20872
CONDITIONALLimerick - Limerick County Council
Proposed Development
the construction of a shared vehicular entrance, dwelling house, garage, domestic waste water treatment system with polishing filter together with all associated site works
View the full application file on the council's planning portal →Application Timeline
Application received
4 Sept 2020
Decision: CONDITIONAL
28 Oct 2020
Decision due
29 Oct 2020
Grant issued
3 Dec 2020
Application Details
- Location
- Turagh , Cappamore , Co. Limerick
- Applicant
- N/A
- Application Type
- PERMISSION
- Planning Authority
- Limerick County Council
- Floor Area
- 262 sq m
- Residential Units
- 2
Timeline
- Registration Date
- 4 September 2020
- Status
- APPLICATION FINALISED
- Decision
- CONDITIONAL
- Decision Date
- 28 October 2020
- Grant Date
- 3 December 2020
- Permission Expires
- 2 December 2025
Location
Planning Applications Nearby
What the council has granted and refused around this site is the best guide to how a similar application will fare.
for an entrance, driveway, dwelling house, domestic waste water treatment system with polishing filter, domestic garage and all associated site works
Turagh , Cappamore , Co Limerick
a two storey extension as constructed to the rear of the existing dwelling and all ancillary site works
Turagh , Cappamore , Co. Limerick
to construct a 5bay double sided slatted unit and all associated site works
Turagh , Cappamore , Co Limerick
development of a grid connection which will consist of the construction of approximately 555 metres of overhead electricity cabling supported on wooden pole sets, the installation of approximately 233 metres of underground electricity cabling in ducting and all other ancillary works including marker posts. The works are required to connect the previously consented Tuogh Solar Farm to the existing 38kV Cappamore Substation. The planning application is accompanied by a Natura Impact Statement
Turagh & Tuogh , Cappamore , Co. Limerick
the construction of a vehicular entrance, dwelling house, domestic garage, connection to main services together with all associated site works
Turagh , Cappamore , Co. Limerick
the demolition of existing garden shed to side of existing dwelling house and for the construction of a replacement garden shed to the rear of the garden together with all associated site works
1 Saint Marys Terrace , Cappamore , Co. Limerick
the proposed development comprising a change of use of commercial/shop building to a dwelling including all necessary alterations and modifications. Permission is also sought to construct 2 No. modular designed detached dwelling units on the site of the former petrol filling station, connection to public services, provision of off street car parking and plot boundaries including all associated site development works
Turagh , Cappamore , Co. Limerick
the demolition of existing rear extensions, construction of a new two-storey rear extension and all ancillary site works
13 St. Marys Terrace (Previously 12 St. Mary's Terrace) , Cappamore , Co. Limerick
an extension to existing dwelling and ancillary works
Turagh , Cappamore , Co. Limerick
the construction of new 22-unit housing development consisting of the following: 6 No 4 bedroom detached dwellinghouses, 2 No 3-bedroom semi-detached dwellinghouses, 10 No 3 bedroom townhouses, and 4 no 2 bedroom townhouses, new vehicular entrance, storm and surface water sewers including attenuation system, public lighting, boundary walls, footpaths, open spaces, new entrance to existing dwellinghouse to the north west together with all other ancillary site works
Moore Street , Turagh , Cappamore