23454
CONDITIONALClare - Clare County Council
Proposed Development
to renovate and extend existing dwelling house, connect to new wastewater treatment system and carry out all ancillary site works
View the full application file on the council's planning portal →Application Timeline
Application received
22 Aug 2023
Decision: CONDITIONAL
13 Oct 2023
Decision due
16 Oct 2023
Grant issued
21 Nov 2023
Application Details
- Location
- Cullen , Newmarket-on-Fergus , Co Clare
- Applicant
- N/A
- Application Type
- PERMISSION
- Planning Authority
- Clare County Council
Timeline
- Registration Date
- 22 August 2023
- Status
- APPLICATION FINALISED
- Decision
- CONDITIONAL
- Decision Date
- 13 October 2023
- Grant Date
- 21 November 2023
- Permission Expires
- 20 November 2028
Location
Planning Applications Nearby
What the council has granted and refused around this site is the best guide to how a similar application will fare.
To construct a single dwelling house, advanced water treatment system and ancillary site works.
Culleen , Newmarket-on-fergus , Co. Clare
for the construction of an entrance, dwelling house, garage, driveway, advanced waste water treatment system together with all ancillary site development works and services
Culleen , Newmarket on Fergus , Co. Clare
for development - the development consists of the construction of an new entrance onto public road, the construction of a road from that entrance of a road from that entrance using inert soil and stone class (170504) and using concrete class (170101) into farmyard and associated site works
Culleen , Drumline , Co Clare
for development which will consist of 1. Land reclamation for agricultural purposes by levelling ground between two contours using imported inert soil and stone class (170504) concrete class (170101) for roadways, together with the associated site works. 2 RETENTION permission of land reclamation of existing lands for agricultural use under planning references 20/712 and 21/347
Ballycasey Beg , Culleen , Newmarket-on-Fergus Co. Clare
the development consists of the construction of a slatted unit and associated site works
Culleen , Drumline , Co Clare
for the construction of a detached single storey garage with single storey granny flat appended, connection to existing wastewater treatment system and percolation area, and all ancillary site and landscaping works
The Orchard , Drumline , Newmarket-on-Fergus Co Clare
for an extension to dwelling house and carrying out of ancillary works
Killulla Stud , Killulla , Newmarket-on-Fergus Co Clare
to erect signage to logistics (warehouse and distribution) building
Shannon Free Zone , Ballycasey Beg , Smithstown Shannon
to construct logistics (warehouse and distribution) building with photo-voltaic arrays on the roof with supporting offices, signage, flag poles, HGV, car and cycle-parking, service yard, new vehicular entrance/exit, connection to existing estate sewers, ESB sub-station, landscaping, boundary treatment and all ancillary site works necessary to facilitate the proposed development
East Park Shannon Free Zone , Ballycasey Beg , Smithstown Shannon
for the development this site at the townlands of Mogullaan, Crossagh, Rathlaheen South, Culleen, Drumline and Ballycasey Beg, Co Clare. Planning Permission is sought for a duration of 10 years, with an operational life of 35 years from the date of commissioning. The proposed development comprises the construction and operation of a solar photovoltaic (PV) farm on a site of approximately 95 hectares. The project includes: (i) Ground-mounted solar arrays supported by steel frames, with an internal network cable facilitating connection to the Drumline 110kV substation. An internal network cable will be installed to enable an under-the-fence connection from the onsite transformer compound to the adjacent substation. The transformer compound will include an Independent Power Producer (IPP) building, a 110kV transformer, and an 18-metre-high lightning monopole mast. (ii) Underground electrical cabling and ducting, security fencing, CCTV stands. (iii) New internal access tracks and site entrance. (iv) Site drainage. (v) All ancillary site development works and apparatus. A Natura Impact Statement will also be submitted to the Planning Authority with this application
Mogullaan Crossagh , Rathlaheen South Culleen , Drumline and Ballycasey Beg Co. Clare
Planning a project of your own?
Find out in two minutes whether you need planning permission. It's free, and based on the exempted development regulations.
Do I Need Permission?