22546
REFUSEDClare - Clare County Council
Proposed Development
of 2 electronic signs and associated works
View the full application file on the council's planning portal →Application Timeline
Application received
20 Jun 2022
Decision: REFUSED
11 Aug 2022
Decision due
14 Aug 2022
Appeal submitted
6 Sept 2022
Appeal decided: CONDITIONAL
22 Nov 2023
Grant issued
28 Nov 2023
Application Details
- Location
- Deerpark West Td , Deerpark Industrial Estate , Ennistymon Co Clare
- Applicant
- N/A
- Application Type
- RETENTION
- Planning Authority
- Clare County Council
- Site Area
- 1.36 ha
Timeline
- Registration Date
- 20 June 2022
- Status
- APPLICATION FINALISED
- Decision
- REFUSED
- Decision Date
- 11 August 2022
- Grant Date
- 28 November 2023
- Permission Expires
- 27 November 2028
An Coimisiún Pleanála Appeal
- Appeal Reference
- ABP-314544-22
- Decision
- CONDITIONAL
- Submitted
- 6 September 2022
- Decided
- 22 November 2023
Location
Planning Applications Nearby
What the council has granted and refused around this site is the best guide to how a similar application will fare.
for 1) to construct an external rainscreen canopy and crane to loading bay 2) extend southern road to include a new truck turning head area and retaining wall structure 3) realign front car parking and walls to allow for traffic movement 4) modification to existing planning ref: P18-645 by omission of windows on proposed factory extension south elevation, and raising of proposed extension parapet height by approx. 1000mm 5) RETENTION PERMISSION of new relief road and pathway to north of existing buildings 6) RETENTION PERMISSION of new ground floor window on easterly facade 7) new window to office block (east elevation), including all associated site works and services
Deerpark West Td , Deerpark Industrial Estate , Ennistymon
for 1) change of use from creche to offices, 2) construct an extension to the factory including tracking for mobile gantry crane, 3) extend car parking to rear, 4) construct new sub-station and water storage tank, 5) remove existing water storage tank and water storage pond including all associated site works services
Deerpark West Td , Deepark Industrial Est , Ennistymon
to demolish existing loading bay and to construct an extension along with associated site works and services
Deerpark West Td. , Deerpark Industrial Estate , Ennistymon Co. Clare
for additional parking spaces and associated site works, all within existing site boundaries
Deerpark West , Ennistymon , Co. Clare
for the following development: for the construction of a Multi Use Games Area (MUGA) with associated site fencing, netting, artificial surface, 4 No. 10m floodlighting poles, associated fittings and all associated ancillary site works
Ennistymon Community School , Lahinch Road , Deerpark West Ennistymon Co. Clare
for a development comprising of: 8 no. industrial units, an entrance, connection to services and all associated site works
Deerpark West , Ennistymon , Co Clare
for development at this subject site ( site area 4.9 hectares ). The development will consist of: (a) The Demolition of the existing single storey Scoil Mhuire Post Primary School Buildings ( 1694m2 ) and the existing two storey Scoil Mhainchín Primary School Buildings ( 878m2 ); (b) Construction of new 3-storey Post Primary School with connected Sports Hall ( 8678m2 ), 2-storey Primary School ( 1341m2 ), new internal road with set-down areas for buses and cars, ESB substation, switch room, ancillary store rooms, boiler house, car parking ( 96 Nr spaces ), ball courts, landscaping and associated site works; (c) New site entrance from Lahinch Road ( N67 ) and new boundary treatment; (d) New vehicular traffic lane and associated road works at the junction of proposed site entrance and Lahinch Road ( N67 ), Ennistymon, Co. Clare. The total development area is circa 10,224 m2
Lahinch Road , Deerpark West , Ennistymon
1) The refurbishment of original convent building and the construction of an extension to same to include 12 two bedroom apartments with a doctors room, day room and laundry facilities. 2) The construction of a new three storey building to the rear of existing convent building consisting of 18 two bedroom apartments. 3) The demolition of outbuilding to rear of existing convent building. All in connection with the development of a retirement village.
The Convent , Lahinch Rd , Ennistymon
for the following works, (A) change the use of the development granted under existing permission P19-333 as a retirement village and presently under construction, to use as residential, (B) change the internal layout, including minor elevational changes to the refurbished convent building as granted, and presently under construction, to provide 13 apartments made up of 1 x 1 bedroom apartment, 10 x 2 bed apartments and 2 x 3 bed apartments and (C) change the site boundaries and layout as granted, all with associated site works
The Old Convent , Lahinch Road , Ennistymon
of a two storey rear extension, being 19.5sqM to ground floor, and 19.5sqM to first floor, total 39sqM and replacement grey colour windows with site works and alterations to services
No 19 Woodmount , Ennistymon , Co Clare