The Register of Planning Applications · Éire

Monday 31 August 2026

← Back to search

2139886

CONDITIONAL

Cork - Cork City Council

Proposed Development

Permission for the installation of a 199kWp rooftop solar photovoltaic array (984m2) on the roof of the existing Avoncourt factory building consisting of 585 No. 340Wp JA Solar panels mounted directly on the roof surface, electrically connected to the existing electrical plant room via 4 no. Solis inverters mounted on the wall of the existing plant room, to the rear of the existing factory building and all associated work.

View the full application file on the council's planning portal →

Application Timeline

  1. Application received

    4 Feb 2021

  2. Decision: CONDITIONAL

    28 May 2021

  3. Decision due

    31 May 2021

  4. Grant issued

    9 Jul 2021

Application Details

Location
Avoncourt Packaging Ltd , Unit 2 , Ballycurreen Industrial Estate
Applicant
N/A
Application Type
PERMISSION
Planning Authority
Cork City Council

Timeline

Registration Date
4 February 2021
Status
APPLICATION FINALISED
Decision
CONDITIONAL
Decision Date
28 May 2021
Grant Date
9 July 2021

Location

Loading map...

Planning Applications Nearby

What the council has granted and refused around this site is the best guide to how a similar application will fare.

1m
2241608CONDITIONAL6 Dec 2022

Permission for the installation of a 215.8 kWp Rooftop Solar Photovoltaic Array extension (circa 1,020m2), consisting of circa 520 No. panels, to an existing Rooftop Solar Photovoltaic Array (circa 1032m2), with the proposed panels mounted directly on the roof surface, electrically connected to the existing electrical plant room via 4 No. inverters mounted on the wall of the existing plant room, located to the rear of the existing factory building and all associated work.

Avoncourt Packaging Ltd , Unit 2 Ballycurreen Industrial Estate , Airport Road

99m
2140420CONDITIONAL11 Aug 2021

Permission to extend the temporary permission Planning Ref 18/07022 as granted to Construct a temporary 500 m2 Single storey Computer Equipment storage building for a further 3 year period including all ancillary site works

Balycurreen Industrial Estate , Ballycurreen , Kinsale Road

99m
187022CONDITIONAL19 Nov 2018

To construct a temporary 500 m2 single storey computer equipment storage building for a 3 year period including all ancillary site works

Ballycurreen Industrial Estate , Ballycurreen , Kinsale Road

111m
184209N/A29 Jan 2018

Construction of and ESB substation and transformer base.

Ballycurreen Industrail Estate , Ballycurreen , Co. Cork

111m
184430CONDITIONAL20 Feb 2018

Construction of an ESB substation and transformer base.

Ballycurreen Industrial Estate , Ballycurreen , Co. Cork

142m
2240863CONDITIONAL9 Feb 2022

Permission for the installation of a 516.8kWp rooftop solar photovoltaic array on the roof of an existing factory building consisting of 1,276 No. 405Wp Suntech Power panels mounted directly on the roof surface, electrically connected to the existing electrical plant room and inverters mounted on the wall of the existing plant room, and all associated work.

Unit 21A , Ballycurreen Industrial Estate , Kinsale Road

178m
2241671CONDITIONAL22 Dec 2022

Permission for the installation of an circa 336.98 kWp Rooftop Solar Photovoltaic Array consisting in combination of circa 812 no. panels (circa 1,599.64m2) partially extending to an existing Rooftop Solar Photovoltaic Array (circa 2,513.72m2) located on Unit 21A, Ballycurreen Industrial Estate, Kinsale Road, Cork, with the extension situated on the most southern roof area of this industrial building; and partially on a vacant roof area located on an adjacent industrial building located to the North East, at Ballycurreen Industrial Estate, Kinsale Road, Cork, T12R866, with all the proposed panels mounted directly on the roof surface of the buildings and electrically connected to the existing electrical plant rooms via a combined total of 4 no. inverters mounted on the wall of the existing plant rooms, and all associated site works.

Unit 21A Ballycurreen Industrial Estate , Kinsale Road Cork and , Industrial building at Ballycurreen

201m
186209CONDITIONAL21 Aug 2018

Retention of an existing 20 metre telecommunications structure with antenna and dishes attached, associated equipment and fencing

Tidy Mechanical Services , Ballycurreen Industrial Estate , Kinsale Road

209m
2443160CONDITIONAL6 Aug 2024

Permission is sought for the retention of elevational and internal changes, including the addition of two mezzanine storage areas, from that granted in planning 96731, retention of change of use from a warehouse to a light industrial use (laundry facility), retention of two external prefabricated buildings, retention of two external storage tanks, retention of wall mounted signage and permission for demolition of the two aforementioned external prefabricated buildings and permission for a single-storey 400m2 extension and a canopy roofed area to north elevation and all associated site works.

Ashton Linen Service Ltd. , Ballycurreen Industrial , Estate Ballycurreen

214m
2140464CONDITIONAL1 Sept 2021

Permission to construct side extension to existing commercial unit, together with dock leveller and associated site works.

Montara House , Ballycurreen Industrial Estate , Kinsale Road

Planning a project of your own?

Find out in two minutes whether you need planning permission. It's free, and based on the exempted development regulations.

Do I Need Permission?