2240863
CONDITIONALCork - Cork City Council
Proposed Development
Permission for the installation of a 516.8kWp rooftop solar photovoltaic array on the roof of an existing factory building consisting of 1,276 No. 405Wp Suntech Power panels mounted directly on the roof surface, electrically connected to the existing electrical plant room and inverters mounted on the wall of the existing plant room, and all associated work.
View the full application file on the council's planning portal →Application Timeline
Application received
9 Feb 2022
Decision due
5 Apr 2022
Decision: CONDITIONAL
5 Apr 2022
Grant issued
17 May 2022
Application Details
- Location
- Unit 21A , Ballycurreen Industrial Estate , Kinsale Road
- Applicant
- N/A
- Application Type
- PERMISSION
- Planning Authority
- Cork City Council
- Site Area
- 0.5004 ha
Timeline
- Registration Date
- 9 February 2022
- Status
- APPLICATION FINALISED
- Decision
- CONDITIONAL
- Decision Date
- 5 April 2022
- Grant Date
- 17 May 2022
Location
Planning Applications Nearby
What the council has granted and refused around this site is the best guide to how a similar application will fare.
Permission for the installation of an circa 336.98 kWp Rooftop Solar Photovoltaic Array consisting in combination of circa 812 no. panels (circa 1,599.64m2) partially extending to an existing Rooftop Solar Photovoltaic Array (circa 2,513.72m2) located on Unit 21A, Ballycurreen Industrial Estate, Kinsale Road, Cork, with the extension situated on the most southern roof area of this industrial building; and partially on a vacant roof area located on an adjacent industrial building located to the North East, at Ballycurreen Industrial Estate, Kinsale Road, Cork, T12R866, with all the proposed panels mounted directly on the roof surface of the buildings and electrically connected to the existing electrical plant rooms via a combined total of 4 no. inverters mounted on the wall of the existing plant rooms, and all associated site works.
Unit 21A Ballycurreen Industrial Estate , Kinsale Road Cork and , Industrial building at Ballycurreen
Construction of and ESB substation and transformer base.
Ballycurreen Industrail Estate , Ballycurreen , Co. Cork
Construction of an ESB substation and transformer base.
Ballycurreen Industrial Estate , Ballycurreen , Co. Cork
Permission to construct side extension to existing commercial unit, together with dock leveller and associated site works.
Montara House , Ballycurreen Industrial Estate , Kinsale Road
Permission to construct side extension to existing commercial unit, together with dock leveller and associated site works.
Montara House , Ballycurreen Industrial Estate , Kinsale Road
Permission to demolish part of the existing kitchen and construct new kitchen to the rear and side of existing dwelling and all associated site works.
No. 94 , Curragh Woods , Frankfield
Permission for the installation of a 199kWp rooftop solar photovoltaic array (984m2) on the roof of the existing Avoncourt factory building consisting of 585 No. 340Wp JA Solar panels mounted directly on the roof surface, electrically connected to the existing electrical plant room via 4 no. Solis inverters mounted on the wall of the existing plant room, to the rear of the existing factory building and all associated work.
Avoncourt Packaging Ltd , Unit 2 , Ballycurreen Industrial Estate
Permission for the installation of a 215.8 kWp Rooftop Solar Photovoltaic Array extension (circa 1,020m2), consisting of circa 520 No. panels, to an existing Rooftop Solar Photovoltaic Array (circa 1032m2), with the proposed panels mounted directly on the roof surface, electrically connected to the existing electrical plant room via 4 No. inverters mounted on the wall of the existing plant room, located to the rear of the existing factory building and all associated work.
Avoncourt Packaging Ltd , Unit 2 Ballycurreen Industrial Estate , Airport Road
To construct a temporary 500 m2 single storey computer equipment storage building for a 3 year period including all ancillary site works
Ballycurreen Industrial Estate , Ballycurreen , Kinsale Road
Permission to extend the temporary permission Planning Ref 18/07022 as granted to Construct a temporary 500 m2 Single storey Computer Equipment storage building for a further 3 year period including all ancillary site works
Balycurreen Industrial Estate , Ballycurreen , Kinsale Road
Planning a project of your own?
Find out in two minutes whether you need planning permission. It's free, and based on the exempted development regulations.
Do I Need Permission?