19655

N/A

Clare - Clare County Council

Proposed Development

for the construction of a new boundary wall and separate new entrance to Northern boundary of site

View the full application file on the council's planning portal →

Application Timeline

  1. Application received

    14 Aug 2019

  2. Further information requested

    4 Oct 2019

  3. Further information received

    11 Dec 2019

  4. Application withdrawn

    13 Jan 2020

Application Details

Location
Ballymorris , Cratloe , Co. Clare
Applicant
N/A
Application Type
PERMISSION
Planning Authority
Clare County Council

Timeline

Registration Date
14 August 2019
Status
WITHDRAWN
Decision
N/A
Withdrawn
13 January 2020

Location

Loading map...

Planning Applications Nearby

What the council has granted and refused around this site is the best guide to how a similar application will fare.

1m
17890CONDITIONAL22 Nov 2017

for the construction of an extension to the side of dwelling house, consisting of an independent living unit, a new detached garage and new boundary walls and entrance piers, with all ancillary site works

Ballymorris , Cratloe , Co. Clare

106m
2560029N/A24 Jan 2025

for development which will consist of a 3.5-metre extension to the existing 21.5 metre-high monopole telecommunications structure (overall height to be 25-metre), carrying antennae and dishes, along with ancillary finial and all ancillary works

ESB Cratloe 38kV Substation , Ballymorris , Shannon Co. Clare

125m
2560196N/A16 Apr 2025

Retention permission (Ref . No. 16651) and permission for development at this site : ESB Telecoms Ltd Compound, ESB Cratloe 38kV Substation, Ballymorris, Shannon, Co. Clare. The development will consist of retaining the existing 21.5 metre-high monopole telecommunications structure and to construct a 3.5-metre extension to the existing 21.5 metre-high monopole telecommunications structure (overall height to be 25-metre), carrying antennae and dishes, along with ancillary finial and all ancillary works.

ESB Cratloe 38kV Substation , Ballymorris , Shannon Co. Clare.

125m
2560366CONDITIONAL20 Jun 2025

the development will consist of retaining the existing 21.5 metre-high monopole telecommunications structure and PERMISSION to construct a 3.5-metre extension to the existing 21.5 metre-high monopole telecommunications structure (overall height to be 25-metre), carrying antennae and dishes, along with ancillary finial and all ancillary works

ESB Telecoms Ltd. Compound , ESB Cratloe 38kV Substation , Ballymorris Shannon Co. Clare

211m
18246CONDITIONAL29 Mar 2018

to construct a dwelling house, wastewater treatment unit and site related works

Ballymorris , Cratloe , Co. Clare

312m
17794CONDITIONAL17 Oct 2017

to convert and extend an existing stable to a habitable unit and upgrade the existing wastewater treatment system and ancillary site works

Ballymorris , Cratloe , Co. Clare

314m
17367REFUSED18 May 2017

to construct a dwelling house & garage with effluent treatment system, new entrance from public road, and all associated site works

Ballymorris , Cratloe , Co Clare

321m
2460447CONDITIONAL18 Sept 2024

to construct a new dwelling house, private garage, site entrance, access road, wastewater treatment system and all associated site works and services

Ballymorris , Cratloe , Co. Clare

348m
2660301CONDITIONAL7 May 2026

for the construction of a garage/workshop, associated concrete area and site works

The Grange Ballymorris , Cratloe , Co. Clare

415m
21975CONDITIONAL15 Sept 2021

the development will consist of a new dwelling house, site entrance, wastewater treatment system and associated site works

Ballymorris , Cratloe , Co Clare

Affected by this application?

Submissions can be made for 5 weeks from the date the application was received. Only material planning grounds count. Build a valid submission letter in minutes.

Make a Submission or Objection

Planning a project of your own?

Find out in two minutes whether you need planning permission. It's free, and based on the exempted development regulations.

Do I Need Permission?