2310
N/ACavan - Cavan County Council
Proposed Development
for demolition of existing garage and construction of 3 storey split level building consisting of 8 No. Units (with 4 no. 1 Bed units & 4 no. 2 Bed Duplex units), connection to existing public services and all ancillary works
View the full application file on the council's planning portal →Application Details
- Location
- Townparks E.D. , Ballyhaise , Co Cavan
- Applicant
- N/A
- Application Type
- PERMISSION
- Planning Authority
- Cavan County Council
Timeline
- Registration Date
- 18 January 2023
- Status
- INCOMPLETED APPLICATION
- Decision
- N/A
Location
Planning Applications Nearby
What the council has granted and refused around this site is the best guide to how a similar application will fare.
for demolition of existing garage and construction of 3 storey split level building consisting of 8 No. Units (with 4 no. 1 bed units & 4 no. 2 bed duplex units), connection to existing public services and all ancillary works. Significant further information and revised plans have been submitted.
Townparks E.D. Ballyhaise , Ballyhaise , Co. Cavan
to erect an 18m high monopole telecommunications support structure together with antennas, dishes and ancillary works and remove the existing no. 2 timber commumications poles
eir Exchange , Townparks Td Ballyhaise , Co. Cavan
to retain and continue a change of use of previously approved office to beauty salon
Cutting Edge Hair & Beauty Salon , Townparks , Ballyhaise
for the demolition of part of existing public house to form new site entrance, demolition of existing outbuildings, erection of 28 no. fully serviced dwellings comprising of 14 no. 2 bed semi-detached two storey dwellings & 14 no. 3 bed semi-detached two storey dwellings, connection to public services, new service road, and all ancillary works. A Natura Impact Statement (NIS) will be submitted to the Planning Authority with this application
Townparks , Ballyhaise , Co. Cavan
for completion of phase two of previously approved development works (granted approval under Planning Reg No 20/57). Phase One works have been completed and Phase Two shall comprise of the following: (a) New 2 story Club Rooms including 4 no. dressing rooms, meeting rooms, office space, and ancillary accommodation; (b) upgrading and widening of existing access road with a short retaining gabion stone wall section, entrance & public footpaths & lighting; (c) turnstiles and access gates; and (d) all connections and ancillary site works
Annalee Park , Townparks and Raheg Ballyhaise , Co. Cavan
for (a) New 2 story Club Rooms including 4 no. dressing rooms, meeting rooms, office space, gym space and ancillary accommodation; (b) upgrading and widening of existing access road with a short retaining gabion stone wall section, entrance & public footpaths & lighting; (c) flood lit synthetic grass training pitch and hurling wall; (d) turnstiles and access gates; (e) provision of all associated surface water and foul drainage services and connections and all ancillary site works
Annalee Park , Townparks and Raheg , Ballyhaise
to erect; single story extension and erection of granny flat to rear of dwelling, alterations to existing elevations and all ancillary works
Townparks (E.D. Ballyhaise) , Ballyhaise , Co Cavan
for erection of first floor extension to side of existing dwelling, alterations to existing elevations, retention of additional floor area to granny flat (previously approved under planning permission no. 20/65) and all ancillary works
Townparks (E.D. Ballyhaise) , Ballyhaise , Co Cavan
to (A) increase height of existing first floor walls of dormer dwelling to form two storey dwelling and amend rood design, (B) erect a single storey porch & bay window to front of dwelling, (c) erect a two storey extension of front and side of dwelling, (D) erect single storey extensions to side and rear of dwelling, (E) make alterations to existing floor pland and elevations and (F) all ancillary site works
Townparks , Ballyhaise , Co Cavan
erect detached domestic garage. Significant further information and revised plans have been submitted.
Townparks , Ballyhaise , Co Cavan
Affected by this application?
Submissions can be made for 5 weeks from the date the application was received. Only material planning grounds count -- build a valid submission letter in minutes.
Make a Submission or ObjectionPlanning a project of your own?
Find out in two minutes whether you need planning permission -- free, based on the exempted development regulations.