19868
CONDITIONALClare - Clare County Council
Proposed Development
for the erection of a permanent health and safety sign including all ancillary site works at the entrance to Glenmore Wind Farm
View the full application file on the council's planning portal →Application Timeline
Application received
7 Nov 2019
Decision: CONDITIONAL
16 Dec 2019
Decision due
10 Jan 2020
Grant issued
24 Jan 2020
Application Details
- Location
- Glenmore , Kilmihil , Co Clare
- Applicant
- N/A
- Application Type
- PERMISSION
- Planning Authority
- Clare County Council
Timeline
- Registration Date
- 7 November 2019
- Status
- APPLICATION FINALISED
- Decision
- CONDITIONAL
- Decision Date
- 16 December 2019
- Grant Date
- 24 January 2020
- Permission Expires
- 23 January 2025
Location
Planning Applications Nearby
What the council has granted and refused around this site is the best guide to how a similar application will fare.
for the construction of a battery storage compound adjacent to an existing electricity substation, with new palisade fencing, bunded concrete plinths, up to 4 No. storage units and associated equipment, transformers and all ancillary site works. A Natura Impact Statement ( NIS ) has been prepared and included as part of this application
Glenmore , Kilmihil , Co Clare
to construct a new dwelling house with private garage, site entrance, on-site wastewater treatment system and all other associated site works
Glenmore , Kilmihil , Co Clare
for the development of a quarry and all associated site development and infrastructure works and services ( including site office, staff welfare facilities, site boundary treatment, landscaping and site reinstatement ) on a site measuring approximately 1 hectare in the Townland of Glenmore, Kilmihil, Co. Clare. The proposed quarry will have an operational period of ten years after which the site will be reinstated
Glenmore , Kilmihil , Co. Clare
to construct an overhead and underground 20kV grid connection from Booltiagh 110kV substation in the townland of Booltiagh to the proposed Kiltumper Windfarm substation in the townland of Kiltumper. The proposed grid connection will be erected over/under, or in the vicinity of, the townlands of Booltiagh, Boolynaknockaun, Glenmore, Cahermurphy and Kiltumper
Kiltumper Tld , Co. Clare
for development at this site measuring c. 1.42 Ha located within the townland of Booltiagh, Ennis, Co. Clare. The development seeks to amend the Battery Energy Storage System (BESS) development permitted under ref. 23/60414 and the existing permanent 110kV Booltiagh Substation permitted under ref. 00/567 (ACP ref. 120616) amended by ref. 11/340, which are both co-located with the existing and operational Booltiagh wind farm. There are no proposed amendments to the permitted and operational wind farm. The amendments to the permitted BESS will consist of the excavation and removal of 0.36Ha of peat within the proposed fenced BESS enclosure area and the import of equivalent amount of stone to level the site; a revised BESS enclosure to occupy a reduced footprint and layout for the construction and operation of reduced battery array units (32 nos.) with built in inverters resulting in the exclusion of permitted standalone inverters; a revised control & SCADA room, inclusion of 2 no. auxiliary transformer units, 1 no. storage container, and 1 no. standby generator and fuel tank; replacement of permitted MVA transformers with 8 no. MVA Skids (transformers and switchgear); and a revised gated access point and roads; and the installation of a 230m long 20kV underground interconnector cable to connect the BESS control and SCADA room to the existing 110kV Booltiagh substation. The amendments to the permitted 110kV substation will consist of the replacement of the grid transformer in the IPP compound including 110kV circuit breaker, combined CT/VT, disconnector, earth switch and surge arrestors, two post insulators, two auxiliary transformers, one house transformer, one generator and diesel tank and underground cabling trenching; and revisions to permitted ancillary infrastructure layout including security fencing, lighting, lightening masts, two interface kiosks, and CCTV. This application seeks a 10-year duration of planning permission and 35-year duration of operational lifetime of the permitted BESS infrastructure. This development is covered by the provisions of the Renewable Energy Directive III (Directive (EU) 2023/2413) and it is important to note that the planning application may be subject to section 34D of the Planning and Development Act 2000, as amended. When a notice issues in accordance with section 34D(b), the provisions of article 26A of the Planning and Development Regulations 2001 to 2025 shall apply
Booltiagh , Ennis , Co. Clare
the development will consist 10 year planning permission for the construction and operation of battery arrays (240 number units, each 1.87m2 by c. 2.32m tall), a control building with gross floor area 140m2 by 6.40m tall, 3 number 12MVA transformers (c. 3.5m tall), 1 number 2.5MVA transformer (c. 2.5m tall) and inverters (24 number units, each 1.85m2 by c. 2.22m tall. The development will include for ancillary infrastructure including security fencing, lighting, CCTV, internal access roads and drainage. The development will have a 35 year operational lifetime. The overall development site is ca. 1.42 hectares (ha).
Booltiagh , Ennis , Co. Clare
for development which will consist of the installation of battery arrays located within container units (18 number units, each 30m2 by c. 2.6m tall) a control building (c 160.5m2 by c.6.4m tall) and transformer (c. 5m tall). The development will include for ancillary infrastructure including security fencing, lighting, CCTV, Internal access roads & drainage . The overall development site is c.1.4Ha.
Booltigh , Ennis , Co Clare
to Extend the appropriate Period of Planning Permission for P18/555 for development which will consist of the installation of battery arrays located within container units (18 number units, each 30m2 by c. 2.6m tall) a control building (c 160.5m2 by c.6.4m tall) and transformer (c. 5m tall). The development will include for ancillary infrastructure including security fencing, lighting, CCTV, Internal access roads & drainage. The overall development site is c.1.4Ha
Booltiagh , Ennis , Co. Clare
for development which will consist of a 10 year planning permission for the construction and operation of battery arrays (240 number units, each 1.87m2 by c. 2.32m tall), a control building with gross floor area 140m2 by 6.40m tall, 3 number 12MVA transformers (c. 3.5m tall), 1 number 2.5MVA transformer (c. 2.5m tall) and inverters (24 number units, each 1.85m2 by c. 2.22m tall. The development will include for ancillary infrastructure including security fencing, lighting, CCTV, internal access roads and drainage. The development will have a 35 year operational lifetime. The overall development site is ca. 1.42 hectares (ha)
Booltiagh , Ennis , Co. Clare