2350427
CONDITIONALDonegal - Donegal County Council
Proposed Development
INSTALLATION OF A BULK LPG STORAGE TANK AND ROAD TANKER FILLING FACILITIES, FIRE SUPPRESSION GANTRY WITH ASSOCIATED WATER STORAGE TANK AND PUMP HOUSE AND ANCILLARY SITE SERVICES. A NATURA IMPACT STATEMENT (NIS) ACCOMPANIES THIS APPLICATION
View the full application file on the council's planning portal →Application Timeline
Application received
31 Mar 2023
Decision: CONDITIONAL
18 May 2023
Decision due
25 May 2023
Appeal submitted
14 Jun 2023
Appeal decided: CONDITIONAL
12 Apr 2024
Application Details
- Location
- BUNNAGEE , LETTERKENNY , CO. DONEGAL
- Applicant
- N/A
- Application Type
- PERMISSION
- Planning Authority
- Donegal County Council
- Site Area
- 0.385 ha
Timeline
- Registration Date
- 31 March 2023
- Status
- APPLICATION FINALISED
- Decision
- CONDITIONAL
- Decision Date
- 18 May 2023
- Permission Expires
- 11 April 2029
An Coimisiún Pleanála Appeal
- Appeal Reference
- ABP-317354-23
- Decision
- CONDITIONAL
- Submitted
- 14 June 2023
- Decided
- 12 April 2024
Location
Planning Applications Nearby
What the council has granted and refused around this site is the best guide to how a similar application will fare.
INSTALLATION OF A BULK LPG STORAGE TANK AND ROAD TANKER FILLING FACILITITES, FIRE SUPPRESSION GANTRY WITH ASSOCIATED WATER STORAGE TANK AND PUMP HOUSE AND ANCILLARY SITE SERVICES
BUNNAGEE , LETTERKENNY , CO. DONEGAL
(1) ERECTION OF A WASTE TRANSFER STATION CONTAINED WITHIN THE EXISTING BUILDING (1,856 M2) HAVING AN ANNUAL WASTE INTAKE OF UP TO 24,500 TONNES/YEAR, (2) CONSTRUCTION OF A CIVIC AMENITY BRING CENTRE (408 M2) TO THE EAST OF THE EXISTING BUILDING AND ALL ASSOCIATED SITE WORKS AND SERVICES TO ACCOMMODATE THE CIVIC AMENITY SITE AND WASTE TRANSFER STATION AND (3) ALL ASSOCIATED SITE WORKS AND SERVICES, FOOTPATHS, UPGRADING OF SITE ACCESS AND BOUNDARY FENCE, BICYCLE PARKING RACKS, ADDITIONAL CAR PARKING SPACES AND LANDSCAPING
MILK ISLE , BONAGEE , LETTERKENNY
CONTINUATION OF USE FOR A PERIOD OF THREE YEARS OF; 8NO. FUEL DISPENSING PUMPS ON 3NO. PUMP ISLANDS FOR SALE OF FUEL TO PUBLIC, BOUNDARY FENCING AND EGRESS ROAD
BONAGEE , LETTERKENNY , CO. DONEGAL
(1) CONSTRUCTION OF A NEW BUILDING TO PROVIDE A WAREHOUSE STORAGE FACILITY WITH A FLOOR AREA OF 5,753 SQ/M, (2) CONSTRUCTION OF A NEW SEPARATE OFFICE BUILDING TO SERVE THE DEVELOPMENT WITH A FLOOR AREA OF 167.4 SQ/M, (3) PROVISION OF A NEW FOUL SEWER CONNECTION TO AN EXISTING SEWAGE TREATMENT SYSTEM LOCATED IN THE APPLICANTS ADJOINING YARD, (4) PROVISION OF STORM WATER DRAINAGE INCLUDING THE INSTALLATION OF A STORM WATER INTERCEPTOR, (5) PROVISION FOR A NEW WATER CONNECTION TO THE OFFICE BUILDING FROM THE ADJOINING PUBLIC WATER MAIN, (6) PROVISION OF ONSITE CARPARKING, (7) ALL ASSOCIATED SITE DEVELOPMENT WORKS. THIS APPLICATION IS ACCOMPANIED BY A NATURA IMPACT STATEMENT (NIS)
BUNNAGEE , LETTERKENNY , CO DONEGAL
(1) CONSTRUCTION OF A NEW BUILDING TO PROVIDE A WAREHOUSE STORAGE FACILITY WITH A FLOOR AREA OF 5,753 SQ/M, (2) CONSTRUCTION OF A NEW SEPARATE OFFICE BUILDING TO SERVE THE DEVELOPMENT WITH A FLOOR AREA OF 167.4 SQ/M, (3) PROVISION OF A NEW FOUL SEWER CONNECTION TO AN EXISTING SEWAGE TREATMENT SYSTEM LOCATED IN ADJOINING YARD, (4) PROVISION OF STORM WATER DRAINAGE INCLUDING THE INSTALLATION OF A STORMWATER INTERCEPTOR, (5) PROVISION FOR A NEW WATER CONNECTION TO THE OFFICE BUILDING FROM THE ADJOINING PUBLIC WATER MAIN, (6) PROVISION OF ON-SITE CARPARKING, (7) ALL ASSOCIATED SITE DEVELOPMENT WORKS
BUNNAGEE , LETTERKENNY , CO DONEGAL
CHANGE OF USE FROM A WAREHOUSE TO A KIDS PLAY CENTRE, CONNECTION TO EXISTING SERVICES AND ALL ASSOCIATED WORKS
BUNAGEE , LETTERKENNY , LETTERKENNY PO
CHANGE OF USE OF EXISTING MANUFACTURING BUILDING TO STORAGE/WAREHOUSING
BUNNAGEE , LETTERKENNY , CO. DONEGAL
ERECTION OF A NEW SPECTATOR STAND & 2 NO. DUGOUTS AND RETENTION PERMISSION FOR EXISTING SCOREBOARD / ADVERTISING BOARD
GLEBE , LETTERKENNY , LETTERKENNY PO
(1) CHANGE OF USE FROM STORAGE TO LIGHT INDUSTRIAL, (2) CHANGE OF USE FROM STORAGE TO COMMERCIAL KITCHEN WITH CAFE ADJACENT, (3) SEMI-ENCLOSED EXTERNAL SEATING AREA, WITH TIMBER AND PERSPEX CANOPY, TO SIDE OF EXISTING CAFE, (4) CONSTRUCTION OF FIRST FLOOR LEVEL TO ACCOMMODATE ASSOCIATED OFFICE, STAFF TOILETS, STAFF CANTEEN AND STORAGE, (5) MODIFICATIONS TO FENESTRATION, INCLUDING ADDITIONAL, REPOSITIONING AND REMOVAL (AS DIFFERS FROM THOSE GRANTED UNDER REF NO. 10/80101), (6) SIGNAGE ON FRONT ELEVATION AND BOUNDARY FENCE, (7) 2 NO. STORAGE CONTAINERS FOR STORING VEHICLES AND (8) EXTENSION OF EXISTING COMMERCIAL YARD/HARD-STANDING TO PROVIDE ADDITIONAL CARPARKING, AND PERMISSION FOR INSTALLATION OF SEWAGE TREATMENT SYSTEM AND ALL ASSOCIATED SITE WORKS
BUNNAGEE , LETTERKENNY , CO. DONEGAL
(1) CHANGE OF USE FROM (A) STORAGE TO LIGHT INDUSTRIAL AND (B) STORAGE TO COMMERCIAL KITCHEN WITH CAFE ADJACENT; (2) SEMI ENCLOSED EXTERNAL SEATING AREA WITH TIMBER AND PERSPEX CANOPY TO SIDE OF EXISTING CAFE; FIRST FLOOR LEVEL TO ACCOMMODATE ASSOCIATED OFFICE, STAFF TOILETS, STAFF CANTEEN AND STORAGE (3) MODIFICATION TO FENESTRATION INCLUDING ADDITIONAL REPOSITIONING AND REMOVAL (DIFFERS FROM THOSE GRANTED UNDER REF NO. 10/80101) (4) SIGNAGE ON FRONT ELEVATION AND BOUNDARY FENCE (5) 2 NO. OF STORAGE CONTAINERS FOR STORING VEHICLES (5) EXTENSION OF COMMERCIAL YARD/ HARD-STANDING TO PROVIDE ADDITIONAL CAR PARKING AND COMMISSION FOR INSTALLATION OF SEWAGE TREATMENT SYSTEM AND ALL ASSOCIATED SITE WORKS
BUNNAGEE , LETTERKENNY , CO. DONEGAL