregate storage structure measuring approx. 1,130m2, an aggregate storage structure measuring approx. 135m2 and an aggregate storage structure measuring approx. 180m2. Permission for retention of demolition of a canteen building measuring approx. 109m2 is also being sought, all within an application area of c. 0.164ha.

Carrigcleena More Bweeng Co. Cork

336m
18/5035WITHDRAWN26 Apr 2018

The development will consist of a readymix concrete batching plant and a concrete block production facility comprising of a concrete batching plant, mobile block making machine, block production area (4,285m2), block storage area (1457m2), closed circuit settlement system and all ancillary works within an application area of c. 1.1ha.

Carrigcleena More Bweeng Co. Cork

336m
19/5704INCOMPLETED APPLICATION4 Jul 2019

The development will consist of a readymix concrete batching plant and a concrete block production facility comprising of a concrete batching plant, mobile block making machine, block production area (4,285m2), block storage area (1,457m2), closed circuit settlement system and all ancillary works within an application area of c. 1.1ha.

Carrigcleena More Bweeng Co. Cork

336m
19/5902CONDITIONAL29 Jul 2019

The development will consist of a readymix concrete batching plant and a concrete block production facility comprising of a concrete batching plant, mobile block making machine, block production area (4,285m2), block storage area (1,457m2), closed circuit settlement system and all ancillary works within an application area of c.1.1ha.

Carrigcleena More Bweeng Co. Cork

Planning a project of your own?

Find out in two minutes whether you need planning permission. It's free, and based on the exempted development regulations.

Do I Need Permission?