221006

CONDITIONAL

Galway - Galway County Council

Proposed Development

for the development and operation of a 150 to 500 MVA (electrical rating) synchronous condenser. The development which will be located within a site compound of c. 1 hectare east of the existing ESB substation for the purpose of stabilizing the electricity grid will consist of the following elements: The development and operation of a 150 to 500 MVA (electrical rating) synchronous condenser. Compound building housing synchronous condenser generator and flywheel (540 sqm c. 12m high); 5 No. modular containers to house electrical and control equipment (total area of c. 195 sqm, c. 5m high), a generator step-up transformer, auxiliary transformer and electrical plant including and external circuit breaker (c. 8m); 1 No. firefighting water tank and pump, boundary fencing (c. 3m high) and CCTV, c. 50m of underground cabling ducts and cable to the neighbouring ESB Substation, all other ancillary site works including access roads and upgrade of existing local access road. Planning permission is being sought for a duration of 10 years. Gross floor space of proposed works: 540 sqm

View the full application file on the council's planning portal →

Application Timeline

  1. Application received

    26 Aug 2022

  2. Further information requested

    18 Oct 2022

  3. Further information received

    21 Dec 2022

  4. Decision due

    26 Jan 2023

  5. Decision: CONDITIONAL

    26 Jan 2023

  6. Grant issued

    6 Mar 2023

Application Details

Location
Barrettspark ,
Applicant
N/A
Application Type
PERMISSION
Planning Authority
Galway County Council
Site Area
1 ha

Timeline

Registration Date
26 August 2022
Status
APPLICATION FINALISED
Decision
CONDITIONAL
Decision Date
26 January 2023
Grant Date
6 March 2023
Permission Expires
5 March 2033

Location

Loading map...

Planning Applications Nearby

What the council has granted and refused around this site is the best guide to how a similar application will fare.

52m
22303REFUSED7 Mar 2022

for a development consisting of the development and operation of a 150 to 500 MVA (electrical rating) synchronous condenser. The development which will be located within a site compound of c. 1 hectare east of the existing ESB substation for the purpose of stabilizing the electricity grid will consist of the following elements: The development and operation of a 150 to 500 MVA (electrical rating) synchronous condenser. Compound building housing synchronous condenser generator and flywheel (540sqm c. 10m high). Cooling equipment (c. 160sqm, c. 3m high); 5 no. modular containers to house electrical and control equipment (total area of c. 195sqm, c. 5m high). A generator step-up transformer, auxiliary transformer and electrical plant including and external circuit breaker (c. 8m); 1 no. firefighting water tank and pump, boundary fencing (c. 3m high) and CCTV, c. 50m of underground cabling ducts and cable to the neighbouring ESB Substation, all other ancillary site works including access roads. Planning permission is being sought for a duration of 10 years. Gross floor space of proposed works: 540sqm.

Barrettspark ,

258m
181883CONDITIONAL21 Dec 2018

for a ten-year planning permission for the development of an up to 100MW Battery Energy Storage Facility that will provide energy services to the national grid and will be delivered in 4 no. phases. The development will consist of the construction and operation of up to 34 metal containers to store up to a project total of up to 100MW in sealed battery cells each with entrances, fire suppression systems, heating, ventilation and air conditioning systems. The proposed development includes for inverters, control systems, other electrical components, security lighting and ancillary infrastructure and all associated works including security fencing and ancillary grid infrastructure. Gross floor space of proposed works: 2186.6 sqm

Barrettspark ,

281m
201221REFUSED28 Aug 2020

and completion of extension to Industrial Premises. Gross floor space of work to be retained: 3980.00 sqm

Cashla ,

284m
21829REFUSED17 May 2021

of extensions and alterations to factory premises and site and entrances at Cashla, Athenry to include the following: - A. Machine Shop and Canteen to South Elevation. B. Switch Room & Compressor Room to south elevation. C. Maintenance Garage and Stores to East elevation. D. Monitoring Office Building to back of site. E. Steel Cleaning Shop to North elevation. F. Store to south elevation. G. Retention of existing entrance at North Western corner of site as HGV entrance only. (existing entrance on West Boundary to be relocated nearer to car park to be for cars only. -- covered under planning ref. no:- 20/1221. H. Enlargement of site to back of factory

Cashla ,

289m
24260CONDITIONAL6 Sept 2024

for the installation of solar panels over the roof of an existing telecommunications cabin on a steel frame (covering an area of 60 sqm to maximum height of 5 meters above ground level) works to consist of all ancillary development works, including steel uprights

Barrettspark , ESB Telecoms Ltd Compound , Cashla 220k V Substation

290m
2360948CONDITIONAL11 Aug 2023

& retention permission for development at C&F Tooling, Cashla, Athenry, County Galway. Retention planning permission for the following extensions to the existing C&F Tooling premises: • machine shop & canteen (gross floor area - 792m2) • switch room & compressor room (gross floor area - 96 m2) •maintenance garage & stores gross floor area - 673 m2) • monitoring office building (gross floor area - 444 m2) • steel cleaning shop (gross floor area - 62.3 m2) • store (gross floor area - 20.3 m2) • machine shop (gross floor area - 4,065 m2). In addition to the above, retention permission for the existing component storage area (external) (approx. 1.54 Ha in area). Planning permission for: • upgraded surface water drainage system & associated works, •relocation of existing traffic barrier at the existing vehicular entrance to the premises, • new vehicular staff entrance on the western boundary of the site, & • alterations to the existing staff car park to provide 357no. car parking spaces to include the provision of EV charging & accessible car parking bays, • provision of visitor car park to provide 31no. car parking spaces (including EV charging & accessible car parking bays). The proposed development includes for all associated site development works & landscaping

Cashla , Athenry , Co. Galway

332m
19325CONDITIONAL7 Mar 2019

to refill an existing disused quarry with inert material

Barretts Park ,

376m
25365N/A23 Dec 2025

to extend wind turbine testing & research site to rear of existing factory (previously granted under planning permission ref. number 13/1242) to include the following: 24 no. 20-30kw wind turbines (maximum height is 30.100 meters), includes 2 no. turbines in upper test site (previously granted under planning permission ref. no. 20/101), all other ancillary site works

Cashla & Moor , Athenry , Co. Galway

697m
20499CONDITIONAL21 Apr 2020

for a twenty year planning permission for the continued operation of the existing quarry and all associated uses and activities, as well as for an extension to the existing quarry extraction area and all associated site works including landscaping arrangements. The proposed quarry extraction area extension is on lands to the north, south and east of the existing quarry and the additional extraction area amounts to approximately 6.7 hectares. The application is accompanied by an Environmental Impact Assessment Report and a Natura Impact Statement.

Barrettspark ,

697m
21859UNCONDITIONAL20 May 2021

to continue quarrying with associated roads and ancillary services and to operate a concrete batching plant and a bitumen batching plant within the quarry. The 13 hectare extraction area and the 27.5 hectare site boundary remains identical to that outlined in the existing quarry planning permission for Coshla Quarries Ltd (P06/4125). An Environment Impact Statement (EIS) will be submitted with the application