Proposed Development
Permission for the construction of a new substation building within a car park permitted under Council Ref: 22/41121 to cater for additional electrical vehicle (EV) charging points at Hollyhill Industrial Estate, Hollyhill, Cork, T23YK84. The proposed substation building will include a medium voltage switch room, electrical distribution room and all associated site development works
View the full application file on the council's planning portal →Application Timeline
Application received
14 Dec 2023
Decision: CONDITIONAL
15 Feb 2024
Decision due
16 Feb 2024
Grant issued
25 Mar 2024
Application Details
- Location
- Hollyhill Industrial Estate , Kilmore Heights , Hollyhill
- Applicant
- N/A
- Application Type
- PERMISSION
- Planning Authority
- Cork City Council
- Site Area
- 0.0994 ha
Timeline
- Registration Date
- 14 December 2023
- Status
- APPLICATION FINALISED
- Decision
- CONDITIONAL
- Decision Date
- 15 February 2024
- Grant Date
- 25 March 2024
Location
Planning Applications Nearby
What the council has granted and refused around this site is the best guide to how a similar application will fare.
Permission for the construction of a four storey over partial lower ground floor level office building providing office space, meeting rooms, staff welfare, service areas and all ancillary site development works. The proposed office building will be constructed within the existing carpark and will connect to an existing office building known as ‘HH4’ to the southeast by way of a cantilevered link corridor at first floor level resulting in façade amendments and internal reconfigurations to the existing ‘HH4’ building. A central pedestrian avenue will also be provided between the existing and proposed building. The proposed development includes a single storey commute hub building providing bicycle/scooter parking, storage and staff facilities serving the wider Apple campus, a single storey energy centre building and 2 no. single storey security huts. A new surface car park on lands to the north of the David McCarthy Road is proposed to accommodate the relocation of the displaced car parking spaces resultant from the construction of the proposed office building and provision of additional car parking spaces, in addition to the reconfiguration of the existing car park to the south of the David McCarthy Road. The proposed carpark to the north of the David McCarthy Road will be linked with the main campus via a pedestrian underpass under David McCarthy Road and a covered pedestrian pathway. 2 no. new vehicular accesses are proposed off the David McCarthy Road. Ancillary site development works include hard and soft landscaping, boundary treatments, lighting, public realm upgrades, signage, plant and photovoltaic panels and all other site development works above and below ground. An Environmental Impact Assessment Report has been prepared in respect of the planning application.
Hollyhill Industrial Estate , Tadgh Barry Road and lands , adjacent to David McCarthy Road and
Permission for the construction of a new substation building consisting of a medium voltage switchroom and electrical distribution room and all associated site development works.
Hollymount 2 , (The Former Banta Site) , Hollymount Industrial Estate
Permission for an extension to the entrance lobby of an existing office building and all ancillary site development works.
Hollyhill Industrial Estate , Tadhg Barry Road , Holyhill
Permission for modifications to the existing warehouse building and all ancillary site development works at the Former Banta site, Hollymount Industrial Estate, Hollyhill, Cork. The proposed development consists of a change of use of part of the existing warehouse building to use as a testing and measurement facility with ancillary office use and modifications to the building consisting of: the construction of a new mezzanine floor; and modifications to the façade including (1) New windows at first floor level, relocation of doors and opening; and (2) The installation of extract fans and associated ducts. The proposed site development works include: (a) The removal of 1 no. existing shelter; (b) The relocation of an existing generator; (c) Installation of a bicycle rack; (d) The construction of an external plant enclosure comprising of a back up generator with associated diesel tank, air chiller with associated circulation pumps, 2 no. air handling units, 4 no. external condenser units and gas storage tanks; and (e) An external plant enclosure comprising of an air handling unit.
The Former Banta Site , Hollymount Industrial Estate , Hollyhill
Permission for modifications to and the expansion of the existing plant compound permitted by Ref. No. 21/39966 and all associated site development works at Hollymount 2, Hollymount Industrial Estate, Hollyhill, Cork. The proposed works consist of: (1) The construction of an expanded plant compound and the installation of (A) Condenser units, (B) 1 no. air handling unit, (C) 3 no. dry air coolers, and (D) The construction of 2 no. pump enclosures. Permission is also sought for the retention of modifications to the existing plant compound permitted by Ref. No. 21/39966 comprising of an increase in the area of the plant compound and the provision of 2 no. pump enclosures within the compound.
Hollymount 2 , Hollymount Industrial Estate , Hollyhill
Permission for development at Lands adjacent to David McCarthy Road and Nash's Boreen, Knocknacullen West, Hollyhill, Cork. The development will consist of: An extension to the existing staff car park to provide additional parking spaces and associated internal roads. The development will be accessed via the permitted vehicular access points off David McCarthy Road permitted under Planning Reference: 22/41121. The development also includes boundary treatments, service gate, drainage and all ancillary site development works.
Lands adjacent to , David McCarthy Road and , Nashs Boreen Knocknacullen West
Permission is sought by ESB Telecoms Ltd of 43 Merrion Square East, Dublin 2 for the continued use of the existing 36 metre high communications structure, carrying radio equipment, with associated ground-mounted equipment (exempted development) shared with other licensed operators within an existing 2.4 metre high palisade fence, following on from the expiry of the parent permission LPA Ref: 12/35370 and permission to attach additional antennae and dishes to allow for future third party co-location at ESB's existing Hollyhill 38kV Substation, Hollyhill Road, Cork.
ESB's Hollyhill , 38kV Substation , Hollyhill Road
Permission for modifications to the elevation of an existing building and all ancillary site development works at Hollyhill Industrial Estate, Tadhg Barry Road, Holyhill, Cork. The proposed modifications consist of upgrades to the elevation of an existing office building including the addition of new windows at ground and first floor levels facing into the existing service yard. Permission is also sought for the retention of modifications to two loading bays including a ground floor extension and associated modifications to the elevations.
Hollyhill Industrial Estate , Tadhg Barry Road , Holyhill
Permission for the construction of a new substation building within the existing car park to cater for additional electric car charging points at the Hollyhill Industrial Estate
Hollyhill Industrial Estate , Tadhg Barry Road , Hollyhill
Permission for alterations within the existing lower service yard consisting of the construction of a 110.5m2 single storey extension with a rooftop plant enclosure to an existing production building and all ancillary site development works.
Hollyhill Industrial Estate , Tadgh Barry Road , Holyhill