2272
CONDITIONALLeitrim - Leitrim County Council
Proposed Development
relocate the slatted/dry bedded agricultural building that was previously granted under ref 20221 to a new revised location on the landholding and all associated ancillary works
View the full application file on the council's planning portal →Application Timeline
Application received
5 May 2022
Further information requested
27 Jun 2022
Further information received
20 Oct 2022
Decision: CONDITIONAL
17 Nov 2022
Decision due
23 Nov 2022
Grant issued
21 Dec 2022
Application Details
- Location
- Tawnahoney , Drumkeeran , Co Leitrim
- Applicant
- N/A
- Application Type
- PERMISSION
- Planning Authority
- Leitrim County Council
Timeline
- Registration Date
- 5 May 2022
- Status
- APPLICATION FINALISED
- Decision
- CONDITIONAL
- Decision Date
- 17 November 2022
- Grant Date
- 21 December 2022
- Permission Expires
- 20 December 2027
Location
Planning Applications Nearby
What the council has granted and refused around this site is the best guide to how a similar application will fare.
construct a slatted/dry bedded agricultural building and all associated ancillary works
Tawnahoney , Drumkeeran , Co Leitrim
1. To retain the new domestic site entrance; 2. To carry out a single storey extension to the rear of the existing domestic dwelling; 3. To carry out alterations to the existing elevations; 4. To upgrade the existing wastewater treatment system to the current EPA code of Practice and all ancillary works
Tawnylea , Drumkeeran , Co. Leitrim
1. 2 no. agricultural sheds. 2. 3 no. domestic sheds. 3. An equestrian riding arena with a fenced enclosure around the full perimeter. 4. An agricultural entrance onto the public road.
Tawnylea , Drumkeerin , Co. Leitrim
amendment to the development permitted under Leitrim County Planning Register Reference P.19/26 for the construction of a culvert crossing to an existing stream along the access to consented wind turbine no. 18.The planning application will be accompanied by a Natura Impact Statement (NIS)
Tullynamoyle and Gowlaun , Killarga , Co Leitrim
1. To construct a single storey flat roof domestic extension. 2. To make elevational changes to both side gables and the front elevation of the existing domestic dwelling. 3. To upgrade a wastewater treatment system to EPA code of practice and all ancillary works.
Gowlaun , Drumkeeran , Co. Leitrim
(a) to demolish an existing rear extension; (b) to construct a storey and a half type extension to the rear of the existing dwelling and all ancillary works.
Derrintawny , Drumkeeran , Co Leitrim
A thirty year planning permission for an additional four (4) wind turbines to an existing fifteen (15) turbine windfarm. The proposed development will constitute the following: (a) the construction of four (4) wind turbines with hub heights of up to 92 metres with an overall height of up to 150 metres to blade tip.; (b) the construction of crane hardstand areas located beside each turbine; (c) the construction of two (2) 20 Kv substation buildings with associated electrical plant, equipment and security fences; (d) Internal windfarm underground cabling; (e) the construction of new site access tracks and the provision of upgraded access roads; (f) Installation of a drainage system for the proposed hardstand and road areas; (g) Underground grid connection approximately five (5) Km in length, predominantly along existing public road network; (h) all associated site development and ancillary works. The planning application is accompanied by an Environmental Impact Assessment Report (EIAR) and by a Natura Impact Statement in lieu of a thirty year planning permission for an additional six(6) wind turbines to an existing fifteen (15) turbine windfarm in the townlands of Lackagh, Tullynamoyle, Gowlaun and Altavra, Killarga, County Leitrim. The grid connection to Corderry Substation will be located in the townlands of Knockacullion, Tawnahoney, Lisnagowan, Tawnylea, Derrintawny, Shivdelagh, Cloonagh, Drumduffy and Corderry, Killarga County Leitrim. The proposed development will constitute the following: (a) the construction of six (6) wind turbines with hub heights of up to 92 metres with an overall height of up to 150 metres to blade tip.; (b) the construction of crane hardstand areas located beside each turbine; (c) the construction of two (2) 20 Kv substation buildings with associated electrical plant, equipment and security fences; (d) Internal windfarm underground cabling; (e) the construction of new site access tracks and the provision of upgraded access roads; (f) Installation of a drainage system for the proposed hardstand and road areas; (g) Underground grid connection approximately five (5) Km in length, predominantly along existing public road network; (h) all associated site development and ancillary works. The planning application is accompanied by an Environmental Impact Assessment Report (EIAR) and by a Natura Impact Statement.
townlands detailed above ,
construct a domestic extension and all ancillary works
Altavra , Drumkeerin , Co Leitrim
Planning a project of your own?
Find out in two minutes whether you need planning permission. It's free, and based on the exempted development regulations.
Do I Need Permission?