1929

CONDITIONAL

Kilkenny - Kilkenny County Council

Proposed Development

to construct a dormer style, three-bedroom dwelling house, a detached garage, a new site entrance, a new septic tank and a percolation area and all associated site works

View the full application file on the council's planning portal →

Application Timeline

  1. Application received

    24 Jan 2019

  2. Decision: CONDITIONAL

    19 Mar 2019

  3. Decision due

    20 Mar 2019

  4. Grant issued

    23 Apr 2019

Application Details

Location
Lodge Demesne West , Freshford , Co. Kilkenny
Applicant
N/A
Application Type
PERMISSION
Planning Authority
Kilkenny County Council
Site Area
0.485 ha
Floor Area
231 sq m
Residential Units
1

Timeline

Registration Date
24 January 2019
Status
APPLICATION FINALISED
Decision
CONDITIONAL
Decision Date
19 March 2019
Grant Date
23 April 2019
Permission Expires
22 April 2024

Location

Loading map...

Planning Applications Nearby

What the council has granted and refused around this site is the best guide to how a similar application will fare.

249m
17707CONDITIONAL25 Oct 2017

to build a dwelling, entrance, bore well, install septic tank including associated site works

Lodge Demesne West , Freshford , Co. Kilkenny

638m
2560260N/A14 May 2025

to build a single storey dwelling, treatment system with a pumped raised polishing filter, new bore well, site entrance and all associated site works

Tifeaghna , Freshford , Kilkenny

638m
21272CONDITIONAL8 Apr 2021

to build a single storey dwelling, garage, pumped raised polishing filter treatment system, new bore well, site entrance and associated site works on my land

Tifeaghna , Freshford , Co Kilkenny

895m
18480CONDITIONAL17 Jul 2018

for the construction of a 3 metre high ball wall, all weather area, perimeter fencing and associated site works

Clontubrid , Co Kilkenny

982m
21285CONDITIONAL13 Apr 2021

to build a dwelling, alter existing entrance, install waste water treatment system, including associated site works

Graigueswood , Freshford , Co. Kilkenny

1.0km
2560371CONDITIONAL23 Jun 2025

for the proposed renovations to existing dwelling to include internal layout changes and elevational changes, proposed storey and a half rear/side extension, proposed decommissioning of existing septic tank and percolation area, proposed new treatment tank and percolation area, proposed relocation of vehicular entrance, proposed stormwater soakaways, landscaping and all associated site works. Including the demolition of an existing single storey extension

Tinnascarty , Freshford , Co. Kilkenny

1.1km
18868CONDITIONAL31 Dec 2018

to construct slatted cubicle Shed with loose straw area and all associated site works

Clontubbrid , Freshford , Co Kilkenny

1.1km
2360085CONDITIONAL7 Mar 2023

(A) DEMOLITION OF EXISTING AGRICULTURAL BUILDINGS (B) CONSTRUCTION OF A SLATTED UNDERGROUND EFFLUENT STORAGE TANK AND FEED PASSAGE (C) CONSTRUCTION OF A CALF SHED AND CALVING FACILITIES, TOGETHER WITH ALL OTHER ASSOCIATED SITE WORKS

Tinnascarty , Freshford , Co. Kilkenny

1.1km
2460554CONDITIONAL19 Nov 2024

for construction of a slatted cubicle shed with underground effluent storage tank and to amend the farm entrance approved under Planning Reference 16141, together with all other associated site works

Tinnascarty , Freshford , Co. Kilkenny

1.2km
2560019N/A18 Jan 2025

for a wind energy project consisting of nine 500 kW wind turbines represents a total installed capacity of 4.5 MW. This medium-scale wind farm is suitable for small communities, industrial applications, or grid-connected renewable energy projects. Key Details: Total Capacity: 4.5 MW (9 turbines x 500 kW each). Annual Energy Output: Approximately 10–18 million kWh/year (depending on the site's wind conditions and capacity factor). Land Requirement: Requires around 20–40 hectares, depending on the spacing between turbines (typically 5–7 times the rotor diameter). Grid Connection: Includes step-up transformers to integrate the generated power into the local grid at higher voltage levels. Turbine Configuration: Rotor diameter: 40–50 meters. Hub height: 40–60 meters. Cut-in wind speed: ~3 m/s. Cut-out wind speed: ~20 m/s. Environmental Benefits: Offsets ~13,500–18,000 metric tons of CO2 annually compared to coal-fired electricity. Provides clean energy for approximately 2,700–3,600 households. Applications: This project could support rural electrification, reduce dependence on fossil fuels, and serve as a model for community-based renewable energy development.

Tifeaghna ( Mt Garrett) , Clontubrid , Lisdowney

Planning a project of your own?