The Register of Planning Applications · Éire

Monday 31 August 2026

← Back to search

21511

CONDITIONAL

Kerry - Kerry County Council

Proposed Development

RETAIN (A) DWELLING HOUSE AS CONSTRUCTED ON SITE AND (B) DOMESTIC GARAGE AS CONSTRUCTED, AND ALL ASSOCIATED SITE WORKS WITHIN REVISED SITE BOUNDARIES

View the full application file on the council's planning portal →

Application Timeline

  1. Application received

    13 May 2021

  2. Further information requested

    6 Jul 2021

  3. Further information received

    30 Nov 2021

  4. Decision: CONDITIONAL

    13 Jan 2022

  5. Decision due

    14 Jan 2022

  6. Grant issued

    16 Feb 2022

Application Details

Location
GURTEENAVALLIG , TARBERT , CO KERRY
Applicant
N/A
Application Type
RETENTION
Planning Authority
Kerry County Council
Site Area
0.169 ha
Floor Area
1 sq m
Residential Units
1

Timeline

Registration Date
13 May 2021
Status
APPLICATION FINALISED
Decision
CONDITIONAL
Decision Date
13 January 2022
Grant Date
16 February 2022
Permission Expires
15 February 2027

Location

Loading map...

Planning Applications Nearby

What the council has granted and refused around this site is the best guide to how a similar application will fare.

984m
17466CONDITIONAL22 May 2017

FOR THE MODIFICATION OF THE PERMITTED NORTHERN ACCESS, JUNCTION TO LEANAMORE WIND FARM, (PREVIOUSLY GRANTED UNDER PLANNING REG. NO. 11/299). THE MODIFICATION INCLUDES THE MOVEMENT OF THE PERMITTED JUNCTION 50M DUE SOUTH IN ORDER TO FACILITATE IMPROVED ACCESS

MEELCON AND GURTEENAVALLIG , BALLYLONGFORD , CO KERRY

1.0km
18117CONDITIONAL14 Feb 2018

RETAIN DWELLING HOUSE AND WASTE WATER TREATMENT UNIT AND TO MODIFY 1 OF PLANNING REF NO 05/3732 BY REMOVING CONDITION 1(a)

DOONCAHA , TARBERT , CO KERRY

1.3km
2011CONDITIONAL13 Jan 2020

(A) DEMOLISH EXISTING SLATTED CUBICLE HOUSE (EXISTING SLATTED TANKS TO REMAIN) (B) CONSTRUCT IN ITS PLACE A NEW EASY FEED SLATTED LIVESTOCK UNIT

DOONCAHA , TARBERT , CO KERRY

1.3km
20325CONDITIONAL7 Apr 2020

(A) CONSTRUCT A NEW MILKING COMPLEX INCORPORATING COVERED DRAFTING AREA, FLOW CHANNEL AND COLLECTING YARD. COLLECTING YARD TO INCORPORATE SLATTED TANK WITH EXTERNAL AGITATION (B) ERECT A MEAL BIN

DOONCAHA , TARBERT , CO KERRY

1.4km
20438REFUSED15 May 2020

AMEND A PREVIOUSLY GRANTED PERMISSION (KERRY COUNTY COUNCIL PLANNING REF 19/381) ( AN BORD PLEANALA REF ABP- 304807-19) WHICH RELATES TO A CHANGE IN THE GRID CONNECTION ROUTE FOR THE PERMITTED WIND FARM. THE REVISED ROUTE WILL ENTAIL THE CONSTRUCTION OF APPROXIMATELY 12.1KM OF 38KV UNDERGROUND ELECTRIC CABLE CONNECTING THE EXISTING PERMITTED WINDFARM (19/381) TO THE 38Kva/110Kva SUBSTATION AT KILPADDOGE, TARBERT. THE UNDERGROUND CABLES WILL BE LOCATED ALONG THE PUBLIC ROADS R551, R552 AND L-1010 AND ALONG 2 SECTIONS OF PRIVATE PROPERTY. THE CABLE WILL BE INSTALLED IN EXCAVATED TRENCHES APPROXIMATELY 1.2M IN DEPTH AND WILL INCLUDE ASSOCIATED UNDERGROUND DUCTING JOINT BAYS, COMMUNICATION CHAMBER BAYS, DRILL PITS, SHEATH LINK BOXES AND INSPECTION CHAMBERS, ASSOCIATED EQUIPMENT AND ALL ANCILLARY SITE AND GROUND WORKS. THE DEVELOPMENT WILL ALSO CONSIST OF THE CONNECTION OF THE PERMITTED WINDFARM (19/381), VIA EXISTING PERMITTED UNDERGROUND ELECTRICITY CABLES, TO THE PROPOSED CABLE.THE UNDERGROUND CABLE WILL BE LOCATED IN THE TOWNLANDS OF BALLYLINE WEST, BALLYMACASY, LISLAUGHTIN, GLANCULLARE SOUTH, GURTEENAVALLIG,MEELCON CARHOONA, FARRANAWANA, DOONARD UPPER, DOONARD LOWER TARBERT AND KILPADDOGE ' THE APPLICANT IS SEEKING A TEN YEAR PLANNING PERMISSION AND OPERATIONAL PERIOD OF 25 YEARS. AN APPROPRIATE ASSESSMENT SCREENING REPORT AND AN ENVIRONMENTAL IMPACT ASSESSMENT SCREENING REPORT HAS BE PREPARED AND SUBMITTED AS PART OF THIS APPLICATION. AN NIS HAS BEEN SUBMITTED WITH THIS APPLICATION

MEELCON CARHOONA FARRANAWANA TARBERTDOONARD UPPER AND LOWER KILPADDOGE BALLYLINE WEST BALLYMACASY LISLAUGHTIN GLAMCULLARE SOUTH GURTEENAVALLIG , CO KERRY

1.4km
25107CONDITIONAL30 Apr 2025

(A) EXTENSIONS TO THE NORTH, EAST AND WEST ELEVATIONS (B) DORMER TYPE ROOF WINDOW ON THE WEST ELEVATION, (C) ALTERATIONS TO THE FRONT, NORTH AND EAST ELEVATIONS, (D) DWELLING HOUSE AS ERECTED WITHIN REVISED SITE BOUNDARIES

GLANCULLARE SOUTH , TARBERT , CO KERRY

1.5km
17339CONDITIONAL18 Apr 2017

MODIFY THE ALIGNMENT OF A 210M LONG SECTION OF PERMITTED WIND FARM ACCESS ROAD AND ASSOCIATED DRAINAGE (PREVIOUSLY GRANTED UNDER PLANNING REG 11/299). THE MODIFICATION CONSISTS OF MOVING THE ALIGNMENT OF THE ROAD SOUTH WEST BY A MAXIMUM DISTANCE OF 25M.

LEANAMORE AND LISLAUGHTIN , BALLYLONGFORD , CO KERRY

1.7km
2460229CONDITIONAL19 Apr 2024

Retention of house, storage shed, treatment unit and sandcell polishing filter and revised site boundaries

Dooncaha , TARBERT , Tarbert

1.9km
201244CONDITIONAL18 Dec 2020

RETAIN TWO STOREY SIDE EXTENSION TO DWELLING AND PLANNING PERMISSION TO DEMOLISH EXISTING DOMESTIC GARAGE AND ERECT A TWO STOREY EXTENSION TO DWELLING HOUSE

SALLOWGLEN , TARBERT , CO KERRY

Planning a project of your own?

Find out in two minutes whether you need planning permission. It's free, and based on the exempted development regulations.

Do I Need Permission?