21138
CONDITIONALRoscommon - Roscommon County Council
Proposed Development
to construct dwelling house along with domestic garage, new treatment system and percolation area and all ancillary site development works at
View the full application file on the council's planning portal →Application Timeline
Application received
18 Mar 2021
Decision due
12 May 2021
Decision: CONDITIONAL
12 May 2021
Grant issued
16 Jun 2021
Application Details
- Location
- Ballyfeeny , Parkowen , Co Roscommon
- Applicant
- N/A
- Application Type
- PERMISSION
- Planning Authority
- Roscommon County Council
- Site Area
- 0.367 ha
- Floor Area
- 271 sq m
- Residential Units
- 1
Timeline
- Registration Date
- 18 March 2021
- Status
- APPLICATION FINALISED
- Decision
- CONDITIONAL
- Decision Date
- 12 May 2021
- Grant Date
- 16 June 2021
- Permission Expires
- 15 June 2026
Location
Planning Applications Nearby
What the council has granted and refused around this site is the best guide to how a similar application will fare.
Retention Permission for 1. Retention of existing agricultural gate and entrance from public road (R-371). 2. Retention of an existing hardstanding surface and fencing on lands at
Ballyfeeny Townland , Kilglass , Co. Roscommon.
to construct domestic house, along with treatment system and all ancillary site developments works at
Ballyfeeny , Kilglass , Co. Roscommon
Retention Permission for the following: 1. Seek for temporary retention of a specialized support unit for a period of 7 years. The unit is used for ancillary therapeutic and educational purposes in support of a state-mandated Foster Care Program. 2. Retention of the existing wastewater connection from this unit to the on-site treatment system. 3. Retain minor elevational alterations to 2 existing outbuildings: Outbuilding 1: Enclosure of the front elevation with new blockwork wall and new entrance door; Outbuilding 2: Installation of a new lean-to roof structure. 4. Revise site boundary originally granted under Planning Ref. 20/243 at
Ballyfeeny Townland , Kilglass , Co. Roscommon
Permission to 1. Seek for Temporary Retention (Personal Condition, under Section 34 of the Act) of a Specialized Support Unit for a period of 7 years. The unit is used for ancillary therapeutic and educational purposes in support of a state-mandated Foster Care Program. 2. Retention of the existing wastewater connection from this unit to the on-site treatment system. 3. Retain minor elevational alterations to 2 existing outbuildings at
Ballyfeeny Townland , Kilglass , Co. Roscommon
Retention Permission & Permission for the following: 1. Seek for Temporary Retention of a Specialized Support Unit for a period of 7 years. The unit is used for ancillary therapeutic and educational purposes in support of a state-mandated Foster Care Program. 2. Retention of the existing wastewater connection from this unit to the on-site treatment system. 3. Retain minor elevational alterations to 2 existing outbuildings: Outbuilding 1: Enclosure of the front elevation with new blockwork wall and new entrance door; Outbuilding 2: Installation of a new lean-to roof structure. 4. Revise Site boundary originally granted under Planning Ref. 20/243 at
Ballyfeeny Townland , Kilglass , Co. Roscommon
Planning permission is sought for proposed demolition of existing water tower, proposed extension to the front, side and rear of existing school building to include construction of 1 No. classroom, ancillary room/WC, entrance area, staff area with changes to existing pedestrian access to front, drainage and all ancillary site works all at
Ballyfeeney National School , Ballyfeeney , Scramogue
to construct an agricultural shed for seasonal storage of organic fertilisers along with soiled water containment tank, concrete apron and all ancillary site works at
Ballyfeeney , Scramogue , Co. Roscommon.
Permission for development consisting of: • The construction and operation of a wind farm consisting of six wind turbines; • The turbine specification is unconfirmed but will fall within the parameter range outlined by Roscommon County Council and will be one of the following three Options; - Technology Option 1: tip height of 160m, rotor diameter of 136m and hub height of 92m; or - Technology Option 2: tip height of 156m, rotor diameter of 133m and hub height of 90m; or - Technology Option 3: tip height of 159m, rotor diameter of 138m and hub height of 90m; • Construction of turbine hardstands (including crane and assembly areas) and turbine foundations; • Construction of approximately 3.9km of new permanent internal site access tracks and the upgrade of 0.5km of existing internal site access tracks; • Construction of a permanent onsite 38kV electrical substation, including one single storey substation building with welfare facilities, Lidar, diesel generator and fuel storage tank, all associated electrical plant and equipment, all associated underground cabling, rainwater harvesting and storage tank, wastewater holding tank, security fencing, gates, signage, and all ancillary structures and works; • Installation of underground electrical and communications cabling connecting the wind turbines to the proposed onsite 38kV electrical substation; • Construction of two temporary site compounds with associated site offices, welfare facilities, car parking, site fencing and lighting; • Erection of a permanent 30m high communications relay tower; • Construction access via six site entrances (SE1 – SE6) to include: - SE1 on the R371, SE2 and SE3 on the L6018, and SE4, SE5 and SE6 on the L60498; - SE1 and SE6 are temporary and will be reinstated following construction. SE1 may be re-established if required for turbine component repair or replacement. SE2 – SE5 will be retained permanently for operational access; • Tree felling to facilitate the construction and operation of the proposed development; • Installation of approximately 5.1km of permanent underground electrical cabling for the grid connection including cabling within the public road corridor, extending from the proposed onsite 38kV electrical Substation at Ballyfeeny to end at the junction of the R371 and the Sliabh Bawn Substation Road in the townland of Tooreen; • All associated site works, including site clearance, landscaping, site drainage, s
Pollymount Bellanamullia Scramoge , Treanaceeve and Ballyhubert , County Roscommon.
To construct a new 4 bay double sided slatted cattle shed, to include both slatted and solid floored lying area, together with all associated site works at
Ballyfeeny Td. , Strokestown , Co. Roscommon
a change of house design to that granted under Planning Reference PD/15/362 and all ancillary works at
Tully , Kilglass , Co.Roscommon
Planning a project of your own?
Find out in two minutes whether you need planning permission. It's free, and based on the exempted development regulations.
Do I Need Permission?