2252060
CONDITIONALDonegal - Donegal County Council
Proposed Development
ERECTION OF A DWELLING HOUSE WITH WASTE WATER TREATMENT SYSTEM AND DOMESTIC GARAGE INCLUDING ALL OTHER ASSOCIATED SITE DEVELOPMENT WORKS
View the full application file on the council's planning portal →Application Timeline
Application received
21 Dec 2022
Further information requested
23 Feb 2023
Further information received
28 Jun 2023
Decision: CONDITIONAL
20 Jul 2023
Decision due
25 Jul 2023
Grant issued
23 Aug 2023
Application Details
- Location
- TIEVEBANE , BURNFOOT , LIFFORD PO
- Applicant
- N/A
- Application Type
- PERMISSION
- Planning Authority
- Donegal County Council
- Site Area
- 1.15 ha
- Floor Area
- 435 sq m
- Residential Units
- 1
Timeline
- Registration Date
- 21 December 2022
- Status
- APPLICATION FINALISED
- Decision
- CONDITIONAL
- Decision Date
- 20 July 2023
- Grant Date
- 23 August 2023
- Permission Expires
- 22 August 2028
Location
Planning Applications Nearby
What the council has granted and refused around this site is the best guide to how a similar application will fare.
SITE DEVELOPMENT WORKS AND PERMISSION FOR ERECTION OF AN AGRICULTURAL MACHINERY STORAGE SHED AND ALL OTHER ASSOCIATED SITE DEVELOPMENT WORKS
ROCKSTOWN , TIEVEBANE , BURNFOOT
CONSTRUCTION OF A STOREY AND A HALF DWELLING COMPLETE WITH ENTRANCE ONTO COUNTY ROAD VIA EXISTING ENTRANCE AND ACCESS LANE, EFFLUENT TREATMENT PLANT AND PERCOLATION AREA, PRIVATE WELL WATER SUPPLY AND ALL ASSOCIATED SITE DEVELOPMENT WORKS
ROCKSTOWN , TIEVEBANE , BURNFOOT
CONSTRUCTION OF A STOREY AND A HALF DWELLING COMPLETE WITH ENTRANCE ONTO COUNTY ROAD VIA EXISTING ENTRANCE AND ACCESS LANE, EFFLUENT TREATMENT PLANT AND PERCOLATION AREA, PRIVATE WELL WATER SUPPLY AND ALL ASSOCIATED SITE DEVELOPMENT WORKS. A NATURA IMPACT STATEMENT (NIS) WILL FORM PART OF THIS APPLICATION
ROCKSTOWN , TIEVEBANE , BURNFOOT
COMPLETION OF MULTIPLE RESIDENTIAL DEVELOPMENT APPROVED UNDER PLANNING REF NOS: 05/4780, 06/71954, 07/71842 AND EXTENSION DURATION OF PERMISSION APPROVED UNDER 10/70356 & 10/70357
ROCKSTOWN , TIEVEBANE , BURNFOOT
(1) DEMOLITION OF BLOCKWORK OF PARTIALLY COMPLETED DWELLINGS AND (2) REBUILD AND COMPLETION OF MULTIPLE RESIDENTIAL DEVELOPMENT, APPROVED UNDER PLANNING REF. NOS. 05/4780, 06/71954, 07/71842 AND EXTENDED DURATION OF PERMISSION APPROVED UNDER REF. NOS. 10/70356 & 10/70357. A NATURA IMPACT STATEMENT (NIS) ACCOMPANIES THIS APPLICATION
ROCKSTOWN , TIEVEBANE , BURNFOOT LIFFORD PO
(1) DEMOLITION OF BLOCKWORK OF PARTIALLY COMPLETED DWELLINGS AND (2) REBUILD AND COMPLETION OF MULTIPLE RESIDENTIAL DEVELOPMENT, APPROVED UNDER PLANNING REF. NOS. 05/4780, 06/71954, 07/71842 AND EXTENDED DURATION OF PERMISSION APPROVED UNDER REF. NOS. 10/70356 & 10/70357. A NATURA IMPACT STATEMENT (NIS) ACCOMPANIES THIS APPLICATION
ROCKSTOWN , TIEVEBANE BURNFOOT , LIFFORD PO
(1) DEMOLITION OF BLOCKWORK OF 5 NO. PARTIALLY COMPLETED DWELLINGS AND (2) REBUILD AND COMPLETION OF SAME 5 NO. RESIDENTIAL DWELLINGS APPROVED UNDER PLANNING REF. NOS. 05/4780, 06/71954, 07/71842 AND EXTENDED DURATION OF PERMISSION APPROVED UNDER REF. NOS. 10/70356 & 10/70357. A NATURA IMPACT STATEMENT (NIS) ACCOMPANIES THIS APPLICATION
ROCKSTOWN , TIEVEBANE , BURNFOOT LIFFORD PO
DEMOLITION OF BLOCKWORK OF PARTIALLY COMPLETED DWELLINGS AND PERMISSION FOR REBUILD AND COMPLETION OF MULTIPLE RESIDENTIAL DEVELOPMENT APPROVED UNDER PLANNING REF. NOS. 05/4780, 06/71954, 07/71842 AND EXTENDED DURATION OF PERMISSION APPROVED UNDER PLANNING REF. NOS. 10/70356 & 10/70357. A NATURA IMPACT STATEMENT (NIS) ACCOMPANIES THIS APPLICATION
ROCKSTOWN , TIEVEBANE , BURNFOOT LIFFORD PO
COMPLETION OF MULTIPLE RESIDENTIAL DEVELOPMENT APPROVED UNDER PLANNING REF NOS. 05/4780, 06/71954, 07/71842 AND EXTENSION OF DURATION PERMISSION APPROVED UNDER 10/70356 & 10/70357
ROCKSTOWN , TIEVEBANE , BURNFOOT LIFFORD P.O.
COMPLETION OF MULTIPLE RESIDENTIAL DEVELOPMENT APPROVED UNDER PLANNING REF NOS. 05/4780, 06/71954, 07/71842 AND EXTENSION OF DURATION PERMISSION UNDER 10/70356 & 10/70357
ROCKSTOWN , TIEVEBANE , BURNFOOT LIFFORD P.O.
Planning a project of your own?
Find out in two minutes whether you need planning permission. It's free, and based on the exempted development regulations.
Do I Need Permission?