1930
CONDITIONALCarlow - Carlow County Council
Proposed Development
retention permission sought for recreation room/shed. Planning permission sought for the construction of a front porch extension, side extension and a rear extension, new proprietary effluent waste water treatment system, percolation/polishing filter and ancillary services associated with same
View the full application file on the council's planning portal →Application Timeline
Application received
6 Feb 2019
Decision due
2 Apr 2019
Decision: CONDITIONAL
2 Apr 2019
Grant issued
3 May 2019
Application Details
- Location
- Johnstown , Bennekerry , Co. Carlow
- Applicant
- N/A
- Application Type
- RETENTION
- Planning Authority
- Carlow County Council
- Floor Area
- 69.09100000000001 sq m
- Residential Units
- 2
Timeline
- Registration Date
- 6 February 2019
- Status
- APPLICATION FINALISED
- Decision
- CONDITIONAL
- Decision Date
- 2 April 2019
- Grant Date
- 3 May 2019
- Permission Expires
- 2 May 2024
Location
Planning Applications Nearby
What the council has granted and refused around this site is the best guide to how a similar application will fare.
Erection of a single storey house and planning permission to install a waste water treatment system and all ancillary site works
Johnstown , Bennekerry , Co. Carlow
construct a part two storey part single storey dwelling, single storey garage, new entrance off existing access lane, septic tank and percolation area, bored well and all associated site works
Ardnehue , Bennekerry , Co. Carlow
the construction of a new agricultural shed for use as a grain store, a new Bovine shed with underground slatted tank, a farmyard manure storage area, and all associated site works
Ardnehue Lodge , Bennekerry , Co. Carlow
the construction of a new agricultural shed for use as a grain store, a new Bovine shed with underground slatted tank, a farmyard manure storage area, and all associated site works
Ardnehue Lodge , Bennekerry , Co. Carlow
the construction of a new agricultural shed for use as a grain store, a new Bovine shed with underground slatted tank, a farmyard manure storage area, and all associated site works
Ardnehue Lodge , Bennekerry , Co. Carlow
a single storey extension to the side and rear of existing one and a half storey dwelling, with alterations to external façade including additional dormer windows, internal alterations, use of existing onsite services, existing entrance and all associated site works
Ardnehue , Bennekerry , Co Carlow
the construction of a single storey extension to the rear elevation of existing dwelling and all associated site works
Ardnehue , Bennekerry , Co. Carlow
A 10 year permission for the erection and operation of a solar photovoltaic energy development. The proposed development will consist of the erection and operation of a solar photovoltaic energy development which includes the erection of fixed solar panels on ground mounted frames, electrical transformer and inverter units, distribution systems operator (DSO) sub-station, customer substation, underground cabling and ducting, storage containers, boundary fencing, security entrance gates, CCTV, internal access road and all associated ancillary activities.
Johnstown , Bennekerry , Co Carlow
A 10 year permission for the erection and operation of a solar photovoltaic energy development. The proposed development will consist of the erection and operation of a solar photovoltaic energy development which includes the erection of fixed solar panels on ground mounted frames, electrical transformer and inverter units, distribution systems operator (DSO) sub-station, customer substation, underground cabling and ducting, storage containers, boundary fencing, security entrance gates, CCTV, internal access road and all associated ancillary activities
Johnstown , Bennekerry , Co. Carlow
Permission for a development to include a solar farm on an area of approximately 17.6 hectares, comprising photovoltaic panels on ground mounted frames, 1 no. onsite 38kV substation, 10 no. single storey inverter/transformer stations, security fencing, a palisade double security gate, 2 no. storage containers, CCTV, a temporary construction stage wheel wash system and all associated ancillary development works. Elgin Energy Services Ltd. are applying for the proposed solar farm to have planning permission that is effective for 10 years (an an operational period of 40 years). A Natura Impact Statement (NIS) has been prepared and will be submitted to the planning authority with the planning application
Ardnehue , and Friarstown , County Carlow
Planning a project of your own?
Find out in two minutes whether you need planning permission. It's free, and based on the exempted development regulations.
Do I Need Permission?