Proposed Development

A PERIOD OF 5 YEARS TO CONSTRUCT AND COMPLETE A SOLAR PV ENERGY DEVELOPMENT WITH A TOTAL SITE AREA OF 60.53 HECTARES, TO INCLUDE A SINGLE STOREY ELECTRICAL SUBSTATION BUILDING, INVERTER SUBSTATIONS, MODULES, SOLAR PV GROUND MOUNTED ON SUPPORT STRUCTURES, A TEMPORARY CONSTRUCTION COMPOUND, INTERNAL ACCESS TRACKS, SECURITY FENCING, ELECTRICAL CABLING AND DUCTING, CCTV AND OTHER ANCILLARY INFRASTRUCTURE, DRAINAGE, ADDITIONAL LANDSCAPING AND HABITAT ENHANCEMENT AS REQUIRED AND ASSOCIATED SITE DEVELOPMENT WORKS RELATING TO THE ACCESS OF THE SITE. THE SOLAR FARM WILL BE OPERATIONAL FOR 35-YEARS

View the full application file on the council's planning portal →

Application Details

Location
BALLYTEIGE LITTLE BALLYTEIGE BIG AND COLEHILL , TULLAMORE , CO. OFFALY
Applicant
N/A
Application Type
PERMISSION
Planning Authority
Offaly County Council

Timeline

Registration Date
12 February 2021
Status
INCOMPLETED APPLICATION
Decision
N/A

Location

Loading map...

Planning Applications Nearby

What the council has granted and refused around this site is the best guide to how a similar application will fare.

8m
2198CONDITIONAL3 Mar 2021

A PERIOD OF 5 YEARS TO CONSTRUCT AND COMPLETE A SOLAR PV ENERGY DEVELOPMENT WITH A TOTAL SITE AREA OF 60.53 HECTARES, TO INCLUDE A SINGLE STOREY ELECTRICAL SUBSTATION BUILDING, INVERTER SUBSTATIONS, MODULES, SOLAR PV GROUND MOUNTED ON SUPPORT STRUCTURES, A TEMPORARY CONSTRUCTION COMPOUND, INTERNAL ACCESS TRACKS, SECURITY FENCING, ELECTRICAL CABLING AND DUCTING, CCTV AND OTHER ANCILLARY INFRASTRUCTURE, DRAINAGE, ADDITIONAL LANDSCAPING AND HABITAT ENHANCEMENT AS REQUIRED AND ASSOCIATED SITE DEVELOPMENT WORKS RELATING TO THE ACCESS OF THE SITE. THE SOLAR FARM WILL BE OPERATIONAL FOR 35-YEARS

BALLYTEIGE LITTLE BALLYTEIGE BIG AND COLEHILL , TULLAMORE , CO. OFFALY

8m
2660071CONDITIONAL11 Feb 2026

an amendment to a previously consented development (RED III) (Planning Reference 2198 by Offaly County Council) comprising of; (i) removal of the 38kV substation and infrastructure within the most northern field (Field 1), (ii) internal access track reduced from c.3.4km to c. 3.2km,relocated and tweaked to include turning areas, (iii) replacement of string inverters instead of combined central inverters and MV transformers, the central MV transformers remain, and increase from 11No. to 12 No., however there will be a reduction in their associated hardstanding areas and the number of string inverters is 128, (iv) table layout updated (reduced), (v) PV angle tilt reduced from 10º and 40º to 10º and 30º, (vi) separation area between infrastructure and OHL towers increased, (vii) an additional badger sett buffer added (viii) temporary construction compound has been relocated from Field 1 to Field 4, (ix) alter Condition No. 10 to increase the boundary fencing from 1.8m-2m high to 2.4m high and reduce in the perimeter fence length, (x) CCTV number increase from 81 to 118 and their locations have been amended, (xi) adjustment of the development period from 5 years to 10 years, and (xii) alter Condition No. 11 to change the operational lifetime from 35 years to 40 years. The planning application area comprises of 60.53hectares and comprises of a Solar PV development (i.e. a relevant solar energy development as per the Renewable Energy Directive III). This planning application is accompanied by a Natura Impact Statement (NIS). This development is covered by the provision of the Renewable Energy Directive III (Directive (EU) 2023/2413) and it is important to note that the planning application may be subject to section 34D of the Planning and Development Act 2000, as amended. When a notice issues in accordance with section 34D(b), the provisions of article 26A of the Planning and Development Regulations 2001 to 2025 shall apply

Townlands of Ballyteige Little Ballyteige Big and Colehill Tullamore , County , Offaly

8m
2660044N/A29 Jan 2026

the amendment to a previously consented development (Planning Reference 2198 by Offaly County Council) comprising of; (i) removal of the 38kV substation and infrastructure within the most northern field (Field 1), (ii) internal access track reduced from c.3.4km to c. 3.2km,relocated and tweaked to include turning areas, (iii) replacement of string inverters instead of combined central inverters and MV transformers, the central MV transformers remain, and increase from 11No. to 12 No., however there will be a reduction in their associated hardstanding areas and the number of string inverters is 128, (iv) table layout updated (reduced), (v) PV angle tilt reduced from 10º and 40º to 10º and 30º, (vi) separation area between infrastructure and OHL towers increased, (vii) an additional badger sett buffer added (viii) temporary construction compound has been relocated from Field 1 to Field 4, (ix) alter Condition No. 10 to increase the boundary fencing from 1.8m-2m high to 2.4m high and reduce in the perimeter fence length, (x) CCTV number increase from 81 to 118 and their locations have been amended, (xi) adjustment of the development period from 5 years to 10 years, and (xii) alter Condition No. 11 to change the operational lifetime from 35 years to 40 years. The planning application area comprises of 60.53hectares and comprises of a Solar PV development (i.e. a relevant solar energy development as per the Renewable Energy Directive III). This planning application is accompanied by a Natura Impact Statement (NIS). (RED III) This development is covered by the provision of the Renewable Energy Directive III (Directive (EU) 2023/2413) and it is important to note that the planning application may be subject to section 34D of the Planning and Development Act 2000, as amended. When a notice issues in accordance with section 34D(b), the provisions of article 26A of the Planning and Development Regulations 2001 to 2025 shall apply

Townlands of Ballyteige Little Ballyteige Big and Colehill Tullamore , County , Offaly

8m
2560659N/A18 Dec 2025

an amendment to a previously consented development (Planning Reference 2198 by Offaly County Council) comprising of; (i) removal of the 38kV substation and infrastructure within the most northern field (Field 1), (ii) internal access track reduced from c.3.4km to c. 3.2km,relocated and tweaked to include turning areas, (iii) replacement of string inverters instead of combined central inverters and MV transformers, the central MV transformers remain, and increase from 11No. to 12 No., however there will be a reduction in their associated hardstanding areas and the number of string inverters is 128, (iv) table layout updated (reduced), (v) PV angle tilt reduced from 10º and 40º to 10º and 30º, (vi) separation area between infrastructure and OHL towers increased, (vii) an additional badger sett buffer added (viii) temporary construction compound has been relocated from Field 1 to Field 4, (ix) alter Condition No. 10 to increase the boundary fencing from 1.8m-2m high to 2.4m high and reduce in the perimeter fence length, (x) CCTV number increase from 81 to 118 and their locations have been amended, (xi) adjustment of the development period from 5 years to 10 years, and (xii) alter Condition No. 11 to change the operational lifetime from 35 years to 40 years. The planning application area comprises of 60.53hectares. This planning application is accompanied by a Natura Impact Statement (NIS) This development is covered by the provision of the Renewable Energy Directive III (Directive (EU) 2023/2413) and it is important to note that the planning application may be subject to section 34D of the Planning and Development Act 2000, as amended. When a notice issues in accordance with section 34D(b), the provisions of article 26A of the Planning and Development Regulations 2001 to 2025 shall apply.

Townlands of Ballyteige Little Wood of O Corndarragh Derrynagall or Ballydaly Ardan and Puttaghan , County , Offaly

1.2km
2560141CONDITIONAL24 Apr 2025

an extension to the existing dwelling and associated site works

Colehill , Cappincur , Tullamore

1.2km
1977CONDITIONAL26 Feb 2019

AMENDMENTS TO THE EXISTING SITE BOUNDARY GRANTED UNDER APPLICATION 87/68 INCLUDING ALL ASSOCIATED SITE WORKS

COLEHILL , TULLAMORE CO OFFALY

1.2km
1871CONDITIONAL16 Feb 2018

CONSTRUCTION OF SINGLE STOREY DWELLING HOUSE, GARAGE, SEPTIC TANK/EFFLUENT TREATMENT SYSTEM AND ALL ANCILLARY WORKS AND SERVICES

COLEHILL , TULLAMORE , CO. OFFALY

1.2km
1978CONDITIONAL26 Feb 2019

THE CONSTRUCTION OF A NEW DORMER STYLE DWELLING, NEW GARAGE, NEW ENTRANCE, NEW SEPTIC TANK AND PERCOLATION AREA INCLUDING ALL ASSOCIATED SITE WORKS

COLEHILL , TULLAMORE , CO. OFFALY

1.3km
1710CONDITIONAL16 Jan 2017

CONSTRUCTION OF A SLATTED SHEEP SHED WITH UNDERGROUND SLURRY STORAGE TANK AND ALL ANCILLARY SITE WORKS

BALLYTEAGUE BIG , BALLYCOMMON , TULLAMORE

1.3km
2534N/A4 Apr 2025

THE EXISTING MOBILE HOME STRUCTURE AND EXISTING FOUL WATER HOLDING TANK AND ALL ASSOCIATED EXISTING SITEWORKS AS A THREE-YEAR TEMPORARY DEVELOPMENT. PERMISSION FOR THE CONSTRUCTION OF A DORMER STYLE DWELLING WITH DETACHED GARAGE, SEPTIC TANK AND PERCOLATION AREA AND ALL ASSOCIATED SITE WORKS

BALLYTEIGE LITTLE , BALLYCOMMON , CO.OFFALY.

Affected by this application?

Submissions can be made for 5 weeks from the date the application was received. Only material planning grounds count. Build a valid submission letter in minutes.

Make a Submission or Objection

Planning a project of your own?

Find out in two minutes whether you need planning permission. It's free, and based on the exempted development regulations.

Do I Need Permission?