The Register of Planning Applications · Éire

Monday 31 August 2026

← Back to search

19392

CONDITIONAL

Carlow - Carlow County Council

Proposed Development

Permission for the construction of a four-bedroom, single storey residential dwelling, including roof lights; and a detached single storey domestic garage. Other works as part of the development include: EN certified wastewater treatment system and associated EPA compliant soil polishing filter; soakways; bore well; new vehicular entrance; landscaping; boundary treatment; and all associated works to facilitate the development.

View the full application file on the council's planning portal →

Application Timeline

  1. Application received

    2 Oct 2019

  2. Further information requested

    25 Nov 2019

  3. Further information received

    29 Apr 2020

  4. Decision: CONDITIONAL

    16 Oct 2020

  5. Decision due

    19 Oct 2020

  6. Grant issued

    18 Nov 2020

Application Details

Location
Templepeter , Rathoe , Co. Carlow
Applicant
N/A
Application Type
PERMISSION
Planning Authority
Carlow County Council
Floor Area
322.8 sq m
Residential Units
2

Timeline

Registration Date
2 October 2019
Status
APPLICATION FINALISED
Decision
CONDITIONAL
Decision Date
16 October 2020
Grant Date
18 November 2020
Permission Expires
17 November 2025

Location

Loading map...

Planning Applications Nearby

What the council has granted and refused around this site is the best guide to how a similar application will fare.

312m
18349REFUSED31 Aug 2018

A) Planning permission to construct new agricultural shed, with associated holding tanks, yards and aprons. B) Permission to construct new dwelling house, domestic garage, install ETU with percolation area, and form new entrance with all associated site works

Ballintrane Td. , Fenagh , Co. Carlow

326m
18373N/A27 Sept 2018

for indefinite retention of a 48msq extension to rear of existing dwelling and indefinite retention of a 10msq detached single storey home office

Templepeter , Fighting Cocks , Co. Carlow

326m
18419CONDITIONAL30 Oct 2018

for the indefinite retention of a 48m2 extension to the rear of my existing dwelling and indefinite retention of a 23m2 detached single storey home-office

Templepeter , Fighting Cocks , Co. Carlow

524m
2560342N/A4 Nov 2025

works to existing dwelling house including, partial demolition and single storey extension, upgrade of existing sewerage system to EPA CoP criteria, together with all associated site works

Ballymogue , Rathoe , Co. Carlow

524m
2560347CONDITIONAL5 Nov 2025

works to existing dwelling house including, partial demolition and single storey extension, upgrade of existing sewerage system to EPA CoP criteria, together with all associated site works

Ballymogue , Rathoe , Co. Carlow

558m
2660223N/A16 Jul 2026

1. extend and renovate existing dwelling house and amendments to elevations to include removal of chimneys 2. demolish and relocate the front porch, 3. Demolish outbuildings to the side and rear of the dwelling house, 4. demolish existing extension to the rear of the dwelling house. 5. Change of use of existing outbuilding to side of dwelling house to part of dwelling house. 6. Extension to the rear of dwelling house. 7. Internal amendments to ground and first floor layouts 8. Permission is also sought to remove existing boundary wall and entrance to the front of the property and reinstate same by way set back. 9.and all associated works

Graiguealug , Nurney , Co. Carlow

670m
2233N/A8 Feb 2022

Permission for development at this site: Fennagh, Ballintrane, Co. Carlow. The development will consist of an agricultural shed for the storage of straw. Permission is also sought to relocate a utility pole to site boundary along with all associated site works.

Fennagh , Ballintrane , Co. Carlow

670m
2243CONDITIONAL14 Feb 2022

Permission for development consisting of an agricultural shed for the storage of straw. Permission is also sought to relocate a utility pole to site boundary along with all associated site

Fennagh , Ballintrane , Co. Carlow

689m
22142N/A28 Apr 2022

for a solar farm which will connect to the national grid on lands with a total area of circa 128 hectares, consisting of solar panels on ground mounted frames, 18 no. single storey electrical inverter/transformer stations, equipment container, underground cabling within the solar farm site and within the N80 and L-3046 public roads to connect solar farm field parcels, security fencing, satellite communications pole. CCTV, access tracks inclusive of 9 no. agricultural bridges (including 1 no. bridge over the rive Buren), temporary construction compounds, landscaping and all associated ancillary development works at Ballintrane, Ballbrommell, Bensinstown, Clonmacshane, Garreenleen, Graiguealug, Tinnaclash and Templpeter, Co. Carlow. As part of the proposal, permission is also sought for minor amendments to Carlow County Council planning reference 20143 (An Bord Pleanala reference: 307891-20) comprising removal of 1837sqm of solar panels, provision of additional access tracks and focused removal of hedgerows to accommodate same, and the laying of 1,788metres of 33kV underground cabling for the purposes of future grid connection. Construction and operational access will be via entrances from the L-7111, L-3046 and L-3049. The operational lifespan of the solar farm will be 35 years. A Natura Impact Statement (NIS) has been prepared and will be submitted to the planning authority with the application.

Ballintrane Ballybrommell Bendinstown Clonmacshane , Garreenleen Graiguealug Tinnaclash and Templepeter , Co. Carlow

689m
22163CONDITIONAL20 May 2022

for a 10 year planning permission for a solar farm and associated works, comprising (1) A solar farm which will connect to the national electricity grid on lands with a total area of circa 128 hectares, consisting of solar panels on ground mounted frames, 18 no. single storey electrical inverter/transformer stations, equipment container, underground cabling within the solar farm site and within the N80 and L-3046 public roads to connect solar farm field parcels, security fencing, satellite communications pole, CCTV, access tracks inclusive of 9 no. agricultural bridges (including 1 no. bridge over the river Burrin), temporary construction compounds, landscaping and all associated ancillary development works. (2) minor amendments to a neighbouring solar farm planning permission (Carlow County Council planning reference 20143 & An Bord Pleanala reference: 307891-20) to facilitate future grid connection and additional access tracks for the proposed development. These amendments will comprise of the removal of 1,837 sqm of solar panels, provision of additional access tracks and focused removal of hedgerows to accommodate same, and the laying of 1,788 metres of 33kV underground cabling for the purposes of the future grid connection. (3) Construction and operational access for the solar farm will be via entrances from the L-7111, L-3046 and L-3049. The operational lifespan of the solar farm will be 35 years. A Natura Impact Statement (NIS) has been prepared and will be submitted to the planning authority with the application.

Ballintrane Ballybrommell Bendinstown Clonmacshane Garreenleen Graiguealug Tinnaclash & Templepeter , Co. Carlow

Planning a project of your own?

Find out in two minutes whether you need planning permission. It's free, and based on the exempted development regulations.

Do I Need Permission?