Proposed Development

the construction of 92 No. residential units. The residential units will consist of; 30 No. 2 storey 4-Bed semi-detached houses, 44 No. 2 storey 3-Bed semi-detached houses, 12 No. 1 storey 2-Bed semi-detached bungalows, 4 No. 2 storey 3-bed end terrace houses, 2 No. 2 storey 2-bed mid terrace houses. The proposed development will also include new internal roadways and footpaths, a proposed new distributor road to the east and south-east of proposed development, pedestrian/ cycle access off the existing Tyone Road to the south-west of the site, vehicular access from the existing Ormond Drive to the south-east of the site, new vehicular and pedestrian access, new boundary treatments, landscaping, drainage, site services including new ESB kiosk, attenuation ponds and foul water pumping station and all ancillary site works, all at Tyone, Nenagh, Co. Tipperary. A Natura Impact Statement (NIS) accompanies this application.

View the full application file on the council's planning portal →

Application Timeline

  1. Application received

    22 Apr 2022

  2. Further information requested

    1 Jun 2022

  3. Further information received

    4 Aug 2022

  4. Decision: CONDITIONAL

    10 Jan 2023

  5. Decision due

    14 Jan 2023

  6. Grant issued

    13 Feb 2023

Application Details

Location
Tyone , Nenagh , Co. Tipperary
Applicant
N/A
Application Type
PERMISSION
Planning Authority
Tipperary County Council
Site Area
4.722 ha
Floor Area
9675.300000000007 sq m
Residential Units
92

Timeline

Registration Date
22 April 2022
Status
APPLICATION FINALISED
Decision
CONDITIONAL
Decision Date
10 January 2023
Grant Date
13 February 2023
Permission Expires
12 February 2028

Location

Loading map...

Planning Applications Nearby

What the council has granted and refused around this site is the best guide to how a similar application will fare.

130m
21877N/A17 Jun 2021

the construction of 67 no. residential units, a new single storey crèche, single storey health centre and a 3 storey, 90 bed nursing home - the residential units will consist of: 5 no. 1-Bed semi-detached bungalows, 5 no. 2 Bed Semi-detached bungalows, 13 no. 2 bed mid-terrace bungalows, 2 no. 2 storey 4-bed semi-detached houses, 2 no. 2 storey 4-bed mid terrace houses, 14 no. 2 storey 3 bed semi-detached houses, 14 no. 2 storey 2 bed mid-terrace houses and 1 no. apartment building consisting of: 8 no. 1-bed apartments and 4 no. 2-bed apartments over 2 storeys, located as follows, (2 no. 2 bed and 4 no. 1 bed apartments on ground floor, 2 no. 2 bed and 4 no. 1 bed apartments on first floor), the proposed development will also include new internal roadways and footpaths, a proposed new distributor road to the north and east of proposed develpment, pedestrian/cycle access off the existing Tyone Road to the west of the site, vehicular access from the existing Ormond Drive, south of proposed site, new vehicular and pedestrian access, new boundary treatments, landscaping, drainage, site servides including new ESB Medium Voltage (MV) substation building and all ancillary site works

Tyone , Nenagh , Co Tipperary

145m
21959CONDITIONAL2 Jul 2021

the construction of 67 no. residential units, a new single storey crèche, single storey health centre and a 3 storey, 90 bed nursing home. The residential units will consist of: 5 no. 1-bed semi-detached bungalows, 5 no. 2 bed semi-detached bungalows, 13 no. 2 bed mid-terrace bungalows, 2 no. 2 storey 4-bed semi-detached houses, 2 no. 2 storey 4-bed mid terrace houses, 14 no. 2 storey 3 bed semi-detached houses, 14 no. 2 storey 2 bed mid-terrace houses and 1 no. apartment building consisting of: 8 no. 1-bed apartments and 4 no. 2-bed apartments over 2 storeys, located as follows, (2 no. 2 bed and 4 no. 1 bed apartments on ground floor, 2 no. 2 bed and 4 no. 1 bed apartments on first floor), the proposed development will also include new internal roadways and footpaths, a proposed new distributor road to the north and east of proposed development, pedestrian/cycle access off the existing Tyone Road to the west of the site, vehicular access from the existing Ormond Drive, south of proposed site, new vehicular and pedestrian access, new boundary treatments, landscaping, drainage, site services including new ESB Medium Voltage (MV) substation building and all ancillary site works

Tyone , Nenagh , Co. Tipperary

145m
26101N/A27 Jul 2026

the construction of 67 no. residential units, a new single storey crèche, single storey health centre and a 3 storey, 90 bed nursing home. The residential units will consist of: 5 no. 1-bed semi-detached bungalows, 5 no. 2 bed semi-detached bungalows, 13 no. 2 bed mid-terrace bungalows, 2 no. 2 storey 4-bed semi-detached houses, 2 no. 2 storey 4-bed mid terrace houses, 14 no. 2 storey 3 bed semi-detached houses, 14 no. 2 storey 2 bed mid-terrace houses and 1 no. apartment building consisting of: 8 no. 1-bed apartments and 4 no. 2-bed apartments over 2 storeys, located as follows, (2 no. 2 bed and 4 no. 1 bed apartments on ground floor, 2 no. 2 bed and 4 no. 1 bed apartments on first floor), the proposed development will also include new internal roadways and footpaths, a proposed new distributor road to the north and east of proposed development, pedestrian/cycle access off the existing Tyone Road to the west of the site, vehicular access from the existing Ormond Drive, south of proposed site, new vehicular and pedestrian access, new boundary treatments, landscaping, drainage, site services including new ESB Medium Voltage (MV) substation building and all ancillary site works

Tyone , Nenagh , Co. Tipperary

162m
21812N/A4 Jun 2021

the construction of 67 no. residential units, a new single storey crèche, single storey health centre and a 3 storey, 90 bed nursing home. The residential units will consist of: 5 no. 1-Bed semi-detached bungalows, 5 no. 2 Bed Semi-detached bungalows, 13 no. 2 bed mid-terrace bungalows, 2 no. 2 storey 4-Bed semi-detached houses, 2 no. 2 storey 4-Bed mid terrace houses, 14 no. 2 storey 3 bed semi-detached houses, 14 no. 2 storey 2 bed mid-terrace houses and 1 no. apartment building consisting of: 8 no. 1-Bed apartments and 4 no. 2-Bed apartments over 2 storeys, located as follows, (2 no. 2 bed and 4 no. 1 bed apartments on ground floor, 2 no. 2 bed and 4 no. 1 bed apartments on first floor). The proposed development will also include new internal roadways and footpaths, a proposed new distributor road to the north and east of proposed develpment, pedestrian/cycle access off the existing Tyone Road to the west of the site, vehicular access from the existing Ormond Drive, south of proposed site, new vehicular and pedestrian access, new boundary treatments, landscaping, drainage, site servides including new ESB "Medium Voltage (MV)" substation building and all ancillary site works

Tyone , Nenagh , Co Tipperary

174m
19600960CONDITIONAL30 Aug 2019

the construction of a part two storey, part single storey 50 bed residential community nursing care unit (c. 4510m² total gross floor area) including; a courtyard garden; a production kitchen and laundry; ancillary support accommodation; an enclosed gated service yard incorporating a generator, electrical substation; waste marshalling stores and office area with a screened mechanical and electrical plant area at first floor. The development will also consist of the upgrade to an existing vehicular entrance and access road off Ormond Drive into the site, installation of new services, the provision of a sustainable urban drainage system and new access roads and footpaths with associated hard and soft landscaping and parking for 70 cars and the reinstatement of an existing pedestrian entrance to the south west of the site to provide access to the site from the Tyone Road through the Hospital grounds and the provision of a controlled emergency access way and pedestrian entrance from the hospital into the site involving the formation of two new openings in the existing rubble masonry boundary wall to the south of the site. The boundary wall is within the curtilage of a protected structure Ref No 121.

Tyone , Nenagh , Co. Tipperary

175m
19600919N/A20 Aug 2019

the construction of a part two storey, part single storey 50 bed residential community nursing care unit (c. 4510m² total gross floor area) including; a courtyard garden; a production kitchen and laundry; ancillary support accommodation; an enclosed gated service yard incorporating a generator, electrical substation; waste marshalling stores and office area with a screened mechanical and electrical plant area at first floor. The development will also consist of the upgrade to an existing vehicular entrance and access road off Ormond Drive into the site, installation of new services, the provision of a sustainable urban drainage system and new access roads and footpaths with associated hard and soft landscaping and parking for 70 cars and the reinstatement of an existing pedestrian entrance to the south west of the site to provide access to the site from the Tyone Road through the Hospital grounds and the provision of a controlled emergency access way and pedestrian entrance from the hospital into the site involving the formation of two new openings in the existing rubble masonry boundary wall to the south of the site. The development also includes the reinstatement of an existing pedestrian access way to the south west of the site linking to the site from the Tyone Road through the hospital grounds and the provision of a controlled emergency access way from the hospital into the site involving the formation of two openings in the existing rubble masonry boundary wall to the south of the site, adjacent to Nenagh General Hospital. The boundary wall is within the curtilage of a protected structure Ref No 121.

Tyone , Nenagh , Co. Tipperary

192m
19600835N/A29 Jul 2019

the construction of a part two storey, part single storey 50 bed residential community nursing care unit including; a courtyard garden; a production kitchen and laundry; ancillary support accommodation; an enclosed gated service yard incorporating a generator, electrical substation ; waste marshalling stores and office area and a screened mechanical and electrical plant area at first floor. The development will also consist of the upgrade of an existing vehicular entrance and access road off Ormond Drive into the site, installation of new services, the provision of a sustainable urban drainage system and new access roads and footpaths with associated hard and soft landscaping and parking for 70 cars. The development also includes the reinstatement of an existing pedestrian access way to the south west of the site linking to the site from the Tyone Road through the hospital grounds and the provision of a controlled emergency access way from the hospital into the site involving the formation of two openings in the existing rubble masonry boundary wall to the south of the site. The boundary wall is within the curtilage of a protected structure Ref No 121.

Ormond Drive , Nenagh , Co. Tipperary

206m
18600530CONDITIONAL27 Apr 2018

the change of use of an existing workshop to a Day Centre for adults with disabilities

Tyone , Nenagh , Co. Tipperary

234m
201149N/A7 Oct 2020

(a) to replace the existing sub standard onsite septic tank and soakpit with a proprietary domestic sewage pumping system and rising main to discharge into the public sewer via an existing 150mm diameter private sewer in neighbouring property by consent of the owner (b) to remove and modify a portion of the existing stone road boundary wall of an adjoining property in the ownership of, and with the consent of Iarnrod Eireann to improve sightlines, together with the associated siteworks

Nenagh South , Thurles Road , Nenagh

234m
2561239REFUSED2 Dec 2025

the demolition of an existing boundary wall, extension of existing hard surfaced area and erection of new boundary wall to the rear of surgery

Mount Carmel , Tyone , Nenagh