The Register of Planning Applications · Éire

Monday 31 August 2026

← Back to search

221091

CONDITIONAL

Limerick - Limerick County Council

Proposed Development

the construction of 1130sq.m solar panel array with an export capacity of approximately 240kwh to be mounted on the roofs of the existing bulk storage stores No 1 & 2 and all associated site works(the proposed development is within an existing Seveso site[upper tier])

View the full application file on the council's planning portal →

Application Timeline

  1. Application received

    10 Oct 2022

  2. Decision: CONDITIONAL

    30 Nov 2022

  3. Decision due

    4 Dec 2022

  4. Grant issued

    11 Jan 2023

Application Details

Location
Morgan's South , Askeaton , Co. Limerick
Applicant
N/A
Application Type
PERMISSION
Planning Authority
Limerick County Council

Timeline

Registration Date
10 October 2022
Status
APPLICATION FINALISED
Decision
CONDITIONAL
Decision Date
30 November 2022
Grant Date
11 January 2023
Permission Expires
10 January 2028

Location

Loading map...

Planning Applications Nearby

What the council has granted and refused around this site is the best guide to how a similar application will fare.

49m
221217CONDITIONAL17 Nov 2022

an extension of existing storage bays building and all associated site works(this proposed development is within an existing Seveso site[upper tier])

Morgan's South , Askeaton , Co. Limerick

151m
18482CONDITIONAL17 May 2018

revised location septic tank, percolation area and domestic garage as constructed

Morgans South , Askeaton , Co. Limerick.

198m
20713CONDITIONAL24 Jul 2020

the extension of existing finished product storage yard and all associated site works (this proposed development is within an existing Seveso site(upper tier))

Morgan's South , Askeaton , Co. Limerick

420m
24217CONDITIONAL24 May 2024

the temporary improvement and upgrade of an existing entrance off the N69 and temporary site offices. The permission for retention includes widening an existing entrance, locating temporary site offices at the compound entrance and undertaking ancillary site works and road markings, making it suitable for a site access for use during the refurbishment works of the Limerick to Foynes Rail Line, which is expected to take 3 years. Thereafter, the site access will revert back to its current use

Tomdeely South , Askeaton , Co. Limerick

457m
19412CONDITIONAL26 Apr 2019

construction of a new single storey extension to the side of the dwelling including all ancillary site works. Retention Permission is also sought for a detached garage to the rear and 2 no. rear facing roof windows

Morgans South , Askeaton , Co. Limerick.

766m
1991CONDITIONAL6 Feb 2019

a replacement dwelling house, garage, entrance, effluent treatment system, percolation area and all associated site works

Tomdeely South , Askeaton , Co. Limerick.

769m
237018REFUSED24 Jul 2023

extension of permission for planning ref. 19/91: a replacement dwelling house, garage, entrance, effluent treatment system, percolation area and all associated site works

Tomdeely South , Askeaton , Co. Limerick.

825m
20768CONDITIONAL7 Aug 2020

the construction of a new two storey dwelling house, a domestic garage, a waste-water treatment system, a new site entrance wall and gate and all ancillary site works

Morgans North , Askeaton , Co. Limerick

1.2km
23294REFUSED6 Jun 2023

the development will consist of: (a) The restoration and infilling of the existing and future void over an area of (c. 17.2 ha) of existing permitted quarry (05/7029 and ABP 13.QC.2098) using approximately 2,464,000m3 or 4,435,200 tonnes of inert soil and stone material or stone by-product, or river dredge spoil. (b) The development will consist of the restoration of the void with either: (1) Inert soil and stone waste (imported inert greenfield and non-greenfield soils and stone, and river dredge spoil) which will result in the Proposed Development operating as a soil recovery facility that requires a waste management licence from the EPA; or, (2) Soil and stone by-product (i.e. essentially virgin soil or equivalent to virgin soil and stone) which will be notified to the EPA as an Article 27 by-product at its source of origin and transported as a by-product material to enable the Site to be restored. The Site would then operate under conditions of planning. (c) The proposed development will utilise the permitted quarry infrastructure including internal roads, site office, weighbridge, wheel wash, welfare facilities and other ancillaries to complete the works. (d) Stockpiling of topsoil removed during quarrying for future implementation of a restoration plan. (e) Construction of a soil inspection shed (approximately 120m2 in area, 4m height) and refuelling area (hardstanding) located to the west of the existing site office (approximately 16m2 hardstanding area. (f) Decommissioning and disposal of existing fuel tanks at an appropriately licensed offsite waste facility. (g) Associated minor works to include site access road improvements (resurfacing), upgrade of drainage infrastructure including new fuel/oil interceptor and surface drains on hardstanding. (h) Existing weighbridge and wheel wash upgrades. (i) Demolition of other buildings/structures. An Environmental Impact Assessment Report (EIAR) and Natura Impact Statement (NIS) accompanies the planning application. The development comprises an activity that may require a Waste License

Roadstone Barrigone Quarry , in the townland of Glenbane East , Askeaton

1.2km
2560020CONDITIONAL16 Jan 2025

a) The infilling and restoration of the existing quarry void over an area (c. 4.1 ha) of existing permitted quarry (05/7029 and ABP 13.QC.2098) using approximately 450,000m³ or 810,000 tonnes of inert soil and stone waste or soil and stone by-product. b) The development will consist of the restoration of the void with either: 1) Inert soil and stone waste (imported inert greenfield and non-greenfield soils and stone, and river dredge spoil) which will result in the Proposed Development operating as a soil recovery facility that requires a waste management licence from the EPA; or, 2) Soil and stone by-product (i.e. essentially virgin soil or equivalent to virgin soil and stone) which will be notified to the EPA as an Article 27 by-product at its source of origin and transported as a by-product material to enable the Site to be restored. The Site would then operate under conditions of planning. c) The proposed development will utilise the permitted quarry infrastructure including internal roads, site office, weighbridge, wheel wash, welfare facilities and other ancillaries to complete the works. d) Upgrades to the existing weighbridge and wheel wash facilities. e) Construction of a soil inspection shed (approximately 120m² in area, 4m height) and refuelling area (hardstanding) located to the west of the existing site office (approximately 16m² hardstanding area). f) Associated minor works to include site access road improvements, upgrade of drainage infrastructure including new fuel/oil interceptor and surface drains on hardstanding. g) All ancillary and associated works. The planning application boundary extends to 17.44 hectares. An Environmental Impact Assessment Report (EIAR) and Natura Impact Statement (NIS) accompanies the planning application. The development comprises an activity that may require a Waste Licence.

Barrigone Quarry , Askeaton , Co. Limerick.