ERECTION OF A 20 METRE HIGH, FREE STANDING COMMMUNICATIONS STRUCTURE, CARRYING ANTENNAE AND COMMUNICATION DISHES, WITH ASSOCIATED EQUIPMENT TO FORM PART OF ESB'S COMMUNICATIONS SYSTEM AND TO SHARE WITH OTHER LICENSED OPERATORS WITHIN AN EXISTING COMPOUND

View the full application file on the council's planning portal →

Application Timeline

  1. Application received

    29 Jun 2020

  2. Decision: CONDITIONAL

    20 Aug 2020

  3. Decision due

    23 Aug 2020

  4. Grant issued

    23 Sept 2020

Application Details

Location
ESB'S LETTERKENNY 110KV SUBSTATION , RAROOEY LISTELLIAN , LETTERKENNY
Applicant
N/A
Application Type
PERMISSION
Planning Authority
Donegal County Council
Site Area
0.013 ha

Timeline

Registration Date
29 June 2020
Status
APPLICATION FINALISED
Decision
CONDITIONAL
Decision Date
20 August 2020
Grant Date
23 September 2020
Permission Expires
22 September 2025

Location

Loading map...

Planning Applications Nearby

What the council has granted and refused around this site is the best guide to how a similar application will fare.

2m
1951940N/A16 Dec 2019

ERECTION OF A 20 METRE HIGH, FREE STANDING COMMUNICATIONS STRUCTURE, CARRYING ANTENNAE AND COMMUNICATION DISHES, WITH ASSOCIATED EQUIPMENT TO FORM PART OF ESB'S COMMUNICATION SYSTEM AND TO SHARE WITH OTHER LICENSED OPERATORS WITHIN AN EXISTING COMPOUND

LISTILLION , LETTERKENNY , LETTERKENNY PO

3m
2151761CONDITIONAL3 Sept 2021

ERECTION OF A 18 METER HIGH, FREESTANDING COMMUNICATIONS STRUCTURE WITH LIGHTING FINIAL, CARRYING ANTENNAE AND COMMUNICATION DISHES WITH ASSOCIATD EQUIPMENT TO FORM PART OF ESB'S COMMUNICATION SYSTEM AND TO SHARE WITH OTHER LICENSED OPERATORS WITHIN AN EXISTING COMPOUND

ESB'S LETTERKENNY 110KV SUBSTATION , RAROOEY , LISTELLIAN

4m
2050203N/A25 Feb 2020

ERECTION OF A 20 METRE HIGH, FREE STANDING COMMMUNICATIONS STRUCTURE, CARRYING ANTENNAE AND COMMUNICATION DISHES, WITH ASSOCIATED EQUIPMENT TO FORM PART OF ESB'S COMMUNICATIONS SYSTEM AND TO SHARE WITH OTHER LICENSED OPERATORS WITHIN AN EXISTING COMPOUND

ESB'S LETTERKENNY 110KV SUBSTATION , RAROOEY LISTELLIAN , LETTERKENNY

80m
1750438CONDITIONAL22 Mar 2017

CHANGING THE FACADE AND FENESTRATION OF EXISTING COMMERCIAL GARAGE

LISTELLION , LETTERKENNY , CO. DONEGAL

81m
1850392CONDITIONAL15 Mar 2018

CHANGING THE FACADE AND FENESTRATION OF EXISTING COMMERCIAL GARAGE

LISTELLIAN , LETTERKENNY PO , CO. DONEGAL

85m
1951623CONDITIONAL23 Oct 2019

ADDITIONAL FACADE WITH FENESTRATION ERECTED ON THE NORTHERN SIDE ELEVATION AND PERMISSION FOR ERECTION OF AN ADDITIONAL RETURN FACADE ON THE EASTERN REAR ELEVATION ON THE EXISTING COMMERCIAL GARAGE

LISTELLIAN , LETTERKENNY , LETTERKENNY PO

99m
2560312CONDITIONAL5 Mar 2025

ERECTION OF DWELLING HOUSE WITH SEPTIC TANK AND DOMESTIC GARAGE INCLUDING ALL OTHER ASSOCIATED SITE DEVELOPMENT WORKS

LISTELLIAN , LETTERKENNY , CO. DONEGAL

109m
2562184CONDITIONAL10 Dec 2025

ERECTION OF A STORAGE SHED WITHIN EXISTING YARD INCLUDING ALL OTHER ASSOCIATED SITE DEVELOPMENT WORKS

LISTELLION , LETTERKENNY , CO. DONEGAL

192m
2561152CONDITIONAL7 Jul 2025

A PERIOD OF 10 YEARS FOR DEVELOPMENT AT THE EXISTING ESB NETWORKS 110KV LETTERKENNY SUBSTATION WHICH WILL CONSIST OF: (1) SOUTHWARD EXTENSION OF THE EXISTING ESB NETWORKS 110KV SUBSTATION COMPOUND BY 0.9HA, (2) CONSTRUCTION OF A 110 KV (KILOVOLT) GAS INSULATED SWITCHGEAR (GIS) BUILDING (APPROXIMATELY 82.5M BY 18.5M) MAXIMUM HEIGHT 18.0M, TO REPLACE THE EXISTING 110KV AIR INSULATED SWITCHGEAR (AIS) SUBSTATION, (3) CONSTRUCTION OF 5 NO. 110 KV LINE CABLE INTERFACE MASTS (LCIMS) TO THE SOUTH AND SOUTH-WEST OF THE EXISTING AIS SUBSTATION COMPOUND AND PROPOSED REPLACEMENT GIS BUILDING, WHICH WILL COMPRISE THE END POINT OF THE EXISTING OVERHEAD LINE CIRCUITS ACCESSING THE PROPOSED GIS BUILDING, (4) CONNECTION OF EXISTING TRANSMISSION CIRCUITS TO THE PROPOSED GIS BUILDING BY WAY OF UNDERGROUND CABLES FROM THE NEW LCIMS, (5) DECOMMISSIONING AND REMOVAL OF 7 NO. EXISTING 110 KV TOWERS AND 3 NO. 110KV H POLES, CABLING, BUSBARS, SWITCHGEARS AND SUPPORT STRUCTURES, (6) ERECTION OF 3 NO. LIGHTNING MASTS AT 11M HIGH AT THE REPLACEMENT GIS COMPOUND, (7) TEMPORARY WIDENING (31M) OF THE EXISTING (4M) FIELD GATE ENTRANCE OFF THE L1054 TO FACILITATE A TEMPORARY CONSTRUCTION ACCESS TRACK (204M), PERMANENT ACCESS TO THE DEVELOPMENT WILL CONTINUE AS EXISTING FROM THE SUBSTATION ENTRANCE OFF THE N13 AND (8) ALL ASSOCIATED AND ANCILLARY WORKS, INCLUDING ASSOCIATED GROUND CABLING AND EARTHGRID, 5 NO. CAR PARKING SPACES, SURFACE WATER DRAINAGE, UNDERGROUND WASTEWATER STORAGE TANK, LIGHTING, LANDSCAPING AND BOUNDARY TREATMENT, SITE PREPARATION, SITE CLEARANCE AND LEVELLING, PROVISION OF HARDSTANDING, PERMANENT INTERNAL ACCESS ROAD (505M), 1 NO. TEMPORARY CONSTRUCTION COMPOUND AND 1 NO. TEMPORARY LAYDOWN AREA WITH 20 NO. TEMPORARY CAR PARKING SPACES AND ALL ANCILLARY WORKS, ON AN OVERALL SITE AREA OF 9.3HA. A NATURA IMPACT STATEMENT (NIS) ACCOMPANIES THIS APPLICATION

LISTELLIAN , LETTERKENNY , CO. DONEGAL

239m
2561057CONDITIONAL24 Jun 2025

CONSTRUCTION OF A DOMESTIC GARAGE AND ALL ASSOCIATED SITE DEVELOPMENT WORKS

LISTELLIAN , LETTERKENNY , CO. DONEGAL