211226

REFUSED

Clare - Clare County Council

Proposed Development

for a ten-year planning PERMISSION for the construction of a renewable energy development at this site, in the townlands of Glendine North, Fahanlunaghta More, Curraghodea, Letterkelly, Cloghaun More, Tooreen, Silverhill, Doonsallagh East and Knockalassa, Co. Clare (approximately 6.5km to the east of Miltown Malbay). The development will consist of the provision of the following: 1. 8 No. wind turbines with an overall ground-to-blade tip height in the range of 175 metres maximum to 173 metres minimum; a blade length in the range of 75 metres maximum to 66.5 metres minimum; and hub height in the range of 108.5 metre maximum to 100 metres minimum; 2. A thirty-year operational life from the date of full commissioning of the development and subsequent decommissioning; 3. A Meteorological Mast with a height of 30 metres; 4. All associated underground electrical cabling (33kV) connecting the proposed turbines via Ring Main Unit (RMU) to the 110kV substation in the townland of Knockalassa; 5. Permanent extension to the 110kV substation at Knockalassa comprising extension to the existing substation compound, provision of a new control building with welfare facilities and all associated electrical plant and equipment for an additional 110kV bay and security fencing; 6. Upgrade of access junctions; 7. Upgrade of existing tracks/roads and provision of new site access roads and hardstand areas; 8. 2 no. borrow pits; 9. 2 no. temporary construction compounds; 10. Site Drainage; 11. Forestry Felling; 12. Operational stage site signage; and 13. All associated site development ancillary works and apparatus. The Proposed Development will have an operational life of 30 years from the date of commissioning of the development and the application seeks a ten-year planning permission. An Environmental Impact Assessment Report (EIAR) and a Natura Impact Statement (NIS) has been prepared in respect of the proposed development and will be submitted to the planning authority with the application

View the full application file on the council's planning portal →

Application Timeline

  1. Application received

    18 Nov 2021

  2. Decision: REFUSED

    20 Jan 2022

  3. Decision due

    21 Jan 2022

  4. Appeal submitted

    14 Feb 2022

  5. Appeal decided: REFUSED

    16 May 2024

Application Details

Location
Glendine North Fahanlunaghta More Curraghodea , Letterkelly Cloghaun More Tooreen Silverhill , Doonsallagh East and Knockalassa Co Clare
Applicant
N/A
Application Type
PERMISSION
Planning Authority
Clare County Council
Floor Area
1 sq m
Residential Units
1

Timeline

Registration Date
18 November 2021
Status
APPLICATION FINALISED
Decision
REFUSED
Decision Date
20 January 2022

An Coimisiún Pleanála Appeal

Appeal Reference
ABP-312728-22
Decision
REFUSED
Submitted
14 February 2022
Decided
16 May 2024

Location

Loading map...

Planning Applications Nearby

What the council has granted and refused around this site is the best guide to how a similar application will fare.

16m
21370REFUSED19 Apr 2021

for a ten-year planning permission for the construction of a renewable energy development, in the townlands of Glendine North, Fahanlunaghta More, Curraghodea, Letterkelly, Cloghaun More, Cloghaun Beg, Tooreen, Silverhill, Doonsallagh East, Shavavogh East and Knockalassa, Co Clare (approximately 6.5km to the east of Miltown malbay), The development will consist of the provision of the following I. Up to 8 no. wind turbines with a maximum overall ground to blade tip height of up to 175 metres; ii. A thirty-year operational life from the date of full commissioning of the development and subsequent decommissioning. iii. A Meteorological mast with a maximum height of up to 30 metres; iv. Underground cabling (33kV) connecting the proposed turbines to an existing 110kV substation in the townland of Knockalassa; v. Permanent extension to the 110kV substation at Knockalassa comprising of a new control building with welfare facilities, associated electrical plant and equipment and security fencing; vi. Upgrade of access junctions; vii. Upgrade of existing tracks/ roads and provision of new site access roads and hardstand areas; viii. 2 no. borrow pits; ix. 2 no. temporary construction compounds; x. Site drainage; xi. Forestry felling; xii. Operational stage site signage; and xiii. All associated site development works and apparatus. An Environment Impact Assessment Report (EIAR) and a Natura Impact Statement (NIS) have been prepared in respect of the proposed development

Glendine North Fahanlunaghta More Curraghodea , Letterkelly Cloghaun More Cloghaun Beg Tooreen Silverhill , Doonsallagh East Shanavogh East and Knockalassa Co Clare

117m
20806N/A3 Nov 2020

for a 10-year planning permission for the construction of a renewable energy development, in the townlands of Glendine North, Fahanlunaghta More, Curraghodea, Letterkelly, Cloghaun More, Cloghaun beg, Silverhill, Doonsallagh East, Shanavogh East and Knockalassa, Co Clare (approximately 6.5km to the east of Miltown Malbay). The development will consist of the provision of the following: i. Up to 8 No. wind turbines with a maximum overall ground to blade tip height of up to 175 metres; ii. A thirty-year operational life from the date of full commissioning of the development and subsequent decommissioning. iii. A Meteorological Mast with a maximum height of up to 110 metres; iv. Underground cabling (33kV) connecting the proposed turbines to an existing 110kV substation in the townland of Knockalassa; v. Permanent extension to the 110kV substation at Knockalassa comprising of a new control building with welfare facilities, associated electrical plant and equipment and security fencing; vi Upgrade of access junctions; vii Upgrade of existing tracks/ roads and provision of new site access roads and hardstand areas; viii. 2 no. borrow pits; ix 2 no. temporary construction compounds; x. Site Drainage; xi Forestry Felling; xii. Operational stage site signage; and xiii. All associated site development works and apparatus. An Environmental Impact Assessment Report (EIAR) and a Natura Impact Statement (NIS) have been prepared in respect of the proposed development.

Glendine North Fahanlunaghta More , Curraghodea LetterKelly Cloghaun More Cloghaun Beg , Silverhill Doonsallagh East Shanavogh East and Knockalassa Co. Clare

1.2km
25406CONDITIONAL22 Dec 2025

for development of a livestock slatted unit with associated ancillary siteworks

Letterkelly , Miltown Malbay , Co. Clare

1.7km
22129CONDITIONAL15 Feb 2022

to upgrade / improve existing access road for the purposes of extracting timber

Cloughaun More Td , Miltown Malbay , Co Clare

1.9km
17528CONDITIONAL6 Jul 2017

to RETAIN the changes to the original cottage and for PERMISSION to alter the fenestration to the first floor windows

Fahanlunaghtamor , Fahamor , Miltown Malbay

2.0km
2660090N/A20 Feb 2026

to restore existing dwelling and construct a new single storey extension to the rear, to install a waste water treatment system, construct a driveway and all ancillary works

Fahanlunaghtamore , Miltown Malbay , Co. Clare

Planning a project of your own?

Find out in two minutes whether you need planning permission. It's free, and based on the exempted development regulations.

Do I Need Permission?