Application Timeline

  1. Application received

    27 Jun 2019

  2. Further information requested

    21 Aug 2019

  3. Further information received

    17 Feb 2020

  4. Decision: CONDITIONAL

    13 Mar 2020

  5. Decision due

    15 Mar 2020

  6. Grant issued

    15 Jun 2020

Application Details

Location
Polkeen ,
Applicant
N/A
Application Type
PERMISSION
Planning Authority
Galway County Council
Site Area
0.829 ha

Timeline

Registration Date
27 June 2019
Status
APPLICATION FINALISED
Decision
CONDITIONAL
Decision Date
13 March 2020
Grant Date
15 June 2020
Permission Expires
14 June 2025

Location

Loading map...

Planning Applications Nearby

What the council has granted and refused around this site is the best guide to how a similar application will fare.

281m
2260701CONDITIONAL8 Jul 2022

to install a freestanding 6x3m Portakabin to the North side of site. Gross floor area of proposed works:18 sqm.

An Poll Caoin ,

411m
2260675CONDITIONAL1 Jul 2022

to retain dwelling house on revised site boundaries, and permission is also sought to upgrade the existing foulwater treatment system. Gross floor space of works ro be retained 111.00sqm.

Polkeen ,

426m
191839CONDITIONAL28 Nov 2019

for development at Twomileditch quarry. The development will consist of an aggregate storage shed (area 980m2) on a 0.098 hectare site within the existing quarry landholding. Gross floor space of proposed works: 980 sqm

Ballygaurran ,

433m
20753CONDITIONAL18 Jun 2020

for Buildings No. 1, 2, 3 and 4 in the existing warehouse facility at Pollkeen Townland, Ballybrit, Galway, at the premises of SSL in the IDA Business and Technology Park, Parkmore West, Co. Galway for the following works: 1: Additional total floor area of 386.5 sqm comprising of 173 sqm (storage) and 151 sqm (storage) at first floor level and 62.5 sqm at second floor level. b. Building 2: Additional total floor area of 124.1 sqm comprising of 30.9 sqm (office) and 46.6 sqm (storage) at first floor level and 46.6 sqm (storage) at second floor level. c. Building 3: Additional total floor area of 913 sqm comprising of 23 sqm (storage) and 497 sqm (storage) at first floor level and 393 sqm (storage) at second floor level with modifications to the elevations. d. Building 4: Additional floor area of 1528 sqm comprising of 37 sqm (new loading bay) and 610 sqm (offices, storage & welfare facilities) at first floor level and 881 sqm (storage) at second floor level with additional modifications to the elevations. e. All ancillary and/or associated site development works and landscaping that are completed. Gross floor space of work to be retained: 2951.60 sqm

Parkmore West ,

466m
211445CONDITIONAL6 Aug 2021

for the construction of a new warehouse building to include for Warehouse Storage Space, Transit Bond, Loading and Unloading facilities, Meeting Rooms, Staff Rooms, WC's. Offices, Reception with External logo signage on selected elevations having a total floor area of 11,387.2 sqm comprising of the following: - Ground Floor - 6578.6 sqm - First Floor level - 2357.3 sqm - Second Floor level - 2451.3 sqm - The building footprint will include warehouse spaces, transit bond, loading, meeting room, staff rooms, WC's, Offices, Reception, and an External elevation logo signage etc. - Construction of a new 32 sqm ESB MV sub-station and all other service and ancillary site infrastructure required to operate the premises. -Construction of a 19m long (66sqm) Link bridge connecting the existing facility to the proposed new facility on the 1st Floor. - The provision of a new public lighting scheme in the vicinity of the proposed building, a building mounted CCTV system, new car parking facilities, hard and soft landscaping to the remainder of the site area, boundary treatments; Drainage infrastructure and connections to services/utilities; Relocation of the existing ESB power lines and the construction of a new EXB MV sub-station along with all other associated and ancillary development works above and below ground level that are required to complete the project to the required standards and regulations. Gross floor space of proposed works is 11,387.2 sqm

PARKMORE WEST ,

489m
17936CONDITIONAL23 Jun 2017

to extend the existing warehouse facility, at the premises of SSL in the IDA Business and Technology Park. The proposed development will consist of the provision of additional warehouse space with an area of 2156.2sqm, provision of car parking facilities at the development totaling 69 no. car parking spaces, including 2 disabled spaces with associated public lighting, provision of new building-mounted advertising signage with an area of 15.6sqm, provision of 6 no. building mounted floodlights (focused downwards), provision of 4 no. CCTV cameras to security standard requirements, along with all associated ancillary works and site development works required to complete. Gross floor space 2156.2m2

Pollkeen ,

490m
21472CONDITIONAL26 Mar 2021

construction of a new slatted shed with loose bedded area, cattle handling facility and all associated ancillary concrete works. Gross floor space of proposed works 433.05sqm.

Polkeen ,

512m
18550CONDITIONAL1 May 2018

for construction of a single storey extension to the rear of existing single storey house, demolition and rebuild of garage, new sewage treatment system and all associated site works. Gross floor space of proposed works 115 sqm.

Castlegar ,

532m
18116CONDITIONAL12 Apr 2018

Permission to retain and complete part of additional car parking facilities and all associated works. The remaining part of the additional parking area is contained within the functional area of Galway County Galway

Parkmore Industrial Estate , Parkmore , Galway

536m
1886CONDITIONAL22 Mar 2018

Permission to construct a mezzanine floor area within the confines of the existing building including an enclosed external fire escape stairs, and to retain and make alterations to existing elevations including all associated works