Proposed Development

the importation, recovery & recycling of soil, stone, concrete and brick materials by sorting, crushing and screening for dispatch/re-use in construction and engineering projects. The annual tonnage proposed for acceptance at the Site shall not exceed 25,000 tonnes per annum. A Natura Impact Statement will be submitted to the Planning Authority with the application

View the full application file on the council's planning portal →

Application Timeline

  1. Application received

    8 Mar 2023

  2. Further information requested

    28 Apr 2023

  3. Further information received

    11 Oct 2023

  4. Decision due

    7 Nov 2023

  5. Decision: REFUSED

    7 Nov 2023

  6. Appeal submitted

    4 Dec 2023

  7. Appeal decided: REFUSED

    10 Feb 2025

Application Details

Location
Ballynamona , Summerhill , Co Meath
Applicant
N/A
Application Type
PERMISSION
Planning Authority
Meath County Council
Site Area
2.16 ha

Timeline

Registration Date
8 March 2023
Status
APPLICATION FINALISED
Decision
REFUSED
Decision Date
7 November 2023

An Coimisiún Pleanála Appeal

Appeal Reference
ABP-318595-23
Decision
REFUSED
Submitted
4 December 2023
Decided
10 February 2025

Location

Loading map...

Planning Applications Nearby

What the council has granted and refused around this site is the best guide to how a similar application will fare.

0m
23207N/A28 Feb 2023

the importation, recovery & recycling of soil, stone, concrete and brick materials by sorting, crushing and screening for dispatch/re-use in construction and engineering projects. The annual tonnage proposed for acceptance at the Site shall not exceed 25,000 tonnes per annum.A Natura Impact Statement will be submitted to the Planning Authority with the application

Basketstown and Ballynamona , Summerhill , Co Meath

47m
2660093N/A26 Jan 2026

planning permission for the development of an aggregate recycling plant at Ballynamona, Summerhill, Co. Meath. The Proposed Project consists of the importation, recovery and recycling of soil, stone, concrete and brick type materials by sorting, crushing and screening for dispatch/re-use in construction and engineering projects. The annual tonnage proposed for acceptance at the Site shall not exceed 25,000 tonnes per annum. A Waste Facility permit will be applied for to Meath County Council

Ballynamona , Summerhill , Co. Meath

225m
22509N/A14 Apr 2022

EXTENSION OF DURATION OF PLANNING APPLICATION TA160678- (1) The importation of subsoil & topsoil for the purpose of land reclamation with a consequential benefit for an agricultural activity. (2) The importation, recovery & recycling of concrete & brick materials by crushing & screening for dispatch/re-use in construction & engineering projects. The development will include a proposed truck wheel-wash, weighbridge, mobile crushing/screening plant, aggregate storage bays, portable office/chemical toilet, new vehicular entrance, access road & ancillary site development works (the application is accompanied by an Environmental Impact Statement & the activity will be subject of an application to the Environmental Protection Agency for a Waste Licence. Significant further information/revised plans submitted on this application

Basketstown & Ballynamona , Summerhill , Co Meath

398m
2561226CONDITIONAL11 Nov 2025

construction of a single-storey flat-roof rear extension with a raised rooflight to serve as a sunroom

Glenbeg Lodge Galtrim , Summerhill , Co. Meath

479m
2660930N/A24 Jul 2026

the development will consist of the reinstatement of the existing quarry at Ballynamona, by importing 223,000 tonnes per annum of soil and stone over a 14-year period, with the final profiling and landscaping completed in the following year. The annual soil and stone intake will comprise approximately 128,000 tonnes of non-waste materials notified as by-product under the Article 27 By Product Regulation and up to a maximum of 95,000 tonnes of inert soil and stone classified as waste. The quantity of non-waste material may vary from year to year, while the volume of waste material shall not exceed 95,000 tonnes in any calendar year. The total annual intake of soil and stone will not exceed 223,000 tonnes in any given year. The proposed development also allows for the provision of an additional wheel-wash, two weighbridges, site/weighbridge office and welfare facilities (c. 52sq. m), a waste acceptance quarantine area and a proprietary sanitary wastewater treatment system, and all associated works within an overall application area of 23.8 ha. The reinstatement will require a Soil Recovery Licence issued by the Environmental Protection Agency (EPA). The planning application is accompanied by an Environmental Impact Assessment Report

Ballynamona , Summerhill , County Meath

482m
2660371N/A2 Apr 2026

The development will consist of reinstatement of the existing quarry at Ballynamona, by importing 223,000 tonnes of soil and stone over a 14-year period, with the final profiling and landscaping completed in the following year. The annual soil and stone intake will comprise approximately 128,000 tonnes of non-waste materials notified as a by-product under the Article 27 By Product Regulation and approximately 95,000 tonnes of inert soil and stone classified as waste. The proposed development also allows for the provision of an additional wheel-wash (39 sq.m), two weighbridges (each 94 sq.m), site/weighbridge office and welfare facilities (50sq.m), a quarantine area (45 sq.m) and a proprietary sanitary wastewater treatment system. All associated works within an overall application area of 23.8 ha.

Ballynamona Townland , Summerhill , County Meath

482m
2660530N/A6 May 2026

the development will consist of the reinstatement of the existing quarry at Ballynamona, Summerhill, Co Meath by importing 223,000 tonnes per annum of soil and stone over a 14-year period, with the final profiling and landscaping completed in the following year. The annual soil and stone intake will comprise approximately 128,000 tonnes of non-waste materials notified as by-product under the Article 27 By Product Regulation and up to a maximum of 95,000 tonnes of inert soil and stone classified as waste. The quantity of non-waste material may vary from year to year, while the volume of waste material shall not exceed 95,000 tonnes in any calendar year. The total annual intake of soil and stone will not exceed 223,000 tonnes in any given year. The proposed development also allows for the provision of an additional wheel-wash, two weighbridges, site/weighbridge office and welfare facilities (c. 52sq. m), a waste acceptance quarantine area and a proprietary sanitary wastewater treatment system, and all associated works within an overall application area of 23.8 ha. The reinstatement will require a Soil Recovery Licence issued by the Environmental Protection Agency (EPA). The planning application is accompanied by an Environmental Impact Assessment Report

Ballynamona Townland , Summerhill , County Meath

728m
2460283CONDITIONAL25 Apr 2024

the development will consist of the construction of a dwelling, new entrance, waste water treatment system and percolation area and all associated site works. Significant further information/revised plans submitted on this application

Basketstown , Summerhill , co. meath

748m
TA190196CONDITIONAL25 Feb 2019

a 78m2 single storey rear extension to the rear of the existing property for additional kitchen/living space with associated site works

Ballinamona , Galtrim , Summerhill Co. Meath

789m
TA170574CONDITIONAL23 May 2017

a gallery at the west end of the church with toilet accommodation underneath and the installation of a waste water treatment unit and percolation area. Galtrim Church is a Protected Structure. Significant further information/revised plans submitted on this application

Galtrim Church , Galtrim Kiltale , Co. Meath

Planning a project of your own?

Find out in two minutes whether you need planning permission. It's free, and based on the exempted development regulations.

Do I Need Permission?