EXTENSION of DURATION of planning application 07/3078 Modifications to design of block D that forms part of previously approved planning permission ref: 03/4247 - modifications include replacing the 6 no. 4 bed townhouses with 19 apartments (5 No 1 bed and 14 no 2 bed) in 3-4 storey block. Modifications to internal site layout, car parking, bin stores and increase in amount of green open space to complete overall development of 87 apartments at
View the full application file on the council's planning portal →Application Timeline
Application received
28 Oct 2021
Further information requested
21 Dec 2021
Application withdrawn
16 Sept 2022
Application Details
- Location
- Lower Docks , Big Meadow , Athlone
- Applicant
- N/A
- Application Type
- EXTENSION OF DURATION
- Planning Authority
- Westmeath County Council
Timeline
- Registration Date
- 28 October 2021
- Status
- WITHDRAWN
- Decision
- N/A
- Withdrawn
- 16 September 2022
Location
Planning Applications Nearby
What the council has granted and refused around this site is the best guide to how a similar application will fare.
The development will consist of: • Permission for the removal of an existing vent stack which is a protected structure, reference 074 in the planning authority’s Record of Protected Structures • Permission for installation of a replacement vent stack and associated pipework and ancillary site works
Townland of Athlone And Bigmeadow , Deerpark Road / Lyster Street , Athlone Co. Westmeath.
We, Irish Water, intend to apply for Planning Permission for development of new sewers in Athlone, Co. Westmeath on Deer Park Road in Doovoge Td, through Athlone Showgrounds in Athlone & Big Meadow Td and across the River Shannon River to the east bank in Burges Park in Golden Island (Kilmaine) Td. The development will consist of the following: A new 450mm diameter open cut combined sewer on Deer Park Road constructed within a 10m wide construction corridor.A new combined tunnel sewer, up to 1200mm diameter, through the Showgrounds from Deer Park Road to the West bank of the River Shannon constructed within a 10m wide construction corridor.A new combined tunnel sewer (Lower Shannon Sewer Crossing), up to 1500mm diameter, that runs underneath the River Shannon to the east bank in Burgess Park at Golden Island constructed within a 10m wide construction corridor.1 No. Tunnel Shafts and associated temporary works construction compound in Burgess Park in Golden Island(Kilmaine Townland). 4 no Tunnel Shafts and associated temporary works construction compounds west of the Shannon in Athlone Showgrounds and in Athlone & Big Meadow and Townland. 2 no Tunnel Shafts and associated temporary works construction compounds on Deerpark Road in Athlone & Big Meadow Townland and Doovoge Townland. Decommissioning and demolition of the existing West Side Pumping Station.Temporary construction access road along the sewer route in Athlone Showgrounds. Temporary construction access thourgh Burgess Park. Decommissioning and demolition of the existing siphon inlet chamber and storm overflow chamber,And all associated site works. A Natura impact statement will be submitted to the planning authority with the application.
Deerpark Road Doovoge Td , Athlone Showgrounds & Big Meadow , Rvier Shannon & Golden Island
We, Irish Water, intend to apply for Planning Permission for development of new sewers in Athlone, Co. Westmeath on Deerpark Road in Doovoge Townland, through Athlone Showgrounds in Athlone & Big Meadow Townland and across the River Shannon River to the east bank in Burges Park in Golden Island (Kilmaine) Townland. The development will consist of the following: A new 450mm diameter open cut combined sewer on Deerpark Road constructed within a 10m wide construction corridor.A new combined tunnel sewer, up to 1200mm diameter, through the Showgrounds from Deerpark Road to the West bank of the River Shannon constructed within a 10m wide construction corridor.A new combined tunnel sewer (Lower Shannon Sewer Crossing), up to 1500mm diameter, that runs underneath the River Shannon to the east bank in Burgess Park at Golden Island constructed within a 10m wide construction corridor.1 No. Tunnel Shafts and associated temporary works construction compound in Burgess Park in Golden Island(Kilmaine Townland). 3 no Tunnel Shafts and associated temporary works construction compounds west of the Shannon in Athlone Showgrounds and in Athlone & Big Meadow and Townland. 2 no Tunnel Shafts and associated temporary works construction compounds on Deerpark Road in Athlone & Big Meadow Townland and Doovoge Townland. Decommissioning and demolition of the existing West Side Pumping Station.Temporary construction access road along the sewer route in Athlone Showgrounds. Temporary construction access thourgh Burgess Park. Decommissioning and demolition of the existing siphon inlet chamber and storm overflow chamber,And all associated site works. A Natura impact statement will be submitted to the planning authority with the application.
Deerpark Road Doovoge Townland , Athlone Showgrounds in Athlone & Big Meadow Townland , River Shannon Golden Island (Kilmaine) Td
We, Irish Water, intend to apply for Planning Permission for development of new sewers in Athlone, Co. Westmeath on Deerpark Road in Doovoge Townland, through Athlone Showgrounds in Athlone & Big Meadow Townland and across the River Shannon River to the east bank in Burgess Park in Golden Island (Kilmaine) Townland. The development will consist of the following: A new 450mm diameter open cut combined sewer on Deerpark Road and Clonown Road constructed within a works construction area. A new combined tunnel sewer, up to 1200mm diameter, through the Showgrounds from Deerpark Road to the West bank of the River Shannon constructed within a 10m wide construction corridor.A new combined tunnel sewer (Lower Shannon Sewer Crossing), up to 1500mm diameter, that runs underneath the River Shannon to the east bank in Burgess Park at Golden Island constructed within a 10m wide construction corridor.1 No. Tunnel Shaft and associated temporary works construction compound in Burgess Park in Golden Island (Kilmaine) Townland. 3 no Tunnel Shafts and associated temporary works construction compounds west of the Shannon in Athlone Showgrounds and in Athlone & Big Meadow and Townland. 2 no Tunnel Shafts and associated temporary works construction compounds on Deerpark Road in Athlone & Big Meadow Townland and Doovoge Townland. Decommissioning and demolition of the existing West Side Pumping Station.Temporary construction access road along the sewer route in Athlone Showgrounds. Temporary construction access thourgh Burgess Park. Decommissioning and demolition of the existing siphon inlet chamber and storm overflow chamber,And all associated site works. A Natura impact statement will be submitted to the planning authority with the application.
Athlone Co Westmeath on Deerpark Road in Doovoge Townland , through Athlone Showgrounds in Athlone & Big Meadow and across The River Shannon , to the east in Burgess Park in
Development of new sewers which will consist of: A new 450mm diameter open cut combined sewer on Deerpark Road and Clonown Road constructed within a works construction area. A new combined tunnel sewer up to 1200mm diameter, through the Showgrounds from Deerpark Road to the west bank of the River Shannon constructed within a 10m wide works construction area. A new combined tunnel sewer (Lower Shannon Sewer Crossing), up to 1500mm diameter, that runs underneath the River Shannon to the east bank in Burgess Park at Golden Island constructed within a 10m wide works construction area. 1 No. Tunnel Shaft and associated temporary works construction compound in Burgess Park in Golden Island (Kilmaine) Townland. 3 No Tunnel Shafts and associated temporary works construction compounds west of the Shannon in Athlone Showgrounds and in Athlone & Bigmeadow Townland. 2 No. Tunnel Shafts and associated temporary works construction compounds on Deerpark Road in Athlone & Bigmeadow Townland and Doovogue Townland. Decommissioning and demolition of the existing West Side Pumping Station. Temporary construction access road along the sewer route in Athlone Showgrounds. Temporary construction access road through Burgess Park. Decommissioning and demolition of the existing siphon inlet chamber and storm overflow chamber. And all associated site works. A Natura Impact Statement will be submitted to the Planning Authority with the Application.
Deerpark Road in Doovoge Townland , through Athlone Showgrounds in Athlone , & Bigmeadow Townland and
Retention of conversion of attic space into a bedroom and en-suite, within third floor of the existing townhouse together with associated rooflights and site works
31 Shannon Weir , Athlone , Co Westmeath
Retention planning permission to retain a change of use from former parochial house to Air B&B and planning permission to construct an extension to the rear of the house at ground floor level to be used ancillary to Air B&B and all associated site works
The Callows , Deer Park Road , Athlone
Removal of all chimneys to blocks A, B, C, D & E at Shannon Weir
Shannon Weir , The Quay , Athlone
A) Retention for the removal of 5 chimneys total, 3 from block E, 1 from block D and 1 from block B B) Permission is sought for the removal of all other chimneys, 23 total from blocks A, B, C, D & E and all ancillary site works
Shannon Weir , The Quay , Athlone
(i) The construction of an additional floor level to the single storey element of the south elevation of the existing house (ii) revising of existing bay window on the east elevation to a rectangular shape and extending ground floor south elevation (iii) provision of an additional window to the existing ground floor south elevation (iv) the replacement of 3 windows and 1 door on the ground floor west elevation with two large glazed openings (v) the replacement of 1 window on the existing first floor west elevation with 2 windows (v) the addition of a rooflight to the west elevation and all ancillary site works
45 Parnell Square , Athlone , Co Westmeath
Affected by this application?
Submissions can be made for 5 weeks from the date the application was received. Only material planning grounds count. Build a valid submission letter in minutes.
Make a Submission or ObjectionPlanning a project of your own?
Find out in two minutes whether you need planning permission. It's free, and based on the exempted development regulations.
Do I Need Permission?