2247
CONDITIONALSligo - Sligo County Council
Proposed Development
Development consisting of the following works: 1. Retention of existing first floor attic conversion from storage to habitable rooms along with 3 roof lights to front and 1 one rear, 2. Replace 2 no. existing Velux windows to the rear with 2 flat roof dormers with windows suitable for escape and rescue, 3. Include one additional Velux window to front, 4. Construction of a flat roof extension to rear of house 35m2 floor area, 5. Elevational changes to existing south side gable to form new window and door opening for access to newutility room along with all associated site works
View the full application file on the council's planning portal →Application Timeline
Application received
11 Feb 2022
Decision: CONDITIONAL
6 Apr 2022
Decision due
7 Apr 2022
Grant issued
13 May 2022
Application Details
- Location
- 9 Kingsfort , Ballintogher , Co Sligo
- Applicant
- N/A
- Application Type
- RETENTION
- Planning Authority
- Sligo County Council
- Site Area
- 0.086 ha
- Floor Area
- 37 sq m
- Residential Units
- 3
Timeline
- Registration Date
- 11 February 2022
- Status
- APPLICATION FINALISED
- Decision
- CONDITIONAL
- Decision Date
- 6 April 2022
- Grant Date
- 13 May 2022
- Permission Expires
- 12 May 2027
Location
Planning Applications Nearby
What the council has granted and refused around this site is the best guide to how a similar application will fare.
Development consisting of the following works: 1. Demolition of existing shelter structure located to the east of existing school; 2. Construction of a new classroom and link corridor extension to the east and north sides of the existing school including signage; 3. Provision of alterations to staffroom block to west side of existing school; 4. Elevation changes to the existing school; 5. Provision of new access ramp and external steps to front (north) of school and provision of a new playground to rear (south) of school; 6. Connection of foul drainage to existing public sewer, connection of surface water into existing system on site and all associated site works
Kingsfort , Ballintogher , Co Sligo
for development consisting of the construction of an additional temporary prefab type classroom, connect to all public services and construct a new school sign on the front gable of the school together with all associated ancillary works
Kingsfort , Ballintogher , Co. Sligo
Development consisting of the construction of five, two storey detached dwelling houses on existing vacant sites located to the east of existing house number six.
Kingsfort Manor , Ballintogher , Co Sligo
(a) construct one detached two storey dwelling house on vacant site number one, (b) construct two semi-detached two storey dwelling houses on vacant site number thirty six and thirty seven and (c) construct one detached two storey dwelling house on vacant site number thirty eight
Kingsfort Manor Housing Estate , Ballintogher , Co. Sligo
development consisting of the construction of 1 no. two-storey detached dwelling house and 2 no. two-storey semi-detached dwelling houses on vacant sites located to the south of house no. 35. Permission is also sought for completion of the public footpath, road, vehicle turning area and site services adjacent to these proposed dwelling houses
Kingsfort Manor , Ballintogher , Co. Sligo
PP & PR - development consisting of the following: retention of a change of use from commercial use to a child care facility and all ancillary services. We also apply for full planning permission to construct a car parking facility on the site
Tiratick , Ballintogher , Co Sligo
We, St. Michaels GAA Club, wish to apply for full planning permission for the following works: 1. permission to upgrade the existing clubhouse from a single storey to a two-storey structure, the extended building will encompass larger changing room facilities on the ground floor. 2. The 1st floor will include a meeting room, kitchen area, viewing balcony and additional toilet facilities. 3. To construct 2 no. ground floor single storey extensions to the existing clubhouse to include additional toilet facilities and storage facilities. 4. To construct a pedestrian pathway around the perimeter of the facility to include low level lighting. 5. To construct a pedestrian pathway to connect both existing GAA pitches. 6. To construct spectator perimeter fencing on both pitches. 7. To fit solar panels to the roof of the new 2 storey building. 8. To construct a new spectator stand, scoreboard and all ancillary works. The works are located at St. Michaels GAA Club, Kingsfort, Ballintogher, Co. Sligo.
St. Michaels GAA Club , Kingsfort Ballintogher , Co. Sligo
development consisting of the construction of a domestic garage together with all associated ancillary works
Altvelid , Ballintogher , Co. Sligo
1. Construction of a new storey and a half type dwelling 2. Construction of a new wastewater treatment plant and percolation area in accordance with EPA Code of Practice 3. Construction of a new vehicular entrance and access road to serve dwelling 4. All associated site development works
Rathgeean , Ballintogher , Co. Sligo
Development consisting of (1) construction of a storey and half dwelling house with a single storey wing attached to the east, (ii) installation of a wastewater treatment system and percolation area, (iii) lowering the ground and setting back roadside boundary to the east of the new entrance to improve road safety and sightlines and, (iv) carrying out of all ancillary site works
Woodfield Td. , Ballintogher East ED. , Co Sligo
Planning a project of your own?
Find out in two minutes whether you need planning permission. It's free, and based on the exempted development regulations.
Do I Need Permission?