2251977
CONDITIONALDonegal - Donegal County Council
Proposed Development
EXTENSION AND RENOVATIONS TO EXISTING DWELLING HOUSE, TOGETHER WITH CONNECTION TO EXISTING SERVICES AND ALL ASSOCIATED WORKS
View the full application file on the council's planning portal →Application Timeline
Application received
12 Dec 2022
Further information requested
2 Feb 2023
Further information received
3 Feb 2023
Decision: CONDITIONAL
23 Feb 2023
Decision due
2 Mar 2023
Grant issued
4 Apr 2023
Application Details
- Location
- NO 1 PORT RONAN , ARDMALIN MALIN HEAD , LIFFORD PO
- Applicant
- N/A
- Application Type
- PERMISSION
- Planning Authority
- Donegal County Council
- Site Area
- 0.051 ha
Timeline
- Registration Date
- 12 December 2022
- Status
- APPLICATION FINALISED
- Decision
- CONDITIONAL
- Decision Date
- 23 February 2023
- Grant Date
- 4 April 2023
- Permission Expires
- 3 April 2028
Location
Planning Applications Nearby
What the council has granted and refused around this site is the best guide to how a similar application will fare.
(1) CONSTRUCTION OF AN EXTENSION TO AN EXISTING RESIDENTIAL DWELLING TO THE SIDE WITH NEW SUN ROOM (2) REPLACEMENT OF EXISTING ROOFLIGHTS WITH LARGER VELUX ROOFLIGHTS
2 PORTRONAN , MALIN HEAD , LIFFORD PO
(1) CONSTRUCTION OF AN EXTENSION TO AN EXISTING RESIDENTIAL DWELLING TO THE SIDE WITH NEW SUN ROOM (2) REPLACEMENT OF EXISTING ROOFLIGHTS WITH LARGER VELUX ROOFLIGHTS
2 PORTRONAN , MALIN HEAD , LIFFORD PO
(1) CONSTRUCTION OF AN EXTENSION TO AN EXISTING RESIDENTIAL DWELLING TO THE SIDE WITH NEW SUN ROOM (2) REPLACEMENT OF EXISTING ROOFLIGHTS WITH LARGER VELUX ROOFLIGHTS
2 PORTRONAN , MALIN HEAD , LIFFORD PO
DOMESTIC GARAGE, TOGETHER WITH ALL ASSOCIATED WORKS
NO. 3 PORT RONAN , ARDMALIN , MALIN HEAD
(1) DEMOLITION OF EXISTING DWELLING HOUSE (2) CONSTRUCTION OF A NEW DWELLING HOUSE WITH ASSOCIATED SITE WORKS TO INCLUDE THE REPLACEMENT OF THE EXISTING WASTEWATER TREATMENT SYSTEM. A NATURA IMPACT STATEMENT (NIS) ACCOMPANIES THIS APPLICATION
ARDMALIN , MALIN , LIFFORD PO
DEMOLITION OF EXISTING DWELLING HOUSE TO ALLOW FOR THE CONSTRUCTION OF A NEW DWELLING HOUSE WITH ASSOCIATED SITE WORKS TO INCLUDE THE REPLACEMENT OF THE EXISTING WASTEWATER TREATMENT SYSTEM. A NATURA IMPACT STATEMENT (NIS) ACCOMPANIES THIS APPLICATION
ARDMALIN , MALIN , LIFFORD PO
CONSTRUCTION OF A NEW DWELLING, DOMESTIC GARAGE AND WASTEWATER TREATMENT SYSTEM TOGETHER WITH ALL ASSOCIATED SITE WORKS
ARDMALIN , MALIN HEAD , CO. DONEGAL
EXTENSION TO EXISTING DWELLING AND ALL ASSOCIATED SITE WORKS
ARDMALIN , MALIN HEAD , CO. DONEGAL
CONSTRUCTION OF AN EXTENSION TO EXISTING GARAGE AT GROUND FLOOR LEVEL AND DEVELOPMENT OF A PLAY AREA TO THE FIRST FLOOR
PORTRONAN , ARDMALIN , MALIN HEAD LIFFORD PO
ERECTION OF 2 NO. GLAMPING PODS WITH WASTEWATER TREATMENT SYSTEM & PERCOLATION AREA, CAR PARKING, CONNECTION TO EXISTING PUBLIC SERVICES AND ALL ASSOCIATED WORKS
MIDDLETOWN , ARDMALIN , MALIN HEAD
Planning a project of your own?
Find out in two minutes whether you need planning permission -- free, based on the exempted development regulations.
Do I Need Permission?