221141

CONDITIONAL

Clare - Clare County Council

Proposed Development

of a separate garage to the side of the existing dwelling house

View the full application file on the council's planning portal →

Application Timeline

  1. Application received

    16 Dec 2022

  2. Decision: CONDITIONAL

    15 Feb 2023

  3. Decision due

    18 Feb 2023

  4. Grant issued

    22 Mar 2023

Application Details

Location
Skehanagh , Clarecastle , Co Clare
Applicant
N/A
Application Type
RETENTION
Planning Authority
Clare County Council

Timeline

Registration Date
16 December 2022
Status
APPLICATION FINALISED
Decision
CONDITIONAL
Decision Date
15 February 2023
Grant Date
22 March 2023
Permission Expires
21 March 2028

Location

Loading map...

Planning Applications Nearby

What the council has granted and refused around this site is the best guide to how a similar application will fare.

69m
25329CONDITIONAL20 Oct 2025

to construct a new dwelling house, septic tank, sewerage treatment system and access to the public road

Killoo , Clarecastle , Co. Clare

78m
17885CONDITIONAL20 Nov 2017

( ref. No. P16-325 of Outline Permission ) to construct private dwelling house, change of use of existing cottage on site. from domestic use to garage, installation of new waste water treatment system and percolation area, connect to existing infrastructure services and all associated site works

Killow , Clarecastle , Co. Clare

140m
1840CONDITIONAL25 Jan 2018

on the grant of outline permission ( Reference No. P16-201 ) which will consist of the construction of a dwelling house, garage, a proprietary waste water treatment system and ancillary site works

Site No. 1 Killow , Clarecastle , Co. Clare

377m
20781CONDITIONAL23 Oct 2020

to develop a motorway service area and rest area adjacent to Junction 12 of the M18 motorway, which will include service station building with convenience shop, food court, staff facilities, canopy, fuel facilities, parking and circulation space, children's play area, picnic area and access provision. The development also includes infrastructural works public lighting, signage, landscaping, internal fencing, electrical substation, sixteen electric car charging points, roof mounted solar panels, storm water runoff, petrol interceptors and attenuation system, on-site wastewater treatment plant including access road, pumping station and connection to public foul sewer, drainage improvement works, underground fuel storage tanks, rain water harvesting system, connection to public water supply, underground storage tanks for fire-fighting purposes, underground rain water harvesting tanks, works to improve visibility at access point, upgrade to adjacent roundabout and ancillary works. The connection to the public sewerage system will be by means of a rising main to an existing public sewer. The rising main sewer will cross under the M18 motorway by directional drilling and thereafter underground via existing road margins/public road and under River Fergus and railway line through the townlands of Kilbreckan, Killow, Skehanagh, Clareabbey and Ballybeg. The inert soil from the directional drilling will be used in landscaping works on the site of the service station building. A Natura Impact Statement (NIS) will be submitted to the Planning Authority with the application

Kilbreckan , Doora , Ennis

539m
18342CONDITIONAL30 Apr 2018

to construct a single dwelling house, garage, advanced wastewater treatment system and ancillary site works

Killow , Clarecastle , Co. Clare

576m
22879CONDITIONAL29 Sept 2022

for the construction of a dwelling house, garage, wastewater treatment system and new entrance including ancillary site works

Killoo , Clarecastle , Co Clare

587m
18634CONDITIONAL3 Aug 2018

to construct a dwelling house and garage complete with new entrance, sewerage treatment system and ancillary works

Skehanagh , Clarecastle , Co. Clare

588m
19567CONDITIONAL9 Jul 2019

to amend external wall finish and amendment to Condition 6(c) previously granted under Planning Permission 18-634.

Skehanagh , Clarecastle , Co Clare

605m
18564N/A11 Jul 2018

with rising main sewer via existing public road / road margins through the Townlands of Kilbreckan, Killow, Skehanagh, Clareabbey and Ballybeg to develop a motorway service area and rest area adjacent to Junction 12 of the M18. The proposed development will include a service station building with convenience shop, food court, staff facilities, canopy, fuel facilities, parking and circulation space, children's play area, picnic area and access provision. The development also includes infrastructural works, public lighting, signage, landscaping, internal fencing, electrical substation, sixteen electric cars charging points, roof mounted solar panels, storm water runoff petrol interceptors and attenuation system, on-site wastewater treatment plant including access road, pumping station and connection to public foul sewer, drainage improvement works, underground fuel storage tanks, rain water harvesting system, connection to public water supply, underground storage tanks for fire fighting purposes, underground rain water harvesting tanks, upgrade to adjacent roundabout and ancillary works. The connection to the public sewerage system will be by means of a rising main to an existing public sewer via existing public road / road margins through the Townlands of Kilbreckan, Killow, Skehenagh, Clareabbey and Ballybeg, A Natura Impact Statement ( NIS ) will be submitted to the Planning Authority with this application.

Kilbreckan , Doora , Ennis

638m
18920CONDITIONAL15 Nov 2018

to construct a new dwelling house and garage complete with a new entrance, sewage treatment system and ancillary works

Skehanagh , Clarecastle , Ennis

Planning a project of your own?

Find out in two minutes whether you need planning permission. It's free, and based on the exempted development regulations.

Do I Need Permission?