Proposed Development

demolition of an existing dwelling house and garage, construction of a residential development comprising 51 no. residential units(5 no. detached dwellings, 34 no. semi-detached houses, 12 no. terrace houses), accessed off the new Croom Distributor Road between the Old Cork Road and the Crecora Road with site entrances off said Distributor Road along with connection(s) to all water and utility services as provided by Limerick City and County Council as part of the new road construction and all ancillary site development works. Ancillary site development works include connection(s) to the public water main, foul and surface water drainage, access roads, footpaths, vehicle parking, landscaping, boundary treatments and site development works above and below ground

View the full application file on the council's planning portal →

Application Timeline

  1. Application received

    12 May 2021

  2. Further information requested

    1 Jul 2021

  3. Further information received

    16 Mar 2022

  4. Decision: CONDITIONAL

    8 Apr 2022

  5. Decision due

    12 Apr 2022

  6. Grant issued

    12 May 2022

Application Details

Location
Skagh , Croom , Co. Limerick
Applicant
N/A
Application Type
PERMISSION
Planning Authority
Limerick County Council
Floor Area
5831.9999999999945 sq m
Residential Units
49

Timeline

Registration Date
12 May 2021
Status
APPLICATION FINALISED
Decision
CONDITIONAL
Decision Date
8 April 2022
Grant Date
12 May 2022
Permission Expires
11 May 2027

Location

Loading map...

Planning Applications Nearby

What the council has granted and refused around this site is the best guide to how a similar application will fare.

95m
2561385CONDITIONAL19 Dec 2025

extension to the existing dwelling together with all associated site works

31 St. Senans Terrace , Croom , Co. Limerick

127m
178011N/A13 Oct 2017

Croom Distributor Road - provision for a scheme to advance the unbuilt section of the distributor road to complete the link to High Street R516 at its southern extent and a distributor road between Crecora Road and Limerick Road to the north. In addition, a new road will be constructed to the north of the proposed distributor road crossing the Laskiltagh River to accommodate access to a proposed post-primary school which will be located north of the river. The proposed road will be a single carriageway road (6.0m carriageway road) with a shared cycleway/footway (1.5m wide cycleway and 1.5m footpath). A 1.0m buffer from the carriageway is also included on both sides of the carriageway with associated earthworks and verges. New junctions will be formed with the existing roads including a roundabout on the Crecora Road. There will be associated road signage/markings, drainage and utility services constructed. In addition, there will be an attenuation pond to facilitate sustainable drainage systems

Skagh , Croom , Co. Limerick.

179m
19552REFUSED7 Jun 2019

14 no. two bedroom apartments consisting of the following: Block 'A' consisting of 6 no. two bedroom apartments, Block 'B' consisting of 4 no. two bedroom apartments and Block 'C' consisting of 4 no. two bedroom apartments and for landscaping and all associated site works

Site No. 11 , Gateway Park Skagh , Croom Co. Limerick.

182m
257029CONDITIONAL28 Oct 2025

Extension of Duration for Planning Ref. No. 19/552: 14 no. two bedroom apartments consisting of the following: Block 'A' consisting of 6 no. two bedroom apartments, Block 'B' consisting of 4 no. two bedroom apartments and Block 'C' consisting of 4 no. two bedroom apartments and for landscaping and all associated site works

Site No. 11 , Gateway Park Skagh , Croom Co. Limerick.

211m
198005CONDITIONAL22 Jul 2019

(a) 16 residential units comprising 2 x 3 bed houses, 5 x 2 bed houses, 7 x 2 bed apartments and 2 x 1 bed apartments, arranged over three blocks of two and single storey buildings, (b) revised junction design consisting of reduced kerb radii to junction of St. Senan's Terrace & Towerfield, revised roadside kerb line on St. Senan's Terrace at the Northeast site boundary, new footpaths throughtout, and 23 new car parking spaces, (c) homezone and landscaped areas, (d) open space and soft landscaping to private amenity space, (e) boundary works including construction/remedial works and new boundaries, (f) alteration to existing and construction of new site services, (g) decommissioning & removal of existing ESB sub-station and construction of new elsewhere on the proposed site, (h) connection to public utilities, (i) all associated site works

Towerfield , Croom , Co. Limerick.

233m
2560949REFUSED19 Sept 2025

construction of 10 no dwelling houses, including 7 no 2-storey and 3 no single storey houses, entrance to the public road, connection to the public sewer & all services together with associated site works, parking, green areas, walls and footpaths. There is a valid Planning Permission on this site for residential development under planning file reference P20/525 and ABP-309917-21

Skagh , Croom , Co Limerick

234m
2460312CONDITIONAL11 Apr 2024

the construction of a new sports ground for Croom United Football Club which will consist of; one astroturf soccer pitch with lighting and two grass pitches, a single story clubhouse of gross floor area 177m2 containing dressing rooms and a gym, the widening of the existing vehicular site entrance, the provision of vehicle parking including accessible spaces and EV charging stations, bicycle parking, a refuse store, new foul and water mains connections, the provision of SuDS measures including attenuation tanks, swales, and a raingarden with all associated landscaping and associated site works

Skagh , Croom , Co. Limerick

240m
21131CONDITIONAL8 Feb 2021

for development at site no. 9 & 10 for 2no. two storey dwelling houses and ancillary drainage and associated site works(Outline permission ref. no. 13/148 which was extended under extension of duration ref. no. 17/7003)

Skagh , Croom , Co. Limerick

244m
2560886CONDITIONAL4 Sept 2025

the construction of an entrance lobby with balcony over and all ancillary site works

Glenwood , Croom , Co. Limerick

246m
20525CONDITIONAL19 Jun 2020

the construction of 14 dwelling houses, including 2 no semi-detached 2 bedroom bungalows, 12 no 2 storey semi-detached 3 bedroom houses, of which 4 will have an optional additional 4th bedroom on the ground floor and associated site development works, which includes 2 entrances to the public road, services, landscaping and the demolition of the side extension to the former community hall

Skagh , Croom , Co. Limerick

Planning a project of your own?

Find out in two minutes whether you need planning permission. It's free, and based on the exempted development regulations.

Do I Need Permission?