22174
CONDITIONALTipperary - Tipperary County Council
Proposed Development
the proposed development will consist of the construction of 3 no. warehousing/light industrial units (with a floor area of 1029sqm for building 1, a floor area of 1430 sqm for building 2 and a floor area of 1430 sqm for building 3, parking spaces and all associated services. In addition, Flamewell Limited is to apply for a change of use for the existing 100 square metre cottage, which is a protected structure on the development from domestic to office use. Existing outbuildings and sheds are proposed to be demolished.
View the full application file on the council's planning portal →Application Timeline
Application received
1 Mar 2022
Further information requested
22 Apr 2022
Decision: CONDITIONAL
10 Nov 2022
Decision due
16 Nov 2022
Appeal submitted
5 Dec 2022
Appeal decided: REFUSED
14 Feb 2024
Application Details
- Location
- Ard Gaoithe , Lawlesstown , Clonmel
- Applicant
- N/A
- Application Type
- PERMISSION
- Planning Authority
- Tipperary County Council
Timeline
- Registration Date
- 1 March 2022
- Status
- APPLICATION FINALISED
- Decision
- CONDITIONAL
- Decision Date
- 10 November 2022
An Coimisiún Pleanála Appeal
- Appeal Reference
- ABP-315268-22
- Decision
- REFUSED
- Submitted
- 5 December 2022
- Decided
- 14 February 2024
Location
Planning Applications Nearby
What the council has granted and refused around this site is the best guide to how a similar application will fare.
the proposed development will consist of the construction of 3 no. warehousing/light industrial units (with a floor area of 1029sqm for building 1, a floor area of 1430 sqm for building 2 and a floor area of 1430 sqm for building 3, parking spaces and all associated services. In addition, Flamewell Limited intend to apply for a change of use for the existing cottage on the development from domestic to office use
Ard Gaoithe , Lawlesstown , Clonmel
the proposed development will consist of the construction of 3 no. warehousing/light industrial units (with a floor area of 1029sqm for building 1, a floor area of 1430 sqm for building 2 and a floor area of 1430 sqm for building 3, parking spaces and all associated services. In addition, Flamewell Limited intend to apply for a change of use for the existing cottage on the development from domestic to office use
Ard Gaoithe , Lawlesstown , Clonmel
a power plant comprising the following main components; Engine Hall comprising up to 6 no. dual fuel gas/diesel IC reciprocating engines and associated generating equipment; 1 no. exhaust stack cluster; Electrical Annex Building; 1 No. 120 MW Step-up transformer; Workshop/Stores Building; Administration Building; Radiator Coolers; Tank Farm comprising: 2 x Fuel Oil Storage Tanks, SCR reagent Tank, Lube Oil Storage Tank, Lube Oil Maintenance Tank, Lube Oil Disposal Tank, Pilot Oil Tank; Standby Generators; Cycle shed; Fire pump house, Firefighting water tank; Surface Water Attenuation Tank; Raw Water Storage Tank; Fencing; Car Park; Landscape planting around perimeter of site and all ancillary services. The plant is subject to a pollution control licence from the EPA
Ard Gaoithe Technology Park , Ard Gaoithe Lawlesstown , Clonmel
development which will consist of: The power plant comprising the following main components; Engine Hall comprising up to 6 no. dual fuel gas/diesel IC reciprocating engines and associated generating equipment; 1 no. exhaust stack cluster; Electrical Annex Building; 1 No. 120 MW Step-up transformer; Workshop/Stores Building; Administration Building; Radiator Coolers; Bunded Tank Farm comprising: 2 x Fuel Oil Storage Tank, SCR reagent Tank, Lube Oil Storage Tank, Lube Oil Maintenance Tank, Lube Oil Disposal Tank, Pilot Oil Tank; Cycle shed; Fire pump house, Firefighting water tank; Surface Water Attenuation Tank, Raw Water Storage Tank; Fencing; Car Park; Landscape planting around perimeter of site and all ancillary services
Ard Gaoithe Technology Park , Ard Gaoithe Lawlesstown , Clonmel
the construction of a wholesale warehouse including all associated site development works such as yards, carparking areas, fencing, lighting, drainage and access from the existing Ard Gaoithe Business Park road
Ard Gaoithe Business Park , Lawlesstown , Clonmel
the erection of a 0.9m high masonry wall with 1m high palisade railing fixed on top, to boundaries of existing car park forming a new secure compound with new gate at existing entrance
Unit 3a Ard Gaoithe Business Park , Clonmel , Co. Tipperary
the change of use of existing thatched cottage, which is a protected structure from residential to office use, retention of existing entrance and PERMISSION for the alteration of existing entrance and retention of an existing lightweight steel agricultural shed
Miletree House , Ardgaoithe Lawlesstown , Clonmel Co. Tipperary
the construction of a boundary wall to existing parking area consisting of a 900 mm rendered blockwork wall including concrete cap with 1000mm decorative palisade type railing fixed on top, and the erection of a new security gate at existing property entrance and assoicated site works
Unit 3a Ard Gaoithe Business Park , Clonmel , Co. Tipperary
the change of use of an existing thatched cottage, which is a protected structure, from residential to office use, including a new entrance and RETENTION PERMISSION FOR an existing lightweight steel agricultural enclosure
Miletree House , Ardgaoithe Lawlesstown , Clonmel Co.Tipperary
the construction of a light industrial Unit which will be sub-divided into 3no units each incorporating two-storey office space. The proposed development will include an access road off the existing Ard Gaoithe Business Park road, roads, yards, carpark area, site fencing, site lighting and all associated siteworks including connection to all existing site services
Ard Gaoithe Business Park , Lawlesstown , Clonmel