20143
REFUSEDCarlow - Carlow County Council
Proposed Development
A 10 year Planning Permission for a solar farm which will connect to the national grid on lands with a total area of circa 127 hectares, consisting of solar panels on ground mounted frames, 28 No. single storey electrical inverter/transformer stations and associated equipment container, security fencing, satellite communications pole, CCTV, upgrading to existing access tracks and new access tracks, temporary construction compounds, landscaping and all associated ancillary development works. Construction and operational access will be via entrances from the L-7111 and L-7112. The operational lifespan of the solar farm will be 35 years. A Natura Impact Statement (NIS) has been prepared and will be submitted to the Planning Authority with the application.
View the full application file on the council's planning portal →Application Timeline
Application received
11 May 2020
Decision due
5 Jul 2020
Decision: REFUSED
16 Jul 2020
Appeal submitted
10 Aug 2020
Grant issued
28 Sept 2021
Appeal decided: CONDITIONAL
28 Sept 2021
Application Details
- Location
- Garreenleen , Bendinstown Tinnaclash and , Ardbearn
- Applicant
- N/A
- Application Type
- PERMISSION
- Planning Authority
- Carlow County Council
Timeline
- Registration Date
- 11 May 2020
- Status
- APPLICATION FINALISED
- Decision
- REFUSED
- Decision Date
- 16 July 2020
- Grant Date
- 28 September 2021
- Permission Expires
- 27 September 2026
An Coimisiún Pleanála Appeal
- Appeal Reference
- ABP-307891-20
- Decision
- CONDITIONAL
- Submitted
- 10 August 2020
- Decided
- 28 September 2021
Location
Planning Applications Nearby
What the council has granted and refused around this site is the best guide to how a similar application will fare.
to apply for a 10 year permission for the proposed development of an underground electricity interconnector cable. The proposed development of the underground electricity interconnector cable will comprise 1 no. 33kV triple circuit cable of c.92 metres in length which is to be installed in an excavated trench including underground ducting and all associated site development and reinstatement works. The proposed development represents a minor revision to the approved layout of the solar farm previously permitted under Carlow County Council planning reference 20/143 and An Bord Pleanala Reference 307891-20 comprising the laying of underground cabling in the previously permitted grassed field area. The purpose of the proposed development is to facilitate the interconnection from the permitted solar farm to a 110kV substation which is the subject to the application to An Bord Pleanala (Reference VA01.313139) A Natura Impact Statement (NIS) has been prepared and will be submitted to the Planning Authority with the application.
Bendinstown , Co. Carlow
a 5-year permission for temporary development at Bendinstown (townland) in County Carlow. The development will consist of the installation of 3 no. single storey porta cabin units for use as office (2 no.) and storage space (1 no.), 6 no. car parking spaces and all associated site development works. The proposed development will serve the Garreenleen Solar Farm Development (as permitted under Carlow County Council Reference 20/143 / An Bord Pleanála Reference ABP-307891-20). The proposed operational development will be accessed via the L7112 local road via the entrance permitted under An Bord Pleanála Reference ABP-313139-22
Bendinstown , (townland) , Co Carlow
a 10 year permission for a Battery Energy Storage system. The proposed development will comprise of the following; A Battery Energy Storage System with associated infrastructure including a new internal access road, approximately 50 metres in length to the permitted Garreenleen Solar Farm (Planning Ref. 22163); An approximately 90 metre 33kV double circuit underground cable grid connection to the permitted Bendinstown 110kV Substation (Planning Ref. ABP–313139), to be installed in an excavated trench including underground ducting; Modular office and welfare buildings; Six steel storage containers and all associated site development and reinstatement works. A Natura Impact Statement (NIS) has been prepared and is included with this planning application.
Within the townlands of Gilbertstown and Bendinstown , Co. Carlow , Ireland
an agricultural entrance & all associated works for access to existing farmyard
Bendinstown , Ballon , Co. Carlow
for a single storey / part storey & half dwelling, septic tank and percolation area, new vehicular entrance, bored well and all associated site works
Ardbearn , Rathoe , Co. Carlow
for a single storey / part storey & half dwelling, septic tank and percolation area, new vehicular entrance, bored well and all associated site works
Ardbearn , Rathoe , Co. Carlow
Permission for retention for an existing single storey garage, planning permission to extend the same with minor alterations to the external façade and alterations to the front porch area to include relocation of front door, additional glazing and all associated site works
Kilnock , Ballon , Co Carlow
for a new vehicular entrance, driveway and all associated site works
Ballynunnery , Rathoe , Co Carlow
single storey dwelling, domestic garage, septic tank and raised percolation area, new vehicular entrance and all associated site works
Ballynunnery , Rathoe , Co. Carlow
the installation of six LED lighting poles (approximately 18 meters in height with a maximum output of 590 lux) to replace and upgrade the existing eight lighting poles, which will be removed, including all associated development works
The Fighting Cocks GAA Club , Kilcoole , Rathoe
Planning a project of your own?
Find out in two minutes whether you need planning permission. It's free, and based on the exempted development regulations.
Do I Need Permission?