The Register of Planning Applications · Éire

Monday 31 August 2026

← Back to search

19600120

CONDITIONAL

Tipperary - Tipperary County Council

Proposed Development

the provision of three battery storage containers which are required for the operation of the previously granted solar farm (Planning Ref 16600640). This planning application also includes an alteration to the approved planning boundary and the operational permission of the solar farm to be increased from 25 to 30 years

View the full application file on the council's planning portal →

Application Timeline

  1. Application received

    15 Feb 2019

  2. Further information requested

    10 Apr 2019

  3. Further information received

    23 May 2019

  4. Decision: CONDITIONAL

    26 Jul 2019

  5. Decision due

    1 Aug 2019

  6. Grant issued

    30 Aug 2019

Application Details

Location
Ballynagrane and Deerparklodge , Carrick-on-Suir , Co. Tipperary
Applicant
N/A
Application Type
PERMISSION
Planning Authority
Tipperary County Council

Timeline

Registration Date
15 February 2019
Status
APPLICATION FINALISED
Decision
CONDITIONAL
Decision Date
26 July 2019
Grant Date
30 August 2019
Permission Expires
17 April 2028

Location

Loading map...

Planning Applications Nearby

What the council has granted and refused around this site is the best guide to how a similar application will fare.

46m
211129N/A30 Jul 2021

alterations to the previously granted solar farm in the townlands of Ballynagrana and Deerparklodge, Carrick-on-Suir, Co. Tipperary (Tipperary County Council Reg Ref. 16600640, and An Bord Pleanála Reg Ref. PL92.248089) as amended by Tipperary County Council Reg Ref. 19600120. Permission was originally granted for a solar photovoltaic installation comprising up to 36,500 m2 of solar panels on ground mounted frames, 6 no. inverters housed in 3 units, 1 no. 20kV substation, security fencing, new entrance onto public road, CCTV; underground cable and ducts including cable and ducts along the public road to the entrance of the existing Deerpark substation within the townland of Deerparklodge, Carrick-on-Suir, Co. Tipperary and all associated ancillary development works and services. Permission was subsequently granted for three battery storage containers, alterations to the approved planning boundary and the operational permission of the solar farm from 25 to 30 years. Permission is now sought for the following; optimized solar pv panel configuration to comprise of up to 33,203 m2 of solar panels on ground mounted frames; increase to the length of the 20 kV substation from 9.98m to 11.975m to allow installation of required electrical equipment; increase in height to the permitted solar panels from 2.72 m to 2.82m and; permission to increase the operational period of the solar farm from 30 years to 35 years. The site is located in the townlands of Ballynagrana and Deerparklodge, Carrick-on-Suir, Co. Tipperary. A Natura Impact Statement (NIS) accompanies this application. Planning Permission is sought for a period of 10 years

Ballynagrana and Deerparklodge , Carrick-on-Suir , Co. Tipperary

77m
211818CONDITIONAL15 Dec 2021

alterations to the previously granted solar farm in the townlands of Ballynagrana and Deerparklodge, Carrick-on-Suir, Co. Tipperary (Tipperary County Council Reg Ref. 16600640, and An Bord Pleanála Reg Ref. PL92.248089) as amended by Tipperary County Council Reg Ref. 19600120. Permission was originally granted for a solar photovoltaic installation comprising up to 36,500 m2 of solar panels on ground mounted frames, 6 no. inverters housed in 3 units, 1 no. 20kV substation, security fencing, new entrance onto public road, CCTV; underground cable and ducts including cable and ducts along the public road to the entrance of the existing Deerpark substation within the townland of Deerparklodge, Carrick-on-Suir, Co. Tipperary and all associated ancillary development works and services. Permission was subsequently granted for three battery storage containers, alterations to the approved planning boundary and the operational permission of the solar farm from 25 to 30 years. Permission is now sought for the following; optimized solar pv panel configuration to comprise of up to 33,203 m2 of solar panels on ground mounted frames; increase to the length of the 20 kV substation from 9.98m to 11.975m to allow installation of required electrical equipment; increase in height to the permitted solar panels from 2.72 m to 2.82m and; permission to increase the operational period of the solar farm from 30 years to 35 years. The site is located in the townlands of Ballynagrana and Deerparklodge, Carrick-on-Suir, Co. Tipperary. A Natura Impact Statement (NIS) accompanies this application. Planning Permission is sought for a period of 10 years

Ballynagrana and Deerparklodge , Carrick-on-Suir , Co. Tipperary

116m
211306N/A1 Sept 2021

alterations to the previously granted solar farm in the townlands of Ballynagrana and Deerparklodge, Carrick-on-Suir, Co. Tipperary (Tipperary County Council Reg Ref. 16600640, and An Bord Pleanála Reg Ref. PL92.248089) as amended by Tipperary County Council Reg Ref. 19600120. Permission was originally granted for a solar photovoltaic installation comprising up to 36,500 m2 of solar panels on ground mounted frames, 6 no. inverters housed in 3 units, 1 no. 20kV substation, security fencing, new entrance onto public road, CCTV; underground cable and ducts including cable and ducts along the public road to the entrance of the existing Deerpark substation within the townland of Deerparklodge, Carrick-on-Suir, Co. Tipperary and all associated ancillary development works and services. Permission was subsequently granted for three battery storage containers, alterations to the approved planning boundary and the operational permission of the solar farm from 25 to 30 years. Permission is now sought for the following; optimized solar pv panel configuration to comprise of up to 33,203 m2 of solar panels on ground mounted frames; increase to the length of the 20 kV substation from 9.98m to 11.975m to allow installation of required electrical equipment; increase in height to the permitted solar panels from 2.72 m to 2.82m and; permission to increase the operational period of the solar farm from 30 years to 35 years. The site is located in the townlands of Ballynagrana and Deerparklodge, Carrick-on-Suir, Co. Tipperary. A Natura Impact Statement (NIS) accompanies this application. Planning Permission is sought for a period of 10 years

Ballynagrana and Deerparklodge , Carrick-on-Suir , Co. Tipperary

422m
2360554CONDITIONAL26 Jul 2023

a single storey garden polytunnel

Ballyrichard , Carrick On Suir , Co Tipperary

426m
2360524N/A17 Jul 2023

the single storey, garden polytunnel in a total area of 35m2, as is erected on lands of 2.65 ha.

Ballyrichard , Carrick on Suir , Co Tipperary

448m
2360952CONDITIONAL30 Nov 2023

as constructed log cabin and the dog house, including all associated site development works

Ballinagrana , Carrick-on-suir , Co.Tipperary

481m
211304CONDITIONAL1 Sept 2021

detached garage and for change of use of part of the detached garage to workshop for use by our son Conor Whelan as a part time hurley making workshop

Ballynagrana , Carrick-on-Suir , Co. Tipperary

505m
211374N/A16 Sept 2021

build a storey and a half type residence, detached garage, vehicular entrance, septic tank and percolation area and all associated site works

Ballynagrana , Carrick-on-Suir , Co. Tipperary

584m
19601018N/A16 Sept 2019

a single storey extension, bedroom and shower to the side of my dwelling house and all associated site works

Ballynagrana , Carrick-on-Suir , Co. Tipperary

595m
19601148CONDITIONAL17 Oct 2019

a single storey extension, bedroom and shower to the side of my dwelling house and all associated site works

Ballynagrana , Carrick-on-Suir , Co. Tipperary