Proposed Development

extension of planning permission ref: PL16/348. Development of a solar panel array consisting of 48,000m2 of solar panels on ground mounted steel frames, electrical control room, power interest units, underground cable ducts, CCTV, Lighting, security fencing and all associated works

View the full application file on the council's planning portal →

Application Details

Location
Coppenagh , Tullow , Co. Carlow
Applicant
N/A
Application Type
EXTENSION OF DURATION
Planning Authority
Carlow County Council

Timeline

Registration Date
10 February 2022
Status
INCOMPLETED APPLICATION
Decision
N/A

Location

Loading map...

Planning Applications Nearby

What the council has granted and refused around this site is the best guide to how a similar application will fare.

75m
22237N/A14 Jul 2022

the development of the following elements: The erection and operation of a photovoltaic energy development which includes the erection of fixed panels on ground mounted frames, 1No. Energy storage compound, customer switchgear container, 1No. DNO substation which will be connected to the national grid, electrical transformer and inverter units, underground cabling and ducting, spare equipment container, boundary fencing, security entrance gates, CCTV, internal access road and all associated ancillary activities. The proposed development will have a projected life span of 30 years.

Coppenagh , Tullow , Co. Carlow

75m
22272CONDITIONAL19 Aug 2022

Application for a five year planning permission for the development of the following elements: The erection and operation of a photovoltaic energy development which includes the erection of a c.20.9 ha fixed panels on ground mounted frames with an export capacity of c. ten mega-watt, 1no. energy storage compound, customer switchgear container, 1no. DSO substation which will be connected to the national grid, electrical transformer and inverter units on an overall site area of c. 22.45 ha, underground cabling and ducting, spare equipment container, boundary fencing, security entrance gates, CCTV, internal access road and all associated ancillary activities. The proposed development will have a projected lifespan of 35 years.

Coppenagh , Tullow , Co. Carlow

75m
2360177CONDITIONAL18 Aug 2023

planning permission to modify a previously granted planning permission to facilitate an increased output from 10 MW to 20MW at the Coppenagh Solar Park development permitted pursuant to permission ref no: 22/272. Increased output is being facilitated arising from improved technological advancements and availability of Grid Capacity. No other alterations to design, siting layout etc are proposed.

Coppenagh , Tullow , County Carlow

75m
2360157N/A2 Aug 2023

a five year planning permission for the development of the following elements: The erection and operation of a photovoltaic energy development which includes the erection of c. 20.9 ha fixed panels on ground mounted frames with an export capacity of c. twenty five mega-watt, 1no. energy storage compound with an export capacity of twenty five mega-watts, customer switchgear container, 1no. DSO substation which will be connected to the national grid, electrical transformer and inverter units on an overall site area of c. 22.45 ha, underground cabling and ducting, spare equipment container, boundary fencing, security entrance gates, CCTV, internal access road and all associated ancillary activities. The proposed development will have a projected life span of 35 years.

Coppengh , Tullow , County Carlow

724m
19296N/A26 Jul 2019

to construct a single storey extension to the side and rear of existing single storey dwelling, a single storey shed to the rear of existing dwelling, new waste water treatment system and percolation area, new bored well, widening of existing entrance and all associated site works

Coppenagh , Tullow , Co. Carlow

724m
19303CONDITIONAL1 Aug 2019

to construct a single storey extension to the side and rear of existing single storey dwelling, a single storey shed to the rear of existing dwelling, new waste water treatment system and percolation area, new bored well, widening of existing entrance and all associated site works

Coppenagh , Tullow , Co. Carlow

788m
22431N/A19 Dec 2022

for a detached home office and gym, garage area to the front with attic storage and all associated site works to the rear of existing two storey dwelling

Coppenagh , Tullow , Co Carlow

788m
23173N/A16 Oct 2023

retention permission for a detached home office, WC, gym, garage area to the front with attic storage and all associated site works to the rear of existing two storey dwelling

Coppenagh , Tullow , Co. Carlow

788m
23182CONDITIONAL6 Nov 2023

a detached home office, WC, gym, garage area to the front with attic storage and all associated site works to the rear of existing two storey dwelling

Coppenagh , Tullow , Co. Carlow

805m
2460429N/A20 Dec 2024

The construction of: 1) a new single story dwelling house, domestic garage, domestic well, onsite wastewater treatment plant and percolation area, along with all associated site and landscaping works, 2 ) New Agricultural Farm Yard consisting of, Agricultural shed with slatted tank, lay back, livestock handling facility and hay storage, a stable block and machinery store shed, dung stand, bailed silage stand, enclosed yard and hard standing area, 3) Alteration and relocation of existing lane entrance from public road

Coppenagh , Tullow , Co Carlow

Affected by this application?

Submissions can be made for 5 weeks from the date the application was received. Only material planning grounds count. Build a valid submission letter in minutes.